TABLE OF CONTENTS
I. EXECUTIVE SUMMARY
1. INTRODUCTION………...................................................................................................…..4
2. Background…………………..……………………………………………………………..…5
2.1 The Industry of the Project……………………………………………………..……........5
2.2 The project Sites..................................................................................................................6
2.3 Project Benefits/Project Justification………………………………………………..….…9
2.4 The Promoter…………………………………………………..………………….…......10
3. General Description of the Area………………………………………………………...…...10
3.1 Location…………………………………………………………..……………………...10
3.2 Topography…………………………………………………………………..…...……...10
3.3 Soil Type…………………………………………………………………..……………..11
3.4 Economic Activity………………………………………………………………......…...11
4. The project description……………………………………………………………………....11
4.2 Object of the Project…………………………………………………………………......11
4.3 Technology and Techniques to be used……………………………………………….....12
4.4 Service Provision capacity and capacity Utilization…………………………………......13
5. Market study and plant capacity
5.1 International and Domestic demand for Hotel services………………………………….13
6. Land use plan and action plan……………………………………………………………..…15
6.1 Land Use Plan……………………………………………………………...…….………15
7. Organization and management………………………………………………………...….…16
7.1 Organizational structure …………………………………………………………………16
8. Financial study………………………………………………………………………….……19
8.1 Project capital and sources of finances…………………………………………..………19
8.2 Initial working capital estimation of the project …………………………………...……22
8.3 Estimated costs of salary expense…………………………………………………...…...22
8.4 Revenue and Revenue projection…………………………………………………..……24
8.5 Depreciation of the Fixed Assets……………………………………………………...…25
8.6 Basic Assumption’s ……………………………………………………………...…...…26
9. Financial Analysis……………………………………………………………………………27
10. Brief Environmental Impact Assessment (EIA) …………………………………………….28
Anne x I: 4-Star International Hotel Project Action Plan/ Gantt chart………………………29
EXECUTIVE SUMMARY
Hence, the project is feasible and important to be undertaken being the first of its kind in the sub-urban
area of the country having international quality and standard. Furthermore, the project would contribute
immensely to the development of tourism industry in particular and the country in general.
1. Introduction
I
n history of mankind and in no measure a particular country or society subdue itself to a humiliating
and grinding poverty as poverty is the indication of deprivation of basic necessities. Ethiopia, the
country with immense natural resource potential, is always cited as one of the home of the people on
the face of the earth stricken with famine, drought and poverty. What so ever the past and whether it was
desecrate or blessing, the existing situations in this country is the most important one. Today in Ethiopia
the gleaming hope for development is quite encouraging, the government policies concerning the private
investments are invigorating and to indicate some major steps taken the country in private investment
policy endeavors;
Capital goods and building materials may be imported duty-free by star designated hotels and
international standard restaurants.
Buses for tourist use may be imported duty free.
Four-wheel-drive passenger vehicles of the Land Cruiser type may be imported duty-free subject to
the conditions that Five brand new vehicles must be purchased within a period of one year in a
maximum of two consignments.
Any investor may employ duly qualified expatriate experts required for the operation of the business
and so on. Furthermore, to some extent the living standards of country’s citizens are improving. In
line with social changes people are trying to pull out themselves from primary economic activities to
civilized activities and improving their income. As income increases many people start to change their
living habits and tastes: with social changes facilities and type of social services should be changed
and modernized. One of the modern versions of social services is the development of modern hotels
and tourism sector. But due to known reasons there is no or very few hotels in many medium and
small towns of the country in general and the region in particular. A few existing ones are with
backward or poor facilities which are nuisance to customers and undesirable for country’s image.
Owing to this realities and the increasing demand for such facilities, this project is proposed to be
established in the area where there is no such hotel at all.
The Project Description
The Building
The Hotel and resort building originally is designed by the sister business enterprise of Bilen micro
Enterprise The splendid monumental property, which occupies almost the entire block between the
entrance to Gelan sub from hight way road from Addis Ababa and Bishoftu City. The construction has
been started in three years before and construction is carried out accordingly.
Currently, Bilen micro enterprise has planned to finalize the construction task in this year and inaugurated
the coming Ethiopia New Year.
The building has a total of 5000 square meter with having a potential area for expansion for further
development of the hotel building with additional facilities such as swimming pool and other services for
the customers.
The whole project site encompasses approximately 5000 square meters. The estimated net floor space of
5000 square meters is spread over three floors above ground floors. The following overview illustrates
the elements foreseen within the framework of the project:
5.2 Main Entrance and Lobby
The main entrance established at the main road from the high way from Addis Ababa to Shager city.
The main road provides a highly exclusive access to the main city entrance with having all facilities
banking hall and to the lobby (see Diagram 11). The integration of a generous lounge into the lobby will
serve guests either arriving or departing but also visitors as a “meeting point” of a special atmosphere due
to the outstanding ceiling height and the imposing stairs which lead to the restaurant in the mezzanine
floor. Furthermore, the attractiveness of the ground floor is enhanced by the integration of a state-of-the
art best design of bar & café.
The ground floor contains the following different rooms internally & externally; the rooms are:
Externally
1 Verenad
2 Toliet
Fig 1.
Bed room
Shower
Balcony
Built cupboard
2 Salon rooms
Salon
Bed room
Balcony
Bath Room
Kitchen
Built cupboard
Bed room
Shower
Balcony
Built in cupboard
2 Salon rooms
Salon
Bed room
Balcony
Bath Room
Kitchen
Built cupboard
1 Assembly hall
2 Cafeteria
3 Lobby bar
4 Rest room
5 balcony
5.7 Executive Rooms
From the first floor and second floor, the hotel will be equipped with 4 special guest
rooms and suites, all featuring the highest international luxury standards in terms of
size, layout, furnishings and equipment. Approximately 75 per cent of the total
amount of guest rooms will be designed as superior double rooms with an average size
of approximately 26 square meters. Apart from that, these 130 superior double rooms
are planned to be distributed over the floors one to three providing interiors of the
highest international luxury standards in terms of size, layout, furnishings and
equipment.
Furthermore, the remaining 25 per cent of all guest rooms will be designed as suites.
In order to attract the very high-end clientele, these 43 suites will be of classic and
timeless design in accordance with the historic features of the building. Depending on
type and size, the suites will feature spacious living and dining areas, one to three
bedrooms, state-of-the-art bathrooms equipped with wellness and spa facilities as well
as splendid balconies. Furthermore, the terraces of the presidential suites will be
equipped with outdoor whirlpools and lounges.
In general, the project is believed to have significant social and economic benefits
that accrue to the society, the region and the country beyond the financial returns
to its owner.3.4. Mission and goal
Mission
Mission of the particular project is to expand the standard star hotel system
and to give quality service.
To prove to other people that struggle for a better life and economic
independences can do business and bring change and can make a difference if
opportunities are given.
To become financially liquid and guaranteed more than ever.
Goal
Objectives are the goals toward which activities of the business are directed and
one of the most important functions the business owner must perform is setting
objectives. This important aims of this sole proprietorship business among
others include the following highly interrelated general goals with each other.
To create employment opportunities for 40 permanent and 60 causal
To achieve standa
Our Vision
In the next three years Bilen micro enter prise Hotel and Restaurant will become the first modern food
provider in Shager city with fresh and healthy foods backed by quick service.
Our Mission
Shager Gelan sub-city is a great place to eat, combining an intriguing atmosphere with excellent,
interesting food. Our mission is not only to have great tasting food, but have efficient and friendly service
because customer satisfaction is paramount. We want to be the restaurant choice for all families and
singles, young and old, male or female. Employee welfare will be equally important to our success.
Everyone will be treated fairly and with the utmost respect. We want our employees to feel a part of the
success of Hotel and Restaurant. Happy employees make happy guests. We will combine menu variety,
atmosphere, ambiance, special theme nights and a friendly staff to create a sense of 'place' in order to
reach our goal of overall value in the dining/entertainment experience. We want fair profits for the
owners, and a rewarding place to work for the employees.
Our Strategy
Our strategy is simple; we intend to succeed by giving people a combination of healthy, fresh and quality
foods in an environment that appeals to a wide and varied group of successful people. We will focus on
maintaining quality and establishing a strong identity in our community. Our main focus in marketing
will be to increase customer awareness in the surrounding communities.
We will direct all our tactics and programs toward the goal of explaining who we are and what we do. We
will keep our standards high and executes the concept so that word of mouth will be our main market
force
Example of
Adventure
clamping park
design
INFRASTRUCTURE: Sales point, storage for equipment, toilets and preferably a visitor facilities (building lavou, tent, sheds, etc)
depending on nearby locations, climate
. Base jump
It will be built at 35 m high jumping pole. We will use different types of braking systems. Høyt & Lavt are
authorized constructor and provide service centre or several different devices.
2. 4.1.e. Indoor adventure center
Weather is always a challenge either to wet, cold or even warm. Off course the indoor
experience differs from being outside in the nature, but still the excitement of challenges,
physical activity and mastery are in ingrediences. We will developed a center with
diversity and activities for broad range of users. Sport climbers, families, kids, beginners,
corporates.
LAYOUT PLANNING
The following are the proposed layout required for the Hotel and Resort:
Hotel
Rooms & Suites
The hotel will be of stylish, comfortable, well-furnished and air-conditioned
rooms with contemporary luxury and gracious service.
The hotel will be having 2 nos. of restaurant, a Lounge Bar and a coffee
shop, which will be offering a choice of continental, Chinese and variety of
food from Indian cuisine, with live piano music, and one open restaurant
with the above amenities for the outside visitors.
The bar will be well stocked with best of spirit and wine where guests can
spend their time with gossiping watching television.
Other Facilities in
hotel Travel Desk
The hotel will also have a Travel Desk, which will help visitors to
gather information and sketch a tour for visiting the tourist place.
Pick up Facility
The hotel will also having a Pick up facility, the company will be
buying vehicles to pick the guests from the suitable place.
Business Center
The hotel will also provide the currency exchange facility to overseas guests.
The Resort will be having good nos. of cottages with a refreshing mix of style
and spacious elegance, our guest rooms and suites will be offering peace and
tranquility as well as the comforts of modern day living.
Ayurveda Centre
The Resort Complex will be having a separate area for the kids; Kids
Arena for children to have fun and play all the time while visiting the Resort.
The Resort will be having an area for board games, which will provide
additional options for the guests to spend excellence time in the Resort.
GYMNASIUM
A gymnasium will be surrounded by state of the art equipment from the
Life Fitness, Ethiopia , the World’s undisputed leader in Gym
Equipment. Equipment will be is available to tone up body muscles and
rejuvenate. Visitors can sweat out superfluous body fat and discover the
fresh self
Garden
Restricted Service
Some hotels operate a restricted service during less busy months. This may be a reduction of the
restaurant service, or some leisure facilities may be unavailable. Please check when booking.
No Dogs
No dogs allowed in bedrooms. Guide dogs for the blind may be accepted as an exception to this
rule. However, even where hotels allow dogs, they may exclude some breeds, and may exclude
dogs from certain areas of the hotel, especially the dining room. It is essential to check the
conditions before booking.
Night Porter
At some hotels, the night porter may be there only between certain hours or on certain nights .
However, four and five star hotels must have a night porter always on duty.
Entertainment
This indicates that entertainment should be available at least once a week throughout the year.
However, some hotels may provide entertainment in the summer season or at other specified
times.
No children
This indicates that children cannot be accommodated. A minimum age may be specified (e.g. No
children 4yrs - no children under four years old). If this does not appear in the entry, it means
that the hotel will accommodate children, but may have no special facilities for them (e.g. no
cots or high chairs). It is essential to check when booking.
Conference Facilities
This denotes that conference facilities are available with maximum numbers that can be
accommodated theatre style; classroom style; boardroom style and the minimum overnight
delegate rate.
Meals
Details of the style of food, last dinner orders, and likely price range are given. If there is a fixed-
price menu or menus, this is the price range quoted. V meals indicates that a choice of vegetarian
dishes is normally available.
In some parts of Britain, particularly in Scotland, high tea (i.e., a savory dish, followed by bread
and butter, scones, cake, etc.), is served in the early evening instead of dinner. However, the
alternative of dinner may be available on request. The last time at which high tea or dinner may
be ordered is shown, but there may be some variation at weekends. On Sunday some hotels serve
the main meal at lunch time, and only a cold supper in the evening.
accepts credit or charge cards, the information is shown in its entry. It is advisable to publish and
notify customer the policy regarding the use of credit cards.
Complaints
A crisis management procedure is a must especially in the case of guest complaints. Fire and bad
weather
Smoking Regulations
Hotel should state clearly its policy on smoking. Ensure that where smoking is allowed there are
designated areas for non-smokers inclusive of rooms away from smokers.
The envisaged project can be justified by the benefits it delivers to the country, the promoter and
the local communities. The main justifying points are explained as follows;
The project will contribute immensely to the tourism industry in particular and changing of
country’s image in general by creating internationally accepted standard facilities,
The investment will benefit the country in generating hard currencies and in boosting the
GTP program,
The project will benefit the local communities through creating job opportunities and markets
for their products to be supplied for the hotel.
3.1. Location
The envisaged two star hotel and restaurant service project is to be located in the Oromia
regional state, shager Gelan sub-city . The envisaged town is one of the growing towns in the
region and is found adjacent to Addis Ababa, the Federal Capital of Ethiopia from the north side.
Gelan sub-city has favorable climate, topography ad people with rich diversified cultural values
creating high potential for tourist attraction. Theses attraction can be clearly categorized and
understood as natural science environmental historical and man cultural and ethic.
The above mention facts are the strong basis to think that the town will developed being an
attractive town for investment and commerce.
However such center of block and other cement product is one of such facility intended to help
the development of Gelan sub-city as center of manufacturing interaction.
For construction big villas building & ware houses in sub-city Gelan is simply possible because
the most parts of soil in Gelan sub-city is red soil.
4.4. Population
The total population of the town was 201,956 in 2009.Out of the total population 133,351 were
rural and 68,605 were urban populations. The economically active population (15-64) constituted
44.2% of the total population. The average family sizes for rural and urban areas were 5.0 and
4.6 persons respectively. The9 crude population density was 235 persons/km2 in the mentioned
year.
The majority of the populations of the town are engaged in different commercial activities
including agricultural activities. There are also peoples who are employed in
Various governmental & non-governmental organizations. Currently private investment
activities are also widely undertaken in the town.
own for its real-estate development and future establishment of industrial city.
The restaurant will be located just minutes from down town, which provides shopping, dining, and
entertainment. The restaurant is also conveniently located, just three blocks from Local Bay shopping center.
Other advantages of the chosen location include:
Plenty of parking, garages, and additional storage area available
Excellent central location with easy access to major destinations, freeways and other
transportation means
A recent new commercial complex opening, just across the street, that will attract many
potential customers to our immediate vicinity
Strategically located on one of the busiest streets in downtown.
High profile area with easy access from all parts of town
Proximity to the business community; there are more than five hundred businesses in the
area
Proximity to trendy, upscale restaurants and recreational facilities
All utilities required for operating a restaurant are available
Facility location is determining the best geographic location for a business’s facility.
Facility location decisions are particularly important for two reasons.
First, they require long-term commitments of investing in the facilities, which means that
mistakes can be difficult to correct. Second, these decisions require sizable financial investment
and can have a large impact on operating costs and revenues. Poor location can result
in high transportation costs, inadequate supplies of raw materials and labor, loss of
competitive advantage, and financial loss. Businesses therefore have to think long and
hard about where to locate a new facility.
Location is a critical factor in planning a restaurant. The ability to capture sufficient customer
volume from existing residents, day-workers and tourists is essential in estimating the feasibility
of restaurants and other culinary venues.
Traffic patterns can provide an important indicator of the level of exposure a new business or
Eating venue (such as a farmer’s market) might receive at a specific downtown location. It is
also important to identify "demand generators," such as company offices and manufacturing
firms, hospitals, colleges and retail stores. These types of businesses typically generate a
significant amount of food and beverage business, often from nonresidents coming into the
community. Finally, market demand for our restaurant may be impacted by changes in
employment, expansion or new construction of commercial buildings, new Residential housing,
and street and transit improvements.
Our management is expected to use resources wisely, operate profitably, pay debts, and abide by laws
and regulations. Our management philosophy is based on team work, responsibility, and mutual respect.
People who work in other restaurant would want to be part of our team because we operate in an
environment that encourages creativity, diversity, growth, and performance.
3.2. Topography
As the town is found bordering the Addis Ababa city, the topography of the town is almost
similar to that of Addis Ababa. Hence, its is found at the high altitude of the country having an
altitude 2200-2400. The area experiences high rainfall having an annual mean rainfall of 1500-
1800mm. Whereas, its mean annual temperature ranges between 12 and 22C 0 . The scene of the
area is beautiful having a yerar mountain from the north-west direction and is so attractive for
tourists and visitors.
3.3. Soil type
Soils found around Addis special from the north-east side are characterized with their black-
verty, brownish and scantly red colors. Obviously the black and brownish soils are having
workability problems during rainy and dry seasons alike but the red soils are best for any
agricultural and construction activities as they do not show any expansiveness and shrinkage
characteristics with weather conditions.
3.4. Economic activity
The livelihood of the local community is primarily dependent on agricultural activities like crop
farming and animal husbandry. But now the investment activities are being expanded and hence,
many young people are employed as employee in investment projects or starting their own
businesses through organizing themselves in micro and small Enterprises. As the town is
adjacent of Addis Ababa city, many people are linking their livelihood with the city's trade
activities.
Preparation Resource
Start Site clearing
of design mobiliation
Supper Sub
Roofing
structure structure Excavation
works
works works
Start
Recruitment Furnish
operations
Fig1. Work process flow for hotel construction and service provisions
2.Material inputs
2.1 Raw material
The materials that go into the final product are called raw materials. This term is somewhat
misleading because it seems to imply unprocessed natural resources like wood pulp or iron ore.
Actually, raw materials refer to any materials that are used in the final product; and the finished
product of one company can become the raw materials of another company. Required raw
materials for hotel and restaurant service include food items, beverages (hot and cold), room
clothing, detergents and the likes. All raw materials are available in the domestic market.
An important aspect of technical analysis is concerned with defining the materials and utilities
required; specifying their properties in is some detail, and setting up their supply programmed.
There is a close relationship between the definition of input requirements and other aspects of
project formulation, such as the definition of plant capacity, location and selection of technology
and equipment, as these inevitably interact with one another.
Material inputs and utilities may be classified into four broad categories: (i) Raw materials, (ii)
Processed industrial materials and components, (iii) Auxiliary materials and factory supplies, and
(iv) Utilities.
The required raw material of our restaurant includes the purchase of imputes such as; meat,
onion, garlic, carrot, paper…etc. of most of these inputs will be brought from the Shager city.
The remaining inputs’ such as carrot, onion, key-sir, oil… etc. will be purchased from different
region in the morning from low bid suppliers who deliver these supplies reliably.
In addition to basic raw materials and processed materials, the restaurant project requires various
auxiliary materials and factory supplies. Among those needed are: -
Decoration
Attractive lamps
Modern food pictures
Cleaning Material (Detergent, Mop, Broom, Towel, Garbage Can etc.)
These auxiliary materials and supplies will also be supplied from
4. Market prospect
Marketing opportunities for hotel services are directly linked with the level of the
country’s/regional/ economic and tourism development. As the region’/Country’s economy
develops, the citizens’ income improves and as income of the citizens improves they certainly
start looking for knowing their surrounding and their whole nation historical and natural
attraction hence the domestic tourist travelling culture will be developed. Similarly, as the
country’s infrastructure developed and its stability and security issues are insured, international
tourist will develop interests in travelling in the country visiting its historical and natural
attractions. Currently, the country’s economic and social development is on the right track and
the future of this nation is shimmering and the hotel and tourism market development will also
do the same.
adopted in Ethiopia and hotels are classified into categories with stars from one to five and hotels
without stars as other countries do.
It is possible to see the number of hotels, the rooms they have and the number of beds they
constitute in the following table.
Table2: Existing Hotels in Ethiopia
No of Average Room/Bed per
C) Sales Promotion – are those promotional activities that are intended to stimulate customer
demand and improve the marketing performance of sellers.
Companies use sales promotion tools to create a stronger and quicker response. Some of the
sales promotional tools are;
Public relation and publicity – public relation is a broad overall communication to influence
various groups attitude towards the organization and/or its product.
The old name for public relation was publicity, which was seen simply as activities to promote
a company or its product by planning news about it in the media not paid for by the sponsor.
The appeal of public relation and publicity is based on their three distinctive qualities.
1 High credibility – news stories and features are more authentic and credible to readers
than advertising.
2 Ability to catch buyers off guard – it can reach many prospects who prefer to avoid
salespeople and advertising. The message gets to the buyer as news rather than as a sale
directed communication.
3 Dramatization – like advertising, public relation has the potential for dramatizing a
company or product.
E) Direct Marketing – use of mail, telephone, fax, e-mail and other non-personal contact tools
to communicate directly with or solicit a direct response from a specified customer and
prospects.
Finally, companies must consider several factors in developing their promotion mix the type of
product, market in which they are selling, whether to use a push or pull strategy, how ready
consumers are ready to make purchase, the product’s stage in the product life cycle and the
company’s market rank.
TECHNICAL STUDY
The project owner interest, as regards to how the overall building design
looks like and the level of service to be rendered by the envisaged project, is
dependent on the area at which the buildings to be placed. The owner has
already decided to commit himself to construct a hotel and resort having the
full knowledge what is required by the national and international standard of
Hotels in Ethiopia. The standard by the way its exhaustiveness as well as
being explicitly specific on the level of the service expected under the
selected category, determines also the physical and financial requirement of
Fig2. Organizational Structure for Hotel Project
General Manager
Reception
Accomodation Procurement
and sales
Hotel Security
17 Laundry and salon Literate 4th and > " 2 1800 43,200
worker
Total 50+50 1104000
NB:- No of manpower is estimated considering two shift (24hrs) services as it is star designated hotel
7. Financial study
Total investment capital required to establish and run the envisaged project is estimated at birr
5,000,000 Million, the project will be financed Owner equity contribution 30% that means
1,500,000 and Bank loan 70% (3,500,000) Detail financial analysis of the project is depicted in
the table blow
Table Total Initial Investment Capital
No Description Cost
1 Fixed Investment
1.1 Land, Building and Construction 5,600,000 0.00
1.2 Machines and Equipment’s 4,400,000 0.00
1.3 Vehicles and Motors 600,000 0.00
1.4 Office Furniture and Equipment 400,000 0.00
Total Fixed Investment Cost 11,000,000 0.00
2 Operating Expense 0.00
2.1 Raw Materials Purchase and Products 4,000,000 0.00
2.2 Salary Expense 2,000,000 0.00
2.3 Other Operating Expense 600,000 0.00
4 Storage “
100 1,000 300,000
6 Generator room “
50 1,100 55,000
7 Incinerator “
80 1,100 88,000
9 Guard/Janitor room “
70 1,050 73,500
13 Intra-road construction km
1 800,000 800,000
Unit cost
No Particulars Unit Qty Total cost (Br.)
(Br.)
I Equipment and Machines
1 Boiler Pcs 1 250,000 250,000.00
2 Assorted Kitchen utensils and - -
equipment 500,000.00
3 Beds and bed clothes Psc 100 40,000 50,000.00
4 Bar and restaurant furniture - - 600,000 60,000.00
5 Bed room chairs (2 in each) Pcs - 1,750 89,000.00
6 Bed room tables “ - 2,250 79,000.00
7 Lobby equipment “ - 55,000.00
8 Bathing room, Jacuzzi and psc -
swimming pool equipment 750,000.00
9 Sauna, steam bathing equipment 400,000.00
10 Massaging equipment 175,000.00
11 First aid equipment 250,000.00
12 Mini Refrigerator " 100 2,500 250,000.00
13 Communication apparatus " 100 1,250 125,000.00
14 Other related expenses “ - 300,000.00
15 Security equipment " 200,000.00
Sub. Total “ 4,400,000.00
II Vehicles and related machines
1 Van carrier pcs 1 600,000 600,000.00
Sub Total 3,675,000.00
III Computers and Office furniture “ - 400,000
Sub Total 400,000.00
Total 5,400,000.00
The major raw materials and auxiliaries required for the production shown in Table 4.1 below.
All the raw and auxiliary materials are to be imported
B. Depreciation
Building…………………………………………………………………………….5%
Machinery and Equipment ………………………………………………………..15%
Office Furniture……………………………………………………………………20%
Vehicles ………………………………………………………………………..…..15%
C. Working Capital
Accounts Receivable…………………………………………………………….30 days
Raw material Local …………………………………………………………..…..30 days
Work in progress…………………………………………………………………5 days
Accommodations
1
service
1. Deluxe/Suit/ rooms
15 23 30 2500 11250000 16875000 22500000
(No)
3. Economic
15 23 30 1400 6300000 9450000 12600000
rooms(No)
2 Hotel services
1. Alcoholic beverages
1000 1500 2000 2000 2000000 3000000 4000000
(lit/year)
7,225,00
Sub Total 0 10,837,500 12,050,000
Other services
1. Meeting services 6 9 12 3000 18,000 27,000 216,000
(occasion)
3
2. Weeding 12 18 24 2500 30,000 45,000 720,000
services(occasion)
Asset
Current Asset
Cash 1,500,000
Fixed Asset
Vehicles 600,000
Total Asset
Liability
Capital
Tsigu M.E
age 46
“A Two Star Hotel”
0 0
Cumulative balance 37,264,15 49,760,20
0 24,656,100 0 0
C. FINANCIAL EVALUATION
1. Profitability
Based on the projected profit and loss statement, the project will generate a profit through out
its operation life. Annual net profit after tax will grow from Birr 24 million to Birr 49.20
million during the life of the project. Moreover, at the end of the project life the accumulated
cash flow amounts to Birr 133.27 million.
2. Ratios
In financial analysis financial ratios and efficiency ratios are used as an index or yardstick for
evaluating the financial position of a firm. It is also an indicator for the strength and weakness
of the firm or a project. Using the year-end balance sheet figures and other relevant data, the
most important ratios such as return on sales which is computed by dividing net income by
revenue, return on assets ( operating income divided by assets), return on equity ( net profit
divided by equity) and return on total investment ( net profit plus interest divided by total
investment) has been carried out over the period of the project life and all the results are found
to be satisfactory.
3. Break-even Analysis
The break-even analysis establishes a relationship between operation costs and revenues. It
indicates the level at which costs and revenue are in equilibrium. To this end, the break-even
point of the project including cost of finance when it starts to operate at full capacity ( year 3)
is estimated by using income statement projection.
BE = Fixed Cost = 27 %
4. Payback Period
Tsigu M.E
age 47
“A Two Star Hotel”
The pay back period, also called pay – off period is defined as the period required to recover
the original investment outlay through the accumulated net cash flows earned by the project.
Accordingly, based on the projected cash flow it is estimated that the project’s initial
investment will be fully recovered within 7 years.
The internal rate of return (IRR) is the annualized effective compounded return rate that can be
earned on the invested capital, i.e., the yield on the investment. Put another way, the internal
rate of return for an investment is the discount rate that makes the net present value of the
investment's income stream total to zero. It is an indicator of the efficiency or quality of an
investment. A project is a good investment proposition if its IRR is greater than the rate of
return that could be earned by alternate investments or putting the money in a bank account.
Accordingly, the IRR of this porject is computed to be 19.28 % indicating the vaiability of
the project.
Net present value (NPV) is defined as the total present ( discounted) value of a time series of
cash flows. NPV aggregates cash flows that occur during different periods of time during the
life of a project in to a common measuring unit i.e. present value. It is a standard method for
using the time value of money to appraise long-term projects. NPV is an indicator of how
much value an investment or project adds to the capital invested. In principal a project is
accepted if the NPV is non-negative.
Accordingly, the net present value of the project at 8.5% discount rate is found to be Birr
30.09 million which is acceptable.
Tsigu M.E
age 48
“A Two Star Hotel”
D. ECONOMIC BENEFITS
The project can create employment for 100 persons. In addition to supply of the domestic
needs, the project will generate Birr 51 million in terms of tax revenue. The project creates
backward linkage with cement, gravel and sand producers and forward linkage with the
construction sector.
Tsigu M.E
age 49
“A Two Star Hotel”
age 50
Tsigu M.E