Professional Documents
Culture Documents
BUILDING.
PROMOTER:-MICALE AMEBACHEW
Nov, 2021
ETHIOPIA
1
Table of Contents
Executive Summary............................................................................5
Introduction........................................................................................6
General Background.........................................................................6
2 Project Objectives.............................................................................8
2.1 General Objective.......................................................................8
2.1.1 Specific objective..................................................................8
Project description............................................................................8
Project Rationale..............................................................................9
The significance of the project..........................................................9
Project Location..............................................................................10
3The market Study............................................................................11
Market Analysis..............................................................................11
The Demand-Supply Gap...............................................................11
Current supply of Mixed use building.............................................12
Future market or Demand of commercial Building rental...............12
Target customers............................................................................13
Marketing promotion and strategy..................................................13
Competition....................................................................................13
The project facilities and Services plan...........................................14
4 Technical Studies...........................................................................16
4.1 Description of the project Service/ Product mix........................16
4.1.1 Land Use Plan....................................................................16
4.2 Construction work and Technology...........................................17
4.2.1 Construction schedule........................................................17
4.2.2 Architectural Design & Layout............................................17
4.2.3 Structural design................................................................18
4.2.4 Reinforced concrete............................................................18
4.2.5 Foundation Design.............................................................18
2
4.2.6 Construction Plan and process...........................................19
4.3 Utilities.....................................................................................19
5 Engineering and civil works............................................................21
5.1 Land, Building and Civil Works................................................21
5.2 Manpower and training requirement.........................................22
5.2.1 Manpower requirement.......................................................22
Labor Availability.........................................................................23
Project implementation...................................................................23
Organizational Structure................................................................24
Organization and management.......................................................24
6 Financial analysis..........................................................................31
6.1 Repair and Maintenance Cost...................................................31
6.2 Depreciation and Amortization.................................................31
6.3 Total Revenue...........................................................................32
6.4 Discounted Payback Period......................................................32
6.5 Cash flow..................................................................................32
6.6 Benefit cost ratio......................................................................32
6.7 Internal Rate of Return.............................................................33
6.8 Net present value......................................................................33
7 Conclusions and Recommendations...............................................34
Conclusion.....................................................................................34
Recommendations..........................................................................35
References.........................................................................................36
List of table
Table 2: The plan is that the ground will be partitioned in to different rooms…14
Table 4: Utilities…………………………………………………………………… 20
Table 5: List of Building and Civil Works and Their Costs ……………………..21
3
Table 6: Manpower Requirement and Annual Labor Cost………………………22
4
1. Executive Summary
1. Project Name Mixed Use Building
3. Nationality Ethiopian
4.Address
5
2 Introduction
The current fast and dynamic economic growth of Oromia region especially
in Nonoworeda ssilk ambatown necessitates equivalent growth of building
and construction sector. The sector should expand rapidly to support the
overall economic development sustainable.
In the building sector of the economy, the multi- purpose in the one
becoming rapidly expanding in Nonosince dynamic economic development
of urban economy requires the construction of these buildings in the city to
support the growing of business service sectors like supermarkets, Beauty
salon, shops, offices cinemas, Computer Center, Cafeterias, restaurant,
assembly hall, apartments and other activities. In this regard, mixed used
building expands in the all parts of the city.
To this effect, the owner of the envisioned Mixed Use Building Mr Deraje
Abera who has been living for long time in this city, planned to construct in
Silk Amba and undertaken this project study to check the market,
technical and financial feasibility of this project. The promoter is very
ambitious and committed to realize the project. Hence, they expect to get
the necessary support from the city administration to make the project to
be operational.
Besides, the government policies and incentives for the private sector
investment are very promising that motivates the promoter to engaged in
mixed use building business.
7
2 Project Objectives
The major goal of this project is to contribute towards the growth of the
trade sector in Silk amba. Its specific objectives include the following.
2.1.1Specific objective
The long-term goal of the project is become the best choice trade center in
the city. The proposed project will have a total area of 200m2, designed to
reader a multipurpose giving business, which will in turn plays significant
role towards solving shortage of business center in Silk amba.
The historical nature of the city as business unique location in one of the
most attractive centerin Ethiopian (100% urban center). The owners plan
the project to render banking and insurance, shopping facility, offices and
cafeteria services to create high quality class to satisfy the interest of
customers in the city. Based on environmental and other considerations,
the entrepreneur has determined the type and size of the building which is
8
already determined by the site; conceptual planning and preliminary
analysis have been carried out by analysts.
In order to attract its clients to the service, the project will develop high
standard shop & banking rooms and office of best choices and will also
save best quality apartments, restaurant and café.
9
A. Source of Revenue
B. Employment opportunity
The license area is located in Nono woreda, Silk Amba locally named as"
Civil Service". The total area of the project is 200 m 2. . It is surrounded by
main asphalt road at west part, south east by resident, south west
resident, and mixed use building at North part.
Mixed-useDevelopments
Mixed-use projects are developments which combine two or more
types of revenue producing real estate developments. Mixed-use
projects may be either low rise
suburbanprojectsorhighrise,highdensityurbanprojects.Mixed-
useprojectswere created to satisfy a convenience and marketing
demand using valuable property for itshighestandbestuse.
[1]Forinstance,tohaveahotelfunctionprovidesadvantage for office
visitors while creating a demand for the hotel itself. The synergy
created between the components creates vitality for the mixed-use
10
development and generally combining different functions in one single
project is superior to each singledevelopment.
significantphysicalandfunctionalintegrationofprojectcompon
ents(andthusa relatively close-knit and intensive use of
land), including uninterrupted pedestrian connections,and
profileandcreatelandmarkssohelpfulinmarketingthedevelopmen
tbuthavea disadvantage of creating less public outdoorspace.
11
Integrated Multi-Tower Structures: These structures
architecturally connect
individualbuildingsandtowersinonemulti-
componentdevelopment.Common building may be an
atrium, a shopping Centre or underground parking area.
Mostly found in downtown central business district (CBD)
or high density suburbandowntowns.
12
3 The market Study
The demand for office space is a derived demand because firms rent space
as an input to the production of services or goods they provide to
businesses and households in the local or national economy.
Following our survey of office space users in several areas are mainly firms
providing banking, offices, cafeteria and restaurants, supermarkets,
computer center service. Future demand for office space is actually driven
from growth in number of offices in the city which in turn is influenced by
the macro-economic growth in the country. Assuming that demand for
14
office space is directly related to the growth in the economy, the forecast for
office space demand is shown in the following table;
1. Business Community
2. Business organization
3. The government bureau
4. Non-governmental organizations
In order to penetrate and gain considerable market share, one of the major
marketing strategies for the project is consistently rendering quality service
to its tenants. Due emphasis must be placed on improving quality of
service and facilities. The major marketing strategies to promote the project
and gain considerable market share include:
15
Advertising through different means focusing on the existing service
and facilities
Promote in association to the key location and nearby business
Working on sustained promotional work.
Working on public relations to reach and influence key personas
and organization with a capacity of making decision.
Keeping the quality of its service/ facilities and consistently
improving with changing situations.
3.7 Competition
There are different forms of competition that may face the envisaged mixed
use building. These are price and non-price based competition. Moreover,
there are different competitors that will compete with the project either
directly or indirectly. But the mixed use building under discussion has
diversified marketing strategies that could enable it Cope up with the
different competitors in the market. Moreover, it will frequently conduct
competitors research which focuses on, the strength and the weaknesses,
the different competitors’ strategies, the techniques they use in rendering
the service, their customer handling methods, and others. Generally, the
project has many other projects all over Nonoworeda silk amba villages
which compete with it.
SiteEvaluation
Theanswerforaquestionof,“asiteforaneed?Oraneedforasite?”dependsonthe
developer’s development strategy and assets. But for both circumstances
market research is the key to a successful development. In order to determine
the most appropriate product type for a specified site for its “highest and best
use” the
developershouldconductagoodmarketresearch.Foraspecifieduse,marketstudy
16
of regional or local areas which gives an understanding of trends and
demographics will lead to find the most suitable sitearea.
Asphysicalfeasibilityisoneofthedeterminantsofproject’soverallfeasibility,ina
feasibilityreport,oncethedecisionhasbeenmadetodevelopinaparticulararea,the
analystevaluatesthepotentialsiteandmakesrecommendationsonthissitebasedon
the criteria definedbelow:
Location
Theoldestclichéintherealestatebusinessisthatwhatmattersis:location,location,
location. Location refers to accessibility and visibility in real estate and they
are
thekeycriteriaforthevalueofsiteandtheintendeddevelopment.Thisisextremely
importantforsometypesofdevelopments.Someretaildevelopmentsrelyheavilyon
sightlinesfromsurroundingstreets.Someofficedevelopmentsmarketwellnotonl
y because of their proximity to freeways but their profile on the skyline.
Mixed-use projects usually have excellent access and good exposure. To
outdistance the competition, the developer’s site must be equal or better
than others within the
marketplace.Tenantswilloftenmaketheirfinaldecisionbasedonvisibilityandeas
e of access.
Adjacentlandhasalsoeffectonthesubjectsite.Presentandpossiblefutureplansfo
r the neighborhood should be reviewed carefully. Any inconvenience, of
which some
arelistedbelow,mayadverselyaffectthemarketabilityofthedevelopment[:
Overhead powerlines
17
Cemetery
Landfill
Railroads, freeways,expressways
Airport glidepaths
Manufacturingplants
Quality ofsurrounding
Trafficpatternsshouldalsobeevaluatedwhenconsideringaccessibilityof
thesite;a heavy traffic may not be desired for some users. This
evaluation may be conducted with a trafficengineer.
The parcel size and configuration should meet the need for the
development. For specified uses minimum size of land parcels will be
required. Mixed-use projects
generallyhaveseveralfeaturesincommon,sositesneedtobesubstantiallyl
argeor allow high density construction. Shape of site is also
important; it should allow the designer to allocate best configuration
in optimumuse.
The land should have the required zoning or have the probability of
being rezoned. But attention should be paid that rezoning process
may take long time, sometimes several years depending on the
community.Alsoitshouldbenotedthatparcelsizeisafunctionofzoningcla
ssification,i.e.open space, parking area and density is determined by
planning guidelines where thesize of the parcel is an important
criteria forevaluation.
18
use projects.
19
Climatic and naturalinfluences
In order to provide mixed use business center building services of a high standard, it
has been planned to construct and develop the infrastructure and facilities that
would viable to meet the requirements of an international standard business center.
Accordingly, various buildings and facilities will be constructed phase by phase
starting with the most needed ones that are essential to commence the operation of
its business activities. With the completion of construction, the building will provide
a combined service such as shops, offices, restaurant and café service as well as
modern business center that primarily serve its guests and major clients.
Table 2: The plan is that the ground will be partitioned in to different rooms:
Since the project will be engaged in mixed building the main sources of its annual
revenue would be from the rental of building spaces such as shops, offices, and
banking, café and restaurant. Therefore, the sources of revenue have been classified
20
in to one category namely the rental of banking and supermarket, offices, shops,
bedrooms restaurant and café based on these classifications. Based on the market
price of similar mixed use building in the area, the envisioned buildings set the
following fair price (Before VAT) for its service, hence when the building construction
fully get operational it is assumed to generate a yearly income of ETB 12,538,850.
4 Technical Studies
The envisioned mixed purpose building will provide different rental services to the
different customer groups for different purpose. The building will have basement,
ground and twelve floors. The purpose of the building explained as follows;
The ground floor, first floor second floor and third floor designed for different
business centers like banks, supermarket, beauty salon(man and women),
Computer center, pharmacy, internet café, boutiques, different shops and
other business activities,
The total land required for the envisioned project is estimated to be 200m 2. The total
area for the construction of the building will be 200m2, as revealed below.
21
Table 3: land utilization Plan
No Description Land M2
Basemen Ground First floor-Twelve
t floor
1 Building (G+12)
1.1 Basement 200
1.2 Ground 200
1.3 First floor-Twelve 200
floor
Total 200
Mechanical and Electrical install coincide with each other due to the need for
coordination between the two divisions. There are several periods of construction
during the schedule in which there are multiple construction activities occurring at
the same time.
The construction site must be organized accordingly as these processes take place.
As with any construction project, the goal of the schedulewill to complete all
construction activities before the required Date of completion.
This date of completion is practical based on the time of year in which the building
will be completed. The team allowed a two week contingency for any setbacks.
Typically, winter construction tends to cause unforeseen delays that negatively
22
impact a construction project. These conditions can and will almost undoubtedly
impact the project schedule by causing unforeseen delays and project inefficiency.
Although functional spaces for the project were laid out in significant detail, the rest
of the building had designated spaces but set layouts. It was at the discretion of the
project promoter to devise typical layouts for the non-detailed commercial and office
spaces. To make sure that the building’s layouts were practical, the project owner
researched typical architectural layouts for laboratory and executive office spaces.
The walls and partitions throughout the floor will congruent with the structural
frame and column locations.
One of principle deliverables of the project is the structural design of the building.
The structural bays were coordinated with the layout of the building adjustments will
be made to the bays if specific layouts are necessary. The frame will be made up of a
grid with repeating standard structural bays. Included in the structural system are
bay sizes, shape and size of structural members, floor compositions and curtain
walls. These elements were established to resist gravity ad lateral loads as
appropriate.
The gravity load design will completed for two frames; one of structural steel and one
of reinforced concrete. The structural steel frame will chosen for further design based
on cost per square foot, local availability of material and constructability
considerations, such as erection and fabrication. The steel system will then designed
for lateral loading with necessary adjustment being made to framing.
The project group prepared hand structural design calculations for a typical bay of a
reinforced concrete frame. In all reinforced concrete bay designs, a superimposed
dead load of 8 pounds per square foot will be assumed for mechanical equipment,
floor coverings and ceilings.
23
Similarly, the design of the typical bay accounted for the use of different commercial
space, in which a live load of 1000 pounds per square was assumed. Loads will be
calculated based on the requirements of the minimum Design loads for Buildings and
other Structures.
The design of a superstructure may be accurate, have considered all possibilities and
still fail because the substructure is incapable of distributing the applied loads to the
supporting soil.
Foundation design takes more into consideration than merely the loading from the
columns. While the main part of the project focused on the structural frame and its
alternate designs, a preliminary foundation plan was designed based upon maximum
load carried from the superstructure through the columns. The foundation design
conducted by the project team consisted of the selection of foundation type,
determination of the bearing capacity and the design for typical interior and exterior
spread footings.
The construction process for this project is normally a disjointed three mages
development by which the conceptualized need of the promoter of this project is
translated into a functional facility that will meet their needs in terms of time, cost
and quality.
Based on a general program of the project owners the consultant who is going to be
hired makes site studies, develops structural designs, prepares drawings and
specifications, determines quantities involved and estimated the resultants costs. All
these activities will be done in the first phase of the project which is the design stage
after the document are produced by the designers have been received, and the works
secured the project is supposed to enter the tendering stage. At this stage contractors
study the project document analyze and subsequently determine the construction
methods, built up their unit rates and submit their bids for the works. The promoter
24
of this project intends to compare the bids and award the contract for the lowest
responsible bidder. This, is of course, presupposes that the favorable proposal does
not exceed the allocated budget.
After the award is made and the contract signed between this project owners and the
contractor, the project constructor is expected to prepare and submits a detailed
construction program which includes material schedule, manpower requirement and
cash flow forecast.
After the award is made and the contract signed between this project owner and the
contractor, the project constructor is expected to prepare and submits a detailed
construction program which includes material schedule, manpower requirement and
cash flow forecast.
4.3 Utilities
Cost
No Description Qty. Unit cost (Birr)
1 Electricity supply, kWh 100,000 1.30*10,000 130,000
2 Water Supplym3 50,000 10*500,000 500,000
4
Fuel, Oil and lubricant 2000 19*2000 38,000
Total 1,188,000
25
BUSINESS PLAN FORMIXED USE BUILDING
The Mixed use building has a total site area of 200 m 2. The building floor area
has covered 24 m2 and the remaining 136 m2 is left for construction. The type
of buildings and its corresponding civil construction cost is given on Table 5.
As shown on Table 5, the total cost of building and civil work is estimated at
Birr 10,152,958.40 and out of which the proponent has worked more than
birr 8.6 million.
The list of manpower and the annual cost of labor is indicated in Table 6.
26
BUSINESS PLAN FORMIXED USE BUILDING
27
BUSINESS PLAN FORMIXED USE BUILDING
Workers for this type of plant are available throughout the year. No foreseeable
problems are expected as most of the work requires no previous skills.
SN Activities Date
1 Preparation Project Proposal May 2020
2 Bank loan processing June-July 2020
3 Site Development July 2020
4 Building and construction work August, 2019-July 2022
5 Preparation for service September, 2022
6 Service execution February, 2022
28
BUSINESS PLAN FORMIXED USE BUILDING
Organizational Structure
Employees under each unit will be supervised by the department head that is
accountable for the general manager. General Manager is appointed by the
owners
He/she will plan, organize, direct and control the overall activities of the
building.
He/she will devise policies and strategies that will enable the center to be
profitable.
29
BUSINESS PLAN FORMIXED USE BUILDING
He/she will plan, organize, direct and control the human and non-human
resources of the building so as to achieve the short and long run objectives
of the organization.
Will provide the right material or inventory to the center with right price
at the right time.
Will plan, organize direct and control the financial transaction of the
building by using all the necessary documents.
Accountant and casher that will collect money from the customers.
30
BUSINESS PLAN FORMIXED USE BUILDING
Follow the overall status of the business and provide maintenance and
repair services
Works in collaboration with general service to make sure tenants are well
served
Owners
General Manager
31
Building Maintenance Marketing
administration Department Department
BUSINESS PLAN FORMIXED USE BUILDING
Promotion
Personnel
&Property Finance
Officers
IT, Supervisors
The financial resource is a prime resource for undertaking any activities. Hence
Electricity
for implementing this mixed use building a total of 15,000,000ETB is
required. From this 30% 4,500,000birr will be covered by the promoter of the
project while the rest 70%(10,500,000) will be covered through loan from bank
at the prevailing interest rate.
Therefore the said amount of finance is needed for undertaking the following.
32
BUSINESS PLAN FORMIXED USE BUILDING
C. Vehicle
SN Description UOM Qty Unit Cost Total cost in Remark
in Fr. Birr
1 Mini-Bus Unit 1 300,000.00 300,000.00 Duty Free
Total 300,000.00
D. Office Equipment’s
SN Description Measurement Qty Unit cost Total cost
in birr in Birr
1 Managerial tables Unit 1 12,600.00 12,600.00
2 Managerial chairs Unit 1 19,500.00 19,500.00
3 Office table with chair Unit 7 12,000.00 12,000.00
4 Secretarial table with chairs Unit 1 8,500.00 8,500.00
5 Computer with chairs Unit 1 15,000.00 15,000.00
6 Shelf Unit 3,500.00 3,500.00
7 Filing cabinets Unit 1 1,500.00 1,500.00
8 Guest chairs Unit 1 4900 4900
9 Fax & Telephone machine Unit 1 1,300.00 1,300.00
10 Carpet and Curtain LS 1 23,000.00
Total 101,800.00
Working Capital
Operating Expenses
SN List of Items Annual cost in birr Assumptions Used
1 Audit and legal fee 48,000.00 4000 br/per ,month
2 Stationery supplies 12,000.00 1000 br/month
3 Promotional Cost 40,000.00 Lump sum annual cost
4 Property Insurance 84,009.00 1% of the building
5 Cleaning Supplies 12,000.00 1000 br. Per month
6 Uniforms 12,000.00
7 Water consumption 5,000.00 2500 m3 by 3.15 br
8 Electric consumption 130,000.00 100,000KWH By Br.1.30
9 Fuel 38,000.00 2000 lit per year by Br.19
11 Telephone & fax 20,000.00 1800 per month
12 Repair expense 72,018.00 2% of building cost
13 Miscellaneous costs 40,000.00 6000 per month
Total 513,027.00
33
BUSINESS PLAN FORMIXED USE BUILDING
Pre-service Expenses
SN Description Cost in birr
1 Project proposal 100,000.00
2 Licensing fee and others
Total 100,000.00
34
BUSINESS PLAN FORMIXED USE BUILDING
6 Financial analysis
The financial analysis of thismixed use project is based on the data presented
in the previous chapters and the following assumptions: -
The annual repair and maintenance cost of the plant is estimated based on the
following rates.
The following depreciation rates are applied to depreciate the assets of the
35
BUSINESS PLAN FORMIXED USE BUILDING
project:
Based on the projected profit and loss statement, the project will generate a
profit throughout its operation life. Annual net profit after tax increases from
Birr 8,810,480at the beginning of the project to Birr 22,502,429during the
last year of operation year. The detail is presented in Annex.
The payback period, also called pay–off period is defined as the period
required recovering the original investment outlay through the accumulated
net cash flows earned by the project. Accordingly, based on the projected
cash flow it is estimated that the project’s initial investment will be fully
recovered within 3 year 9 months.
The projected cash flow of the envisaged project shows that the project would
generate positive net cash flows throughout the operation years. Cumulative
cash flow generated by the project towards the end of the first operation year
will amount to Birr 9,259,139. At the end of the project life, this amount will
rise to Birr 23,618,548. The detail is presented in Annex.
The BCR is defined as the ratio of the sum of the project’s discounted benefits
to the sum of its discounted investment and operating costs.
36
BUSINESS PLAN FORMIXED USE BUILDING
Net present value (NPV) is defined as the total present (discounted) value of a
time series of cash flows. NPV aggregates cash flows that occur during
different periods of time during the life of a project into a common measuring
unit i.e. present value. It is a standard method for using the time value of
money to asses’ long-term projects. NPV is an indicator of how much value an
investment or project adds to the capital invested. In principle a project is
accepted if the NPV is non-negative. Accordingly, the net present value of the
project at 10% discount rate is found to be Birr24,439,417which is
acceptable.
37
BUSINESS PLAN FORMIXED USE BUILDING
1 2 3 4 5 6 7 8 9 10
Ground floor Rent
5,240,000 7,164,000 8,180,400 9,298,440 10,528,284 11,881,112 12,369,224 13,006,146 14,806,761 15,787,437
Size
1110 1110 1110 1110 1110 1110 1110 1110 1110 1110
unit price
350 385 424 466 512 564 620 682 750 825
Rent for shop and office 1-3 floor
2,956,800 3,252,480 3,577,728 3,935,501 4,329,051 4,761,956 5,238,152 5,761,967 6,338,163 6,971,980
Size
1110 1110 1110 1110 1110 1110 1110 1110 1110 1110
unit price
224 246 271 298 328 361 397 437 480 528
Rent for shop and office 4-7 floor
2,890,800 3,179,880 3,497,868 3,847,655 4,232,420 4,655,662 5,121,229 5,633,351 6,196,687 6,816,355
Size
1110 1110 1110 1110 1110 1110 1110 1110 1110 1110
unit price
219 241 265 291 321 353 388 427 469 516
Rent for shop and office 8-12 floor 1,980,000 2,217,600 2,439,360 2,439,360 2,683,296 2,683,296 2,951,625 2,951,625 3,246,787 3,246,787
Size 1110 1110 1110 1110 1110 1110 1110 1110 1110 1110
unit price 150 165 182 200 220 242 266 292 322 354
Parking
91,250 100,375 110,413 121,454 133,599 146,959 161,655 177,820 195,602 215,163
Size
1110 1110 1110 1110 1110 1110 1110 1110 1110 1110
unit price
5 5.50 6.05 6.66 7.32 8.05 8.86 9.74 10.72 11.79
Total Sale
17,158,850 18,914,335 20,805,769 22,642,409 24,906,650 27,128,986 29,841,884 32,530,910 35,784,000 39,037,721
38
BUSINESS PLAN FORMIXED USE BUILDING
513,027 538,678 565,612 593,893 623,588 654,767 687,505 721,881 757,975 795,873
Sub-total
Total Direct cost
B. Indirect cost
Wages and 238,400 1300,320 365,336 433,603 505,283 580,547 659,574 742,553 829,681 921,165
Salary
Repair and 667,449.00 667,450.00 667,451.00 667,452.00 667,453.00 667,454.00 667,455.00 667,456.00 667,457.00 667,458.00
Maintenance
Property 4,275.00 4,275.00 4,275.00 4,275.00 4,275.00 4,275.00 4,275.00 4,275.00 4,275.00 4,275.00
Insurance
Utility 1,188,000 1,247,400 1,309,770 1,375,259 1,444,021 1,516,222 1,592,034 1,671,635 1,755,217 1,842,978
Land lease 422,640 422,641 422,642 422,643 422,644 422,645 422,646 422,647 422,648 422,649
Advertising and 50,000.00 50,001.00 50,002.00 50,003.00 50,004.00 50,005.00 50,006.00 50,007.00 50,008.00 50,009.00
Promotion
Miscellaneous 40,000.00 40,001.00 40,002.00 40,003.00 44,003.30 48,403.63 53,243.99 58,568.39 64,425.23 70,867.75
Expense
Total operating 4,123,791 4,270,766 4,425,090 4,587,130 4,761,271 4,944,319 5,136,739 5,339,022 5,551,686 5,775,275
cost
39
BUSINESS PLAN FORMIXED USE BUILDING
Less: interest 448,658.00 448,658.00 448,658.00 448,658.00 448,659.00 448,660.00 448,661.00 448,662.00 448,663.00 448663
Income 12,586,401 14,194,911 15,932,021 17,606,621 19,696,720 21,736,007 24,256,484 26,743,226 29,783,651 32,813,783
before
Depreciation
Less: 0.00 0.00 667,449 667,450 667,451 667,452 667,453 667,454 667,455 667,455
Depreciation
Profit /Loss 12,586,401 14,194,911 15,264,572.00 16,939,171.00 19,029,269.00 21,068,555.00 23,589,031.00 26,075,772.00 29,116,196.00 32,146,328.00
Before Tax
Less: Tax 3,775,920.30 4,258,473.30 4,579,371.60 5,081,751.30 5,708,780.70 6,320,566.50 7,076,709.30 7,822,731.60 8,734,858.80 9,643,898.40
(30%)
Net Profit or 8,810,480.70 9,936,437.70 10,685,200.40 11,857,419.70 13,320,488.30 14,747,988.50 16,512,321.70 18,253,040.40 20,381,337.20 22,502,429.60
Loss After
Tax
40
BUSINESS PLAN FORMIXED USE BUILDING
41
BUSINESS PLAN FORMIXED USE BUILDING
INFLOW
Net sales
revenue 0
17,158,850 18,914,335 20,805,769 22,642,409 24,906,650 27,128,986 29,841,884 32,530,910 35,784,000 39,037,721
TOTAL
INFLOWS 0
17,158,850 18,914,335 20,805,769 22,642,409 24,906,650 27,128,986 29,841,884 32,530,910 35,784,000 39,037,721
OUTFLOWS
Investment
cost - - - - - - - -
15,000,000 - -
Operating cost
0 4,123,791 4,270,766 4,425,090 4,587,130 4,761,271 4,944,319 5,136,739 5,339,022 5,551,686 5,775,275
Income tax
0 3,775,920 4,258,473 4,579,371 5,081,751 5,708,780 6,320,566 7,076,709 7,822,731 8,734,858 9,643,898
TOTAL
8,529,23 12,213,44 13,161,75 14,286,54
OUTFLOWS 15,000,000 7,899,711 9,004,461 9,668,881 10,470,051 11,264,885 15,419,173
9 8 3 4
42
BUSINESS PLAN FORMIXED USE BUILDING
0 1 2 3 4 5 6 7 8 9 10
INFLFOWS
Inflow Funds
Own Equity
4,500,000
Long-term Loan 0 0
10,500,000
Inflow Operations
17,158,850 18,914,335 20,805,769 22,642,409 24,906,650 27,128,986 29,841,884 32,530,910 35,784,000 39,037,721
Sales revenue
0
17,158,850 18,914,335 20,805,769 22,642,409 24,906,650 27,128,986 29,841,884 32,530,910 35,784,000 39,037,721
TOTAL INFLOWS
15,000,000 17,158,850 18,914,335 20,805,769 22,642,409 24,906,650 27,128,986 29,841,884 32,530,910 35,784,000 39,037,721
OUTFLOWS
Investment cost 0 0 0 0 0 0 0 0 0 0
15,000,000
Operating cost 0 4,123,791 4,270,766 4,425,090 4,587,130 4,761,271 4,944,319 5,136,739 5,339,022 551,686 5,775,275
Financing Cost
· Principal 0 0 0 0 3,451,218 3,451,218 3,451,218 3,451,218 3,451,218 3,451,218 3,451,218
·Interest 0 448,65 448,65 448,658 448,65 448,65 448,658 448,658 448,658 448,658 448,658
43
BUSINESS PLAN FORMIXED USE BUILDING
8 8 8 8
Income Tax 3,775,92
0 4,258,473 4,579,371 5,081,751 5,708,780 6,320,566 7,076,709 7,822,731 8,734,858 9,643,898
0
TOTAL
8,348,369 8,977,897 9,453,119 13,568,757 14,369,927 15,164,761 16,113,324 17,061,629 13,186,420 19,319,049
OUTFLOWS 15,000,000
NET CASH FLOW 0 8,810,481 9,936,438 11,352,650 9,073,652 10,536,723 11,964,225 13,728,560 15,469,281 22,597,580 19,718,672
BEGINNING
0 0 8,810,481 18,746,919 30,099,569 39,173,221 49,709,944 61,674,169 75,402,729 90,872,010 113,469,590
CASH BALANCE
ENDING CASH
0 8,810,481 18,746,919 30,099,569 39,173,221 49,709,944 61,674,169 75,402,729 90,872,010 113,469,590 133,188,262
BALANCE
No Description
Total price
A. SUB-STRACTURE
1 excavation and earth works
279,570.67
2 concrete work 1,936,546.34
Sub total
1,216,117.01
B. SUPER STRACTURE
1 Concrete work
2,753,358.45
2 Block work
551,534.40
3 Roofing
171,108.00
4 Carpentry and joinery
323,760.00
5 Metal works 820,860.00
6 Finishing
1,111,379.44
7 Painting
275,798.88
8 Electrical installation
236,330.00
9 Sanitary installation
1,151,022.00
Subtotal
8,395,151.17
A+B
14,611,268.18
Vat (15%) 541,690.23
44
BUSINESS PLAN FORMIXED USE BUILDING
Grand total
10,152,958.40
45