Professional Documents
Culture Documents
Furthermore, every enterprise wants to accomplish the desired objective at minimum cost also.
Sometimes it may be desirable to extend the project duration if there is considerable saving in
costs. Thus time- cost relationship is of great significance in project management.
The project cost consist of both direct and indirect costs, direct costs are related with the
duration of the activities and include costs on inputs to perform that activity. Indirect costs
include overhead costs, the specified date.
The duration of the project can be shortened by systematic analysis of Critical Path activities,
crashing costs and corresponding costs and corresponding affect of indirect costs. For this time-
cost relationship should be critically examined.
The relationship can be studied with the help of the following costs and time values:
(i) Normal Time: Normal time is the standard time that an estimator would usually allow
for an activity.
(ii) Normal Cost: This is the direct cost required to complete the activity in normal time
duration.
(iii) Crash Cost and Time: The normal time of an activity can be reduced by incurring
additional cost. The additional cost may be due to hiring additional personnel,
machinery, working overtime etc. this reduction is termed as 'Crashing'. However, there
is a minimum time beyond which as activity time cannot be crashed, even by incurring
additional cost. This time is known as 'Crash time' and the direct cost corresponding to
it as 'Crash cost'.
(iv) Project Normal cost/time: The sum of the normal costs of all activities of the project
is known as Project Normal cost and the sum of the normal times of activities in the
critical path of the project is known as Project Normal time.
(v) Optimal Project duration: The optimal project duration is the one which results in
minimum overall cost. This is determined from the normal cost of each activity, normal
duration, the cost of crashing, the extent to which it can be crashed and the indirect
costs per unit time of project duration. Beyond the optimal project duration, it is not
economical to reduce the duration.
(vi) Activity Cost slope: The cost slop indicates the additional cost incurred per unit of time
saved in reducing the duration.