Professional Documents
Culture Documents
net/publication/302589674
CITATIONS READS
0 13,519
3 authors, including:
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Sajjad Al-Amshawee on 10 May 2016.
PREPARED BY
LECTURERS
Page | ii
Chapter 5 Risk Management
5.1 Risk Management ……………………………………………………………… 16
5.2 Risk Management Approach …………………………………………………….. 16
5.3 Risks Identifying …………………………………………………………………. 17
5.3.1 Initial Risks ……………………………………………………………………… 17
5.3.2 Monitor and Control Risks ………………………………………………………..18
5.3.3 Procurement Risks ………………………………………………………………..18
5.3.4 Delay Risks ………………………………………………………………………18
5.3.5 Engineering Staff Risks ………………………………………………………….. 19
5.3.6 Cost Risks ………………………………………………………………………..19
5.3.7 Equipment Risks ……………………………………………………………………19
5.4 Probability of the risk occurring …………………………………………….….. 19
5.5 Impact of risk on the project ……………………………………………………. 20
5.6 The possible risks that may affect the project objectives ……………………….. 21
5.7 Mitigation of the possible risks …………………………………………………... 22
Page | 3
Chapter 7 Organizational Structure
7.1 Roles and Responsibilities ……………………………………….. 29
Appendices
1. Simple Process flow diagram of dry Cement manufacturing ………………….35
2. More detailed Flow sheet about dry cement manufacturing ………………. 35
3. Plant location ………………………………………..………………… 36
4. Plant location factor …………………………………………………………....36
5. Plant Layout ……………………………………………………………37
6. Definitions of Plant layout symbols …...37
7. Table shows you the activities with their durations ‘done by Microsoft office… 38
Tables
Code descriptions Page
1-1 number of plants in each province 1
and their production capacities
2-1 Scope assumptions 5
Page | 4
5-2 Rating impact of the risks 20
5-4 Mitigation of the possible risks 22
5-3 The possible risks that may affect 21
the project objectives
7-1 Roles and Responsibilities 29
7-2 Roles and Responsibilities with 31
Communication requirements,
expectations and classification
influence.
8-1 Communications Management 32
References …………………………………………………………………………… 39
Page | 5
Executive Summary
Cement is a strategic commodity, essential for Canada's economic security and
infrastructure renewal and expansion. Cement industry is an important
economic presence in communities across Canada. The Canadian cement
industry is comprised of 15 fully operational cement production plants which
consist of 14 gray clinker production plants.
The feasibility study conducted by the project team indicates that the national
demand for cement products is increasing. This finding is supported by the
approval of infrastructure projects (roads, bridges, and others) as well as the
growing need for cement used in housing developments. The studies,
conducted by several sources, indicate that if the production of cement does
not increase, the supply will be insufficient during upcoming years.
The Cement Plant project aims to construct a new cement production plant
with two production lines, each with a production capacity of 3,500 tons of
clinker per day. The total production capacity of the plant for different kinds
of cement is planned to be 10,000 tons.
Page | 6
Chapter 1
Introduction
1.1 HISTORICAL BACKGROUND
The term cement is commonly used to refer to powdered materials which develop strong
adhesive qualities when combined with water. These materials are more properly known
as hydraulic cements. Gypsum plaster, common lime, hydraulic limes, and Portland
cements are the more common hydraulic cements, with Portland cement being the most
important in construction. Cement was first invented by the Egyptians. Cement was later
reinvented by the Greeks and the Babylonians who made their mortar out of lime. Later,
the Romans produced cement from an ash found in all of the volcanic areas of Italy, by
mixing the ash with lime. Cement is a fine grayish powder which, when mixed with water,
forms a thick paste. When this paste is mixed with sand and gravel and allowed to dry it
is called concrete. About ninety-nine percent of all cement used today is Portland cement.
The name Portland cement is not a brand name. This name was given to the cement by
Joseph Aspin of Leeds, England who obtained a patent for his product in 1824. The
concrete made from the cement resembled the color of the natural limestone quarried on
the Isle of Portland in the English Channel. The balance of cement used today consists of
masonry cement, which is fifty percent Portland cement and fifty percent ground lime rock.
Table (1-1) number of plants in each province and their production capacities.
Page | 7
Concrete outperforms wood as a construction material, and won't burden building owners
With constant repair and maintenance costs. Versatile, long-lasting, and durable concrete is
a cost-effective, sustainable choice for both residential and commercial buildings. The
demand for cement and its products is increasing due to following advantages:
3. Safe: Concrete is safe, secure, and healthy for building occupants. Being an inert
construction material, concrete does not burn. It also does not feed rot and mildew. It
does not off-gas any volatile organic compounds and provides excellent indoor air
quality. Superior quality of construction helps prevent the entry of pollen, dust and
other airborne pollutants.
The Cement Plant project aims to construct a new cement production plant with two
production lines, each with a production capacity of 3,500 tons of clinker per day. The total
Production capacity of the plant for different kinds of cement is planned to be 10,000 tones.
This plant will especially produce white cement because there is only one plant in Canada
That produces this type of cement. The purpose of the Cement Plant project is to increase
cement production capacity to supply the national demand for cement and its products. By
Completing this project, the country will be able to use the opportunity of exporting cement
to other countries. Furthermore, this project will develop economy of the region by creating
Job opportunities as well as rising living standards and preventing migration to larger cities.
Page | 8
1.4 Constraints
There are several constraints that must be considered as part of the project’s procurement
management plan. These constraints will be communicated to all vendors in order to
determine their ability to operate within these constraints. These constraints apply to
several areas which include schedule, cost, scope, resources, and technology:
1. Schedule: Project schedule is not flexible and the procurement activities, contract
administration, and contract fulfillment must be completed within the established
project schedule.
2. Cost: Project budget has contingency and management reserves built in; however,
These reserves may not be applied to procurement activities. Reserves are only to
be used in the event of an approved change in project scope or at management’s
discretion.
3. Scope: All procurement activities and contract awards must support the approved
Project scope statement. Any procurement activities or contract awards which
specify work which is not in direct support of the project’s scope statement will be
considered out of scope and disapproved.
Page | 9
1.5 Integration Management
In the first step, the project manager developed the project charter to provide a formal
authorization of a project through proper documentation of the initial requirements
Satisfying the needs and specifications of the stakeholders. After the project charter is
signed by both the project manager and the project sponsor/owner, the project manager
will use the project charter for organizing all the required resources for the successful
completion of the project. She/he will also determine the external as well as internal
environment that can influence the project. Then, she/he will start to prepare a detailed
Documentation of project management plan which is beneficial for the project manager
to understand
The project and execute it properly. The project plan will guide the project manager
as well as the team members for directing and managing the execution of the project
Properly. In the next steps, the project manager will direct and manage project execution,
monitor and control project work, perform integrated change control, and finally close the
Project.
Page |
10
Chapter 2
Scope Management
Scope Management
As per Calgary Immigrant Educational Society (CIES), the degree for the Cement Plant
task is characterized through an exhaustive necessities accumulation process. Initial, a
careful investigation was performed on the organizations past concrete development
ventures. The venture portrayal and deliverables are produced taking into account the
necessities accumulation process and info from topic specialists in the concrete business.
This procedure of master judgment gave criticism on the best approaches to meet the first
prerequisites of developing another concrete plant.
The goal of this project is to construct a new cement production plant to increase cement
production capacity to supply the national demand for cement and its products; increase
the production capacity to use the opportunity of exporting cement to other co untried; and
Develop economy of the region by creating job opportunities as well as rising living
standards and preventing migration to large cities.
The objective of this project is to construct a new cement production plant with two
production lines, each with a capacity of 3,500 tons of clinker per day. The total
production capacity of plant for different kinds of cement is planned to be 10,000 tons.
The plant is planned to be located at British Columbia or Alberta, Manitoba, New
Brunswick. The plant land area is 100 hectares.
Page |
11
2.1.3 Project Requirements
1. Getting initial permits, final tests, and getting final operating license.
2. Subcontracting the construction of four major departments and some of the
equipment.
3. Purchasing other equipment and installation of equipment.
4. This project requires about 200 in-field and office staff.
5. Primary crushing department with two crushers (rotary hammer and roll) and total
crushing capacity of 1600 tons per hour. In this department ore extracted from the
mine turn into smaller size rocks for the transition into the next stage.
6. Raw material preparation department with one stacker with capacity of 2,000 tons
per hour, and two reclaims with a capacity of 450 tons each. In this department there
are 3 sets of ball mills, each with a production capacity of 160 tons cement per hour.
7. Clinker production department with a pre-heater tower with heating capacity of
3,500 tons clinker per day. Also, there is a kiln with the capacity of 3000 tons per
hour.
8. Cement production and packing department with a finish mill and 4 loading lines,
each with loading capacity of 200 tons per hour. It also has 4 cement packing
machines. Each of these machines can pack 150 tons of cement per hour.
2.1.4 Assumptions:
1. Staff and trade with required expertise will be available (or be hired).
2. A large percentage of the staff has enough experience so training is not required.
3. Material and equipment will be available (or be ordered).
4. Latest technology will be used to deliver the best quality with minimum negative
environmental impact.
5. The client/sponsor or his representative will be available for interaction.
6. Enough information will be available for initial budget and schedule forecast.
7. The detailed description of the project based on client requirements is in place.
8. Required infrastructure to support the project is ready prior to the start of the
project.
9. Adequate funding has already been obtained for the project.
Page |
12
Table (2-1) Scope assumptions
Cement is the basic material for buildings and civil engineering constructions. Output
from the cement industry is directly related to the state of the construction business in
general and therefore tracks the overall economic situation closely.
Portland cement is made by heating limestone (calcium carbonate) with other materials
(such as clay) to 1450 °C in a kiln, in a process known as calcination.
The most common use for Portland cement is in the production of concrete. Concrete is
a composite material consisting of aggregate (gravel and sand), cement, and water.
Portland cement may be grey or white.
Page |
13
Components of Cement Comparison of Chemical and Physical Characteristics[23][24][25]
Siliceous
(ASTM Calcareous
Portland Slag Silica
Property C618 Class (ASTM C618 Class C)
Cement Cement Fume
F) Fly Ash
Fly Ash
b
Specific surface 15,000–
2 370 420 420 400
(m /kg) 30,000
Cement
General use Primary Cement Cement Property
replacemen
in concrete binder replacement replacement enhancer
t
a
Values shown are approximate: those of a specific material may vary.
b
Specific surface measurements for silica fume by nitrogen adsorption (BET) method,
others by air permeability method (Blaine).
White cement is typically specified to ensure clean, bright, consistent colors, including light
pastels. White cement allows a wide range of color options for producing structural and
architectural concrete, as well as masonry and cementations building products. The final
color and look of concrete and masonry materials are affected by many factors:
Color of cement
Color of supplementary cementations materials
Color and dosage of pigment
Color, gradation, and cleanliness of fine and coarse aggregate
Surface treatment of finished concrete
Water content
Type and dosage of admixtures Cement of the same type and brand from the same mill
should be used throughout the entire job to minimize color variation when possible,
adequate quantities of all materials – cements, supplementary cementing materials, and
aggregates – should be stockpiled to ensure a single source and uniform color.
Page |
14
Page |
15
2.3 Explanation and definition for each of the activities/work packages
Among the work packages that planned to be done there are several activities that is going
to be sourced out to the external party. By doing so it can offer greater budget flexibility
and control. Outsourcing lets organizations pay for only the services they need, when they
need them. It also reduces the need to hire and train specialized staff, brings in fresh
engineering expertise, and reduces capital and operating expenses. For this particular
project, the work packages that are going to be outsource is Construction and Man Power
and Training. By outsourcing these work packages it could help a lot especially in the time
planning. It is also better to do so as the mentioned work packages will be handled and
managed by a party that have the expertise on those packages.
Page | 7
Chapter 3
Time Management
Time management
Time management in this project includes the all processes required to ensure timely completion.
For installation of Dry Cement Plant, many activities and tasks must to do for ensure timely
completion. In this project, all activity view in the project schedule.
N Phase Task WBS Activity Immediate Duration Predecessors successor Start date Finish date
o. /Package Code symbol predecessor ‘day’
1 Initial A 1.1 Getting industrial - 180 - 3,2,6 Fri 1/1/16 Thu 8/9/16
Proceeding permits
2 Design & B 2.1 Civil and A 30 1 5 Fri 9/9/16 Thu 20/10/16
engineering structural design
3 Initial C 1.2 Soil mechanic A 30 1 4 Fri 9/9/16 Thu 20/10/16
Proceeding studies &
topographic maps
4 Initial D 1.3 Land preparation C 60 3 8,10 Fri Thu 12/1/17
Proceeding 21/10/16
Page | 8
13 Primary M 4.1.3 Primary rotary I,K 165 9,11 25 Fri Thu 21/6/18
crushing hammer crusher 3/11/17
14 Primary N 4.1.4 Secondary roll I,K 195 9,11 25 Fri Thu 2/8/18
crushing crusher 3/11/17
16 Cement P 4.4.3 Finish mill J,K 450 10,11 26 Fri Thu 21/3/19
production 30/6/17
17 Cement Q 4.4.4 Cement storage J,K 150 10,11 26 Fri Thu 25/1/18
production silos 30/6/17
Page | 9
3.1 Arrow diagramming method (ADM)
Method of constructing a project network diagram that uses arrows to represent the
activities and connects them at nodes to show their dependencies.
ADM uses only finish-to-start dependencies and may require the use of dummy activities
to define all logical relationships correctly
Page | 10
Page | 11
Figure (3-1): Activities with their specific durations
Table shows the Activity with its duration with ES, EF, LS, LF and slack time for each one of the activities
Table 3.2 ES, EF, LS, LF and Slack time for critical path analysis
Page | 13
Chapter 4
Cost Management
The project manager will be responsible for managing and reporting on the project’s cost throughout the duration of
the project. During the monthly project status meeting, the PM will meet with the sponsor and executive manager to
present and review the project’s cost performance for the preceding month. Performance will be measured using earned
value. The PM is responsible for accounting for cost deviations and presenting the project sponsor with options for getting
the project back on budget. The project sponsor has the authority to make changes to the project to bring it back within
budget.
This Section Defines How Risk Management will be Structured and performed on the
Project. The Project team will use the risk register on to store project risks, including their
definition, category, probability of occurrence, and potential impact.
1. Expert Interview: Two Expert Interviews were held for this project. The
interviews revealed several risks which were then mitigated by making changes to
the project plan. The remaining risks are included in the Risk Register.
2. Risk Assessment Meeting: A risk assessment meeting was held with key team
members and stakeholders. The risks identified during this meeting were added to
the project plan and Risk Register.
3. Historical Review of Similar Projects: The project team reviewed the history of
similar projects in order to determine the most common risks and the strategies used
to mitigate those risk
Page | 16
5.3.1 Initial Risks
a. Fire and explosion which may occur because of using flammable liquids for
Engine combustion, plastics and combustible materials, welding
works, heaters in warehouses, transformers for electricity supply, and
compressors
b. Catastrophic risks such as winds, storms, hurricanes and cyclones, ground
subsidence, landslides and rock falls
c. Defects in workmanship such as carelessness in handling equipment which
may cause innumerable damages to the own work as well as to third parties
d. Errors in calculation or design and employment of defective or inadequate
material.
e. Accidents in plant site that may result in insufficient labor resources.
The project manager will maintain the risk register on the project website. Risks that the
team has identified as high risk will be monitored weekly by the project manager. All risks
will be reviewed monthly at a project team meeting and with project sponsors. At the end
of the project, risks will be reviewed and entered as lessons learned as appropriate.
The most likely and greatest impact risks should be added to the project plan to ensure that
they are monitored during the time the project is exposed to each risk. During the bi-weekly
project team meeting the PM will discuss the status of risks; however, only risks which fall
in the current time period will be discussed. Risk monitoring will be a continuous process
throughout the life of this project.
As risks approach on the project schedule the PM will ensure that the appropriate team
member provides the necessary status updates which include the risk status, identification
of trigger conditions, and the documentation of the results of the risk response.
Page | 17
5.3.3 Procurement Risks
Project risks will be managed in accordance with the project’s risk management plan.
However, for risks related specifically to procurement, there must be additional
consideration and involvement. The project team will include the project sponsor and a
designated representative from the contracting department in all project meetings and status
reviews. Additionally, any decisions regarding procurement actions must be approved by
the project sponsor or. Any issues concerning procurement
Projects also were delayed because they lacked information. Some of the delay was due to
time differences separating parts of global project teams. Losing one or more days on a
regular basis was common, due to misunderstandings and communication time lags. In
other cases, access to information was poor, or delivery of needed reports was interrupted.
Potential delay risks may be difficult to anticipate, and many of them seem to be
legitimately "unknown'' risks. Thorough analysis of the input requirements at each stage of
the project plan, however, will highlight many of them.
The project should be follow the budget plan ,if when we make the important ,we have to
compare between actual and plan cost ,if the actual cost rise of the plan ,then we have the
risk ,if we have less actual cost ,we have the benefit .The project should be follow the plan
of the cost that this making from top management .
The Cement Plant project requires some equipment for the operation the project (e.g.
pumps, Reactor, filters…..act).The risks events should be occur from the equipment but
different level (high, Moderate, low) risk, the project management should be evaluate and
control the risks. The project contents the simple equipment so that easily can make control
of the risk.
The following table shows risk probability definitions. During risk analysis the potential
likelihood that a given risk will occur is assessed and an appropriate risk probability is
selected from the chart below.
Page | 19
5.5 Impact of risk on the project
The following table shows risk impact definitions across each of the potentially impacted
project areas (cost, schedule, scope and quality). During risk analysis the potential impact
of each risk is analyzed, and an appropriate impact level is selected from the table below.
Page | 20
5.6 The possible risks that may affect the project objectives
Table 5.3 the possible risks that may affect the project objectives
Page | 21
Poor attitude toward
quality; substandard 0.06
Quality design/materials/workma Low 0.3 Moderate 0.2 (Moderate
n ship; inadequate )
quality assurance
program
Carelessness in planning
or communicating; lack
of consultation with key 0.06
Communication stakeholders, lack of Low 0.3 Moderate 0.2 (Moderate
communication between )
project staff.
Unenforceable conditions
or contract clauses; poor
0.06
Procurement choice of vendors, delay Low 0.3 Moderate 0.2 (Moderate
in supplying of materials )
and equipment
Fire, explosion,
casualties during 0.24
Safety construction Low 0.3 Very High 0.8 (High)
Environmental 0.12
Weather changes,
changes and Low 0.3 High 0.4 (Moderate
Natural disaster flooding, hurricanes )
Page | 22
5.7 Mitigation of the possible risks
Table 5.4 Mitigation of the possible risks
Risk Area Reductions
Cost Conduct feasibility study
Hire an expert in cost estimation
Closely monitor cost and spending
Early consultation to identify needs at the outset and avoid costs increasing later due to poor initial
understanding of requirements.
Perform value management vendor visits
Use WBS and CPM
Schedule Assign qualified project manager
Use WBS and CPM
Set delivery dates for equipment and materials earlier, so there will be sufficient time to take corrective
actions.
Staging the project so that it can be altered at successive review points
Establish a schedule to monitor the project status. The schedule will be followed closely during all
development stages.
Revision of schedule estimates
Scope Define the deliverables and work packages properly
Hold meetings with project costumer and sponsor to clarify scoop
Use WBS
Risk Project risk that affect project objectives should be considered in all phases.
Hire a risk assessment expert.
Management Assign qualified project manager
Additional team training
Provide cross-training to the team and labors.
Consider hiring consultant with additional experience for initial period.
Human Resources Posts made available to skilled workers outside of Malaysia
Post of assistant made for each head
Acquire health screening before hiring
Communication between the staff is excellent
Quality Standards should be followed in design, materials, etc.
Design Hire qualified design engineers with experience to design the project
Use software simulators to test the design
Make prototype project before turn to large scale
Design flexibility increases the flexibility of designs to make proposals more robust against changes in
future demand
Environmental changes Chose project location out of the effect of hurricanes, flooding, etc.
and Natural disaster Insurance contract should include the damages caused by natural disaster
Page | 23
Chapter 6
Quality Management
Identify and discuss the quality (standards) that will be used for the project (in terms of
technical as well as project management aspects) Include the processes required to ensure
that the project will satisfy the needs for which it was undertaken. There are four key
components to comprehensively achieving project quality which include Quality
Management (QM); Quality Planning, Quality Assurance, and Quality Control.
Quality Planning is the procedure of figuring out what quality norms are pertinent to the
venture, what measures of value will be utilized and what criteria will be utilized to figure
out whether venture quality is fulfilled. Venture Quality targets will be accomplished by
actualizing an incorporated quality system/procedure comprising of Define Quality,
Measure Quality and Improve Quality. The task characterizes quality by recognizing and
reporting quality criteria. Quality criteria comprises of gauges and measurements taking
into account consistence with Request for Proposal (RFP) and Service Request necessities,
Requests for Offer (RFO) or other confirm customer desires and venture goals. Setting up
quality criteria sets quality desires for undertaking procedures and items. Other or extra
venture particular quality measures will be characterized by the Project Manager and
Project Team and kept up by the group subject to endorsement by the Project Sponsor and
Project Director.
Measuring quality guarantees that the task and contractual worker's procedures, items and
systems hold fast to the agreement terms and conditions and the Project Management Body
of Knowledge (PMBOK®). The undertaking will distinguish, gather, examine and
investigate measurements all through the venture's life. The choice of measurements and
information things will advance to concentrate on particular territories as needed. The
venture's utilization of measurements lessens subjectivity in the evaluation and control of
task quality by giving a quantitative premise to deciding. The utilization of measurements
does not take out the requirement for human judgment in their assessment. The utilization
of measurements inside of a venture is relied upon to have a useful impact by making
quality (or absence of value) visible. Product measurements depict the attributes of the
item, for example, Monoester substance, item virtue, and quality level. Process
measurements can be utilized to enhance venture execution and upkeep. Quality
measurements will incorporate:
Page | 25
6.1.3 Assure Quality
Quality affirmation is the obligation of the task supervisor. Preceding considerable
finishing and last acknowledgment of the plant, intermittent conformance investigations
will be led on an office by department premise or on a useful premise by the PM. The
motivation behind these conformance reviews is to minimize defers and protect effective
turnover. The temporary workers ought to amend any development lacks distinguished
amid these visits before a last turnover is planned. The accompanying measurements will
be utilized on the undertaking:
The project manager will use the following checkpoints to monitor project quality, and will
provide detailed feedback to the project sponsor concerning the audit and review results as
defined in the communication plan.
1. Progress reviews: Progress documents should be reviewed by the project team on
regular basis.
2. General building inspections: The construction project engineer will be dedicated
full time on this project for construction inspection and coordination. The project
team will make periodic site visits to observe compliance.
3. Testing: These testing will be done during installation of equipment. Testing will
be in accordance with the contract documents, including in-house-made equipment,
electrical instruments, and imported mechanical equipment.
4. Code compliance: Cement Association of Canada (CAC) will perform plan reviews
and required inspections of the buildings and equipment prior to issuing the final
Page | 26
permit. They will try to assess the plant according to Canadian Standards
Association (CSA), American Concrete Institute (ACI) and American Society for
Testing and Materials Codes (ASTM) standards.
5. Final Inspections: Parties included in the key final inspections will include the
project manager, project sponsor, principal engineer, construction project engineer,
and appropriate project team members. Additional participants may include certain
contract representatives.
6. One year warranty inspection: This inspection will be scheduled with the contractor
representatives 11 months after substantial completion.
As per The government is moving quickly to create and present regulations under the
Federal Regulatory Framework for Industrial Air Emissions for nursery gas discharges. As
directed by the Federal Regulatory Framework for Industrial Air Emissions, Canada's bond
fabricating division will be required to:
Reduce its nursery gas discharges force to 18% underneath 2006 levels by 2010.
further decrease its nursery gas outflows power an extra 2% for each annum
thereafter.
According to an introductory monetary investigation authorized by CAC and attempted by
Mark Jaccard and Associates and Enviro-Economics, "with current requirements on the
utilization of exchange powers and Supplementary Cementing Materials, the industry will
encounter huge operational effects under the Federal Framework" with consistence
expenses coming to 10% of offers by 2015. This same examination observed that even
unobtrusive increments in access to elective and renewable energies and supplementary
solidifying materials would essentially decrease the consistence costs under the Federal
Regulatory Framework.
Page | 27
6.2.2 Air Pollutants Framework
Close by the improvement of nursery gas emanations regulations under the Federal
Regulatory Framework for Industrial Air Emissions, the government is likewise moving
quickly with the advancement of an air poison discharges administrative structure. The
Cement Association of Canada played an administration part amid the mid-year of 2007 in
the foundation of the Multi-Stakeholder Advisory Group to the Minister of Environment
on the improvement of an elected part to regulate air emissions. This gathering is comprised
of natural non-government associations, industry affiliations, and wellbeing non-
government associations. These associations are coordinating to create proposals to the
government on the mutual objective of enhancing Canada's air quality.
As a net trading assembling division, CAC's 2007 Submission to the Joint Finance
Canada
- Canada Revenue Agency Consultation "Enhancing the Scientific Research and
Experimental Development Tax Incentives, Canada's concrete industry is
confronting expanding difficulties to intensity, as highlighted by the Canadian House
of Commons Standing Committee on Industry in its Report to Parliament (February
2007).
Page | 28
Chapter 7
Organizational Structure
Page | 29
7.1 Roles and Responsibilities
Page | 30
4. ensure office and staff follow
established procedures including employee
orientation and training
5. Mail distribution
6. Vehicle coordination
7. Office supplies and all other office functions.
Page | 31
Table (7-2) Roles and Responsibilities with communication requirements, expectations
and classification influence.
Page | 31
Environmental Participation in the Quarterly email 1. Compliance with the External
unions process of project updates , end of environmental legislation Positive
approval and the project report 2. Reduction of air emissions
issuing of 3. Implementation of an energy
necessary permits, efficient cement production line
oversight of
environmental
compliance
Cement plant Participation in the Regular meetings 1. Job creation Internal
employees project 2. Professional and career growth Neutral
implementation 3. Improvement of working
conditions
Customers for Customer Once in a while 1. Expansion of products’ range External
cement meetings 2. Improvement of products’ Positive
quality, packaging, and delivery
3. Products certification in
accordance with the relevant
National and international
standards
4. Possibility of increased
competition as a result of the
cement production expansion
Mass media Informing Interview Timely information about the External
(magazines, stakeholders on the meetings project Positive
newspapers, progress of the
TV and radio project
channels, implementation
news agencies)
Page | 32
Chapter 8
Communications Management
Table (8-1) Communications Management
Project Risks and project team as needed risk register and project manager,
Issues issues log project team
Project Changes project sponsor as needed project change project manager
executive request
management
Public Input or Public as needed public meeting executive
Notifications
manager
Notifications employees who as needed email responsible
may be affected individual
Page | 33
Chapter 9
Procurement Management
9.1 Procurement Management
This procurement management plan sets the procurement framework for this project. It will
serve as a guide for managing procurement throughout the life of the project and will be
updated as acquisition needs change. This plan identifies and defines the items to be
procured, the types of contracts to be used in support of this project, the contract approval
process, and decision criteria.
1. The project team will work with the contracts and purchasing department to define
the item types, quantities, services and required delivery dates.
2. The contracts and purchasing department will then solicit bids from various vendors
in order to procure the items within the required time frame and at a reasonable cost
under the firm fixed price contract once the vendor is selected. This contract will
be awarded to the winning contractor.
Page | 34
3. The project team will work to determine what items or services will require
procurement from outside vendors. This will be determined by using design
documents and conducting a cost analysis of products or services which can be
provided internally and compared with purchase prices from international or
domestic vendors.
4. Once cost analysis is complete and the list of items and services to be procured
externally is finalized, the project team will send the results to contraction officer.
Contraction officer is the connection point between project team and purchasing
and contracts department.
5. The purchasing and contracts department will complete solicitations and send out
Request for Proposals (RFP) to outside vendors. The department will start collecting
the proposals.
6. Once proposals have been received by all vendors the approval process begins. A
review of all vendor proposals will be conducted to determine which meet the
criteria established by the project team and the purchasing and contracts
department. The criteria for the selection and award of procurement contracts under
this project will be based on the following decision criteria:
Ability of the vendor to provide the service by the required delivery date
Quality
Cost
Expected delivery date
Comparison of outsourced cost versus in-sourcing
Past performance
7. All purchases require the approval of the project manager and the Contract Review
Board. The Contract Review Board consists of representatives from the project
team, purchasing and contracts department, finance, and the project manager.
Appendices (2) more detailed Flow sheet about dry cement manufacturing:
Page | 36
Appendices (3) Suggested locations in Canada
1. British Columbia
2. Alberta
3. Manitoba
4. New Brunswick
Page | 37
Appendices (5) Plant Layout
Page | 38
Appendices (7): Table shows you the activities with their durations ‘done by Microsoft
office’
NO Activity 2016 2017 2018 2019 2020
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
1 A
2 B
3 C
4 D
5 E
6 F
7 G
8 H
9 I
10 J
11 K
12 L
13 M
14 N
15 O
16 P
17 Q
18 R
19 S
20 T
21 U
22 V
23 W
24 X
25 Y
26 Z
27 AA
28 AB
29 AC
30 AD
Page | 39
References:
Brilliant Project Management: What the best project managers know, do, and say
(Third Edition)
Calgary Immigrant Educational Society (CIES), 1723 40 St SE, Calgary, AB T2A 7Y3, Canada
Phone: +1 403-235-3666
Nancy Horsman and Peter C. Armstrong ,Joint Finance Canada - Canada Revenue Agency
SR&ED Consultations, 140 O'Connor Street ,L'Esplanade Laurier,Ottawa, Ontario K1A
0G5.
Page | 40
Page | 41