Landscape Construction Schedule in December
Landscape Construction Schedule in December
NOVEMBER DECEMBER
Total finished
Sr. Activity Total quantity Total Finished
percentage
plan Finished per-centage plan
1 Soil replacement for palm trees in LRR&LDR (Nos.) 6530 4874 75% 238 225 95% 251
2 Mass excavation and backfill in LRR&LDR (M2) 158695 124021 78% 3239 762 24% 6284
3 Mass Planting Shrubs (M2) 158695 38885 25% 54030 24720 46% 29310
5 Middle island concrete (m2) 29307 27474 94% 267 267 100% 1336
7 Gravel mulch (m2) 58246 17310 30% 4954 4954 100% 8718
9 Small Berms And Main Berm Tree pit (Nos) 105 73 184 252% 152
10 Small Berms And Main Berm Soil Replacement (m2) 5281 1103 3603 327% 4549
Type-1 16 Paver Type1 installtion(M2) 225229 145113 64% 15763 3863 25% 25401
Type-2 17 Paver Type2 installtion(M2) 76654 47700 62% 7270 7096 98% 17272
Type-3 18 Paver Type3 installtion(M2) 71303 33687 47% 5308 1164 22% 8224
Type-5 20 Paver Type5 installtion(M2) 54822 9223 17% 5853 5586 95% 4826
T
21 Formation(Type-1.2.3.4.5) 430624 321915 75% 26761 20012 75% 40447
O
L
T
A 22 Paver (Type-1.2.3.4.5) 430624 237509 55% 34194 17709 52% 55723
Average 75%