Professional Documents
Culture Documents
Instruction Manual
J1 & J2 Adjustable Clamps
Horizontal Installation
Assembly Instructions.
This instruction manual has been produced to help the installer to understand the safe and proper
way to assemble the J-SAFE Big Base Freestanding Temporary Edge Protection System.
If you are in any doubt , please contact J-SAFE directly in one of the following ways.
Index
Safe plant and equipment and a safe method of Safeguard his own safety and that of others who
work may be affected by his actions.
Information, Instruction, Training and Supervision. Co-operate with the employer to help them comply
A safe place of work with safe access and egress. with their legal duties.
Competence
It is important that the operative has the ability to carry out the installation without
harming the health or safety of themselves or anyone else and the ability to recognise an
unsafe situation arising out of what he or someone else is doing- and act on it.
Medical Conditions
It is important that the installer does not suffer from a medical condition that could affect their
safety whiclt erecting, dismantling or during normal use of the system.
Compliance
It is the Hirer’s responsibility to ensure that the equipment is erected and used in accordance with
its design function.
Instruction Manual
J1 & J2 Adjustable Clamps Horizontal
Installation
Assembly Instructions.
Parts diagram
4
2
1
3
1
1 Clamping arma
2 Threaded stem
3 Wing nut
4 Post holder
If you are in doubt please consult J-SAFE where a suitable system can
be proposed.
Instruction Manual
J1 & J2 Adjustable Clamps Horizontal
Installation
Assembly Instructions.
Step 1
Open the clamp arms until the are spaced adequately to fit over
the structure.
Instruction Manual
J1 & J2 Adjustable Clamps Horizontal
Installation
Assembly Instructions.
Step 2
Tighten the wing nut by hand until it grips the structure and remains vertical.
Instruction Manual
J1 & J2 Adjustable Clamps Horizontal
Installation
Assembly Instructions.
Step 3
Step 4
Step 5
The mesh barrier is installed onto two posts by lifting the top
horizontal surface over the posts and sliding it down so that the posts
retain it at the top.
The vertical; mesh face is always positioned on the inside of the posts.
Step 6
Step 7
Wrap a 9mm nylon cable-tie around the Post and the vertical
mesh of two barriers just above the barrier toe-board and pull
until tight.
Repeat this action on every post .
Trainig register
Date
Project
Components
Trainees