LANDSCAPE CONSTRUCTION SCHEDULE IN DECEMBER-2019

NOVEMBER DECEMBER
Total finished
Sr. Activity Total quantity Total Finished
percentage
plan Finished per-centage plan

1 Soil replacement for palm trees in LRR&LDR (Nos.) 6530 4874 75% 238 225 95% 251

2 Mass excavation and backfill in LRR&LDR (M2) 158695 124021 78% 3239 762 24% 6284

3 Mass Planting Shrubs (M2) 158695 38885 25% 54030 24720 46% 29310

4 Plant tree(Nos.) 4527 1483 33%

5 Middle island concrete (m2) 29307 27474 94% 267 267 100% 1336

6 Backfilling of berm (NOS) 281 105 37%

7 Gravel mulch (m2) 58246 17310 30% 4954 4954 100% 8718

8 Gravel dressing (m2) 295007 0 0%

9 Small Berms And Main Berm Tree pit (Nos) 105 73 184 252% 152

10 Small Berms And Main Berm Soil Replacement (m2) 5281 1103 3603 327% 4549

11 Concrete beam(m) 131000 93659 71% 5071 4504 89% 4737

12 TOTAL INSTALLATION BOUDLERS (Nos.) - - -


B
O
U 13 KWG/CUP-2 BOUDLERS TYPE-7(Nos.) - - -
D
L 14 KWG/CUP-2 BOUDLERS TYPE-8(Nos.) - - -
E
R
15 KWG/CUP-2 BOUDLERS TYPE-9(Nos.) - - -

Type-1 16 Paver Type1 installtion(M2) 225229 145113 64% 15763 3863 25% 25401

Type-2 17 Paver Type2 installtion(M2) 76654 47700 62% 7270 7096 98% 17272

Type-3 18 Paver Type3 installtion(M2) 71303 33687 47% 5308 1164 22% 8224

Type-4 19 Paver Type4 installtion(M2) 2616 1786 68%

Type-5 20 Paver Type5 installtion(M2) 54822 9223 17% 5853 5586 95% 4826

T
21 Formation(Type-1.2.3.4.5) 430624 321915 75% 26761 20012 75% 40447
O
L
T
A 22 Paver (Type-1.2.3.4.5) 430624 237509 55% 34194 17709 52% 55723

Please refer to separated schedule for hard landscape paver ;

Average 75%