Completed( Plan in Completed Schedule in Plan in Completed in 2017

Items Total(m) Per.


m) July(m) in July August 2017(m) 2017(m) Per.

FUEL TRENCH 14285 8987 63% 527 358 413 9170 4013 44%
W.S 17995 15952 89% 133 373 180 3699 1704 46%
W.S (OASIS) 2246 0 0% 198 0 0 2246 0 0%
TSE 7286 7130 98% 201 71 130 804 648 81%
C.W (MAIN LINE) 4189 3720 89% 430 164 25 921 452 49%
C.W (OASIS LINE) 2216 0 0% 373 0 0 2216 0 0%
C.W(Valve Chamber) 26 0 0% 10 0 0 26 0 0%
11KV 13207 8376 63% 818 301 0 11458 8346 73%
415V 22302 16023 72% 483 378 490 15636 9271 59%
415V (OASIS) 2680 0 0% 118 0 0 2680 0 0%
FBS 21909 16010 73% 872 499 795 13673 5336 39%
FBS (OASIS) 2200 677 31% 127 0 0 2200 137 6%
TELECOM 17272 11707 68% 541 204 598 12173 4041 33%
TELECOM (OASIS) 2080 0 0% 0 0 0 2080 115 6%
SANITARY 9770 9528 98% 0 0 0 312 70 22%
S.W 32712 30956 95% 181 256 2548 792 31%
STREET LIGHTING 45614 19687 43% 805 805 1600 26882 955 4%
LANDSCAPE LIGHTING(Qty) 1062 627 59% 120 77 120 1062 627 59%