Professional Documents
Culture Documents
scope.
1 - Time
It's imperative for both the project manager and the organization to have an estimated
cost when undertaking a project. Budgets will ensure that project is developed or
implemented below a certain cost.
Sometimes, project managers have to allocate additional resources in order to meet
the deadlines with a penalty of additional project costs.
SCOPE:
Scope looks at the outcome of the project undertaken. This consists of a list of
deliverables, which need to be addressed by the project team.
A successful project manager will know to manage both the scope of the project and
any change in scope which impacts time and cost.
1. TOPT
This is the fastest time an activity can be completed. For this, the assumption is made
that all the necessary resources are available and all predecessor activities are
completed as planned.
2. TLIKELY
Most of the times, project managers are asked only to submit one estimate. In that
case, this is the estimate that goes to the upper management.
3. TPESS
This is the maximum time required to complete an activity. In this case, it is assumed
that many things go wrong related to the activity. A lot of rework and resource
unavailability are assumed when this estimation is derived.
Project management can be understood as a systematic way of planning, scheduling,
executing, monitoring, controlling the different aspects of the project, so as to attain the
goal made at the time of project formulation. PERT and CPM are the two network-based
project management techniques, which exhibit the flow and sequence of the activities
and events. Program (Project) Management and Review Technique (PERT) is
appropriate for the projects where the time needed to complete different activities are
not known.
On the other hand, the Critical Path Method or CPM is apt for the projects which are
recurring in nature.The two scheduling methods use a common approach for designing
the network and for ascertaining its critical path. They are used in the successful
completion of a project and hence used in conjunction with each other. There are three
times estimates in PERT, i.e. optimistic time (to), most likely time(tm), pessimistic time
(tp). On the other hand, there is only one estimate in CPM.PERT technique is best
suited for a high precision time estimate, whereas CPM is appropriate for a reasonable
time estimate. Crashing is a compression technique applied to CPM, to shorten the
project duration, along with the least additional cost. The crashing concept is not
applicable to PERT.
AOA – Activity on Arrow: networks show each activity as an arrow, and the nodes represent the starting
and ending points
1.It is composed of arrows and nodes. The arrows represent the activities and nodes
represent the events.
2.Each activity carries a brief description usually printed on the logical diagram, the
activity name or symbol and the time duration.
3.At present, this method seems to be the most popular method and it was the first
method to be introduced, developed and computerized
AON – Activity on Node: networks show each activity as a node and arrows show the immediate
predecessor activities
1.In A-O-N networks, the nodes represent the activities and the arrows, their
interdependencies or precedence relationships.
2.Nodes are usually represented by squares or rectangles, but circles and other
convenient geometrical shapes may also be used.
3.Activity number and description are written within the boxes representing the nodes.
4.Length and direction of the arrows have no significance as they indicate only the
dependency of one activity on another.
The different kinds of costs that make up the whole cost of a project are:
● Direct cost
● Indirect cost
● Fixed cost
● Variable cost
● Sunk cost
Direct cost
Direct costs are those directly linked to doing the work of the project. For example, this could
include hiring specialised contractors, buying software licences or commissioning your new
building.
Indirect cost
These costs are not specifically linked to your project but are the cost of doing business overall.
Examples are heating, lighting, office space rental (unless your project gets its own offices hired
specially), stocking the communal coffee machine and so on.
Fixed cost
Fixed costs are everything that is a one-off charge. These fees are not linked to how long your
project goes on for. So if you need to pay for one-time advertising to secure a specialist software
engineer, or you are paying for a day of Agile consultancy to help you start the project up the best
way, those are fixed costs.
Variable cost
These are the opposite of fixed costs - charges that change with the length of your project. It's
more expensive to pay staff salaries over a 12 month project than a 6 month one. Machine hire over
8 weeks is more than for 3 weeks.
Sunk cost
These are costs that have already been incurred. They could be made up of any of the types of cost
above but the point is that they have happened. The money has gone.
"Sunk cost is a loss which should not play any part in determining the future of the project."
Unfortunately, project sponsors and other senior executives (and even project managers) often
value completion over usefulness and it does take courage to suggest to your sponsor that you
stop a project that has already seen significant investment.
1. Fixed Cost
This is defined as the cost spent once for a particular point of time. The purchase
of equipment, machinery etc comes under fixed cost assets.
2. Time-Related Cost
Time-related cost is the cost spend for a particular activity for a given duration.
The cost spent on wages, equipment and building rents etc comes under this
category.
The main sections coming under indirect costs are personnel costs, security costs,
and administration costs. These costs do not have a direct connection with the
construction project.
Project overhead costs can either be fixed or time-related costs. Different costs
coming under overhead costs are the costs of stores, safety facilities, workshops,
offices, staffs and parking facilities. All those plants that are required to support
the working crews will come under this cost.
The general overhead expense and cost are found reasonable through continuous
monitoring of the company expenses. The general overhead costs account for 2 to
5 % of the contract direct costs.
The amount of the general overhead that should be allocated to a specific project
equals:
1.Figurehead role- CM is the legal and social head of the project who takes decision about the projects
progress .
2. leadership role - The CM leads the team of skilled and experienced people who collectively strive to
execute
3.liaisoning role - Deals with activities that involve correspondence with government officials,
contractors, vendors, professionals, consultants etc.
4.monitoring role - Plans the approach for performing tasks, implements time, cost and quality planning
and monitors the system to ensure results
5.disseminator’s role -Transmits relevant information from external sources and internal systems to the
concerned people at site
6.spokesperson's role =The sole representative through whom communication to the client or other
external parties happen
7.entrepreneur’s role -Seeks and identifies opportunities to promote improvements and changes in the
worksite