RINCIAN

DAFTAR KUANTITAS DAN HARGA

PEKERJAAN : Pembangunan Gedung Rawat Jiwa Intensif UPTD Rumah Sakit Jiwa
LOKASI : Kabupaten Bandung Barat
TAHUN ANGGARAN : 2022

PEKERJAAN YANG SUDAH DI PEKERJAAN YANG BELUM DI


NO. URAIAN PEKERJAAN VOL. SAT. KERJAKAN KERJAKAN KETERANGAN
VOL. SAT. VOL. SAT.
I PEKERJAAN PERSIAPAN
A. SISTEM MANAGEMEN KESEHATAN DAN KESELAMATAN KERJA (SMK3) KONSTRUKSI
1 Pekerjaan SMK3K 1.00 Ls

B. PERSIAPAN LAPANGAN
1 Pek. Pemasangan Papan Nama Proyek 1.00 Unit
2 Pek. Pengukuran dan Pemasangan Bouwplank 179.96 m1
3 Pek. Sewa Office Container 40 Feet ( Direksikeet ) + Mobilisasi dan Demobilasasi 6.00 Bln
4 Pek. Pagar Pengaman Proyek 213.39 m1
5 Pengadaan Air Dan Listrik Kerja 1.00 Ls
II PEKERJAAN STRUKTUR

A. STRUKTUR BAWAH
Ref. Produk, PC: SCG
Ref. Produk Tiang Pancang : Beton Elemenindo Perkasa (BEP)
1 Pek. Pasang Tiang Pancang Beton Prestressed Square □25x25, Mutu Beton K-500
a Mobilisasi dan Demobilisasi Alat Pancang Hydraulic 120 ton 1.00 Ls
b Pengadaan/Penyediaan Tiang Pancang Beton Square □25x25 (D13) 1,230.00 m1
c Penetrasi/Pemancangan Tiang Pancang Beton Square □25x25 (D13) 1,230.00 m1
d Pemotongan Kepala Tiang yang Tidak Tertanam 102.00 ttk
e Dolly 103.00 ttk
f Pile Driving Analyzer (PDA) Test 3.00 ttk
2 Bobokan Kepala Pondasi Tiang yang Masuk pada Pile Cap 205.00 ttk
3 Pek. Galian Tanah Biasa Kedalaman ± 1,00 m 221.13 m3
4 Pek. Urugan Pasir, t = 5 cm 17.87 m3
5 Pek. Lantai Kerja, Beton Mutu K-100, Slump 3-6 cm, w/c = 0,87, t = 5 cm 17.87 m3
6 Pek. Pile Cap Type P1 75x75x60
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 120.06 kg

Page 1
PEKERJAAN YANG SUDAH DI PEKERJAAN YANG BELUM DI
NO. URAIAN PEKERJAAN VOL. SAT. KERJAKAN KERJAKAN KETERANGAN
VOL. SAT. VOL. SAT.
Bekisting, Pas. Bata Merah, t. 1/2 Bata, 1 PC : 5 PP 4.08 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 0.68 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 280.44 kg
Bekisting, Pas. Bata Merah, t. 1/2 Bata, 1 PC : 5 PP 5.40 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 1.35 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 11,404.76 kg
Bekisting, Pas. Bata Merah, t. 1/2 Bata, 1 PC : 5 PP 214.11 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 71.37 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 747.85 kg
Bekisting, Pas. Bata Merah, t. 1/2 Bata, 1 PC : 5 PP 15.36 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 5.40 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 3,409.27 kg
Bekisting Kolom Struktur 64.32 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 6.43 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 63.64 kg
Bekisting Kolom Struktur 1.44 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 0.11 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 384.02 kg
Bekisting, Pas. Bata Merah, t. 1/2 Bata, 1 PC : 5 PP 11.52 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 1.73 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 2,221.30 kg
Bekisting, Pas. Bata Merah, t. 1/2 Bata, 1 PC : 5 PP 123.84 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 15.48 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 6,605.42 kg
Bekisting, Pas. Bata Merah, t. 1/2 Bata, 1 PC : 5 PP 230.40 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 28.80 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 1,396.63 kg
Bekisting, Pas. Bata Merah, t. 1/2 Bata, 1 PC : 5 PP 129.76 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 16.22 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 1,138.91 kg
Bekisting, Pas. Bata Merah, t. 1/2 Bata, 1 PC : 5 PP 145.44 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 10.91 m3
Baja Tulangan Wiremesh M8, U50 7,748.98 kg
Bekisting dengan Papan 3x20 29.81 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 213.32 m3
Baja Tulangan Wiremesh M8, U50 105.93 kg

Page 2
PEKERJAAN YANG SUDAH DI PEKERJAAN YANG BELUM DI
NO. URAIAN PEKERJAAN VOL. SAT. KERJAKAN KERJAKAN KETERANGAN
VOL. SAT. VOL. SAT.
Bekisting dengan Papan 3x20 2.52 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 1.94 m3
Baja Tulangan Wiremesh M8, U50 437.22 kg
Bekisting Plat Dinding 40.32 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 8.02 m3
Pek. Water Stop PVC Lebar 230mm-320mm 12.60 m1
20 Pek. Urugan Tanah Kembali 93.56 m3
21 Pek. Peninggian Elevasi Bangunan Dengan Tanah Dari Sumber Pilihan 724.73 m3
22 Pek. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 5PP 7.70 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 14,983.03 kg
Bekisting Kolom Struktur 428.80 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 42.88 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 260.11 kg
Bekisting Kolom Struktur 9.60 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 0.72 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 3,475.01 kg
Bekisting Balok Struktur 252.96 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 34.27 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 5,841.02 kg
Bekisting Balok Struktur 313.20 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 40.60 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 1,571.01 kg
Bekisting Balok Struktur 90.00 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 11.34 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 3,023.19 kg
Bekisting Balok Struktur 129.57 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 12.34 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 941.89 kg
Bekisting Balok Struktur 89.20 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 9.37 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 828.14 kg
Bekisting Balok Struktur 60.99 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 5.62 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 1,534.70 kg
Bekisting Balok Struktur 64.68 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 4.62 m3

Page 3
PEKERJAAN YANG SUDAH DI PEKERJAAN YANG BELUM DI
NO. URAIAN PEKERJAAN VOL. SAT. KERJAKAN KERJAKAN KETERANGAN
VOL. SAT. VOL. SAT.
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 706.12 kg
Bekisting Balok Struktur 67.20 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 4.80 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 70.20 kg
Bekisting Balok Struktur 7.01 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 0.42 m3
Baja Tulangan Wiremesh M8, U50 7,368.92 kg
Bekisting Plat Lantai dengan Metal Sheet 1,352.38 m2
Bekisting dengan Papan 3x20 31.59 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 175.81 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 13,152.37 kg
Bekisting Kolom Struktur 444.88 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 44.49 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 269.30 kg
Bekisting Kolom Struktur 9.96 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 0.75 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 255.28 kg
Bekisting Balok Struktur 18.60 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 2.52 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 319.63 kg
Bekisting Balok Struktur 21.06 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 2.73 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 3,091.37 kg
Bekisting Balok Struktur 83.95 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 10.22 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 276.67 kg
Bekisting Balok Struktur 11.55 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 1.10 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 328.31 kg
Bekisting Balok Struktur 28.80 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 3.02 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 249.89 kg
Bekisting Balok Struktur 18.24 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 1.68 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 201.48 kg
Bekisting Balok Struktur 11.34 m2

Page 4
PEKERJAAN YANG SUDAH DI PEKERJAAN YANG BELUM DI
NO. URAIAN PEKERJAAN VOL. SAT. KERJAKAN KERJAKAN KETERANGAN
VOL. SAT. VOL. SAT.
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 1.00 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 369.29 kg
Bekisting Balok Struktur 23.80 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 1.70 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 4,152.20 kg
Bekisting Balok Struktur 298.56 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 22.39 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 2,006.27 kg
Bekisting Balok Struktur 177.45 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 10.65 m3
Baja Tulangan Wiremesh M8, U50 1,441.57 kg
Bekisting Plat Lantai dengan Metal Sheet 264.56 m2
Bekisting dengan Papan 3x20 13.66 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 34.39 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 106.58 kg
Bekisting Kolom Struktur 2.56 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 0.26 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 1,418.38 kg
Bekisting Kolom Struktur 45.36 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 3.97 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 1,338.54 kg
Bekisting Balok Struktur 38.08 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 3.36 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 353.30 kg
Bekisting Balok Struktur 24.48 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 2.16 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 350.48 kg
Bekisting Balok Struktur 14.00 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 1.00 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 246.17 kg
Bekisting Balok Struktur 22.80 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 1.37 m3
Baja Tulangan Wiremesh M8, U50 875.52 kg
Bekisting Plat Lantai dengan Metal Sheet 160.68 m2
Bekisting dengan Papan 3x20 6.97 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 20.89 m3

Page 5
PEKERJAAN YANG SUDAH DI PEKERJAAN YANG BELUM DI
NO. URAIAN PEKERJAAN VOL. SAT. KERJAKAN KERJAKAN KETERANGAN
VOL. SAT. VOL. SAT.
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 446.21 kg
Bekisting Tangga 18.08 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 1.87 m3
Baja Tulangan Polos, BJTP, fy 240 MPa 130.00 kg
Bekisting Tangga 9.16 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 0.99 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 462.15 kg
Bekisting Tangga 18.95 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 2.10 m3
Baja Tulangan Polos, BJTP, fy 240 MPa 130.00 kg
Bekisting Tangga 9.29 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 0.99 m3

III PEKERJAAN ARSITEKTUR


A PEKERJAAN DINDING DAN PLESTERAN
LANTAI - 1
1 Pek. Pasangan Bata Ringan 600x200x100 1,507.24 M2
2 Pek. Plesteran Mortar 3,014.47 M2
3 Pek. Acian Mortar 3,014.47 M2
4 Pek. Kolom Prakits 15/15 1,007.40 M1
5 Pek. Balok Lintel 10/15 540.13 M1
6 Pek. Acian Aferking Beton (Finishing) 270.74 M2
Pek. Plesteran Profil Jendela (Lebar = 30 cm)
Pek. Acian Profil jendela

LANTAI - 2
1 Pek. Pasangan Bata Ringan 600x200x100 2,052.64 M2
2 Pek. Plesteran Mortar 4,105.28 M2
3 Pek. Acian Mortar 4,105.28 M2
4 Pek. Kolom Prakits 15/15 1,205.00 M1
5 Pek. Balok Lintel 10/15 540.13 M1
6 Pek. Acian Aferking Beton (Finishing) 278.35 M2
Pek. Plesteran Profil Jendela (Lebar = 30 cm)
Pek. Acian Profil jendela

LANTAI - DAK

Page 6
PEKERJAAN YANG SUDAH DI PEKERJAAN YANG BELUM DI
NO. URAIAN PEKERJAAN VOL. SAT. KERJAKAN KERJAKAN KETERANGAN
VOL. SAT. VOL. SAT.
1 Pek. Pasangan Bata Ringan 600x200x100 210.88 M2
2 Pek. Plesteran Mortar 421.76 M2
3 Pek. Acian Mortar 421.76 M2
4 Pek. Kolom Prakits 11/11 31.20 M1
5 Pek. Balok Lintel 10/15 87.05 M1

B PEKERJAAN KUSEN UPVC DAN RAILLING


LANTAI - 1
1 Pek. Pintu Besi + Pintu P1 39.00 Unit
2 Pek. Pasang Kusen UPVC + Pintu P2 9.00 Unit
3 Pek. Pasang Kusen UPVC + Pintu P3 7.00 Unit
4 Pek.. Pintu Allumunium Type P4 5.00 Unit
5 Pek.. Pintu Allumunium Type P4' 2.00 Unit
6 Pek.. Pintu Allumunium Type P5 13.00 Unit
7 Pek. Pasang Kusen UPVC + Pintu P6 1.00 Unit
8 Pek.. Pasang Kusen UPVC + Pintu PD1 1.00 Unit
9 Pek. Pasang Kusen UPVC + Pintu PD2 2.00 Unit
10 Pek. Pasang Kusen UPVC + Pintu PD3 1.00 Unit
11 Pek. Pasang Kusen UPVC + Pintu PD4 2.00 Unit
12 Pek. Pasang Kusen UPVC + Pintu PS1 3.00 Unit
13 Pek. Pasang Kusen UPVC + Pintu PS2 2.00 Unit
14 Pek.. Pasang Kusen UPVC + Pintu PJ1 2.00 Unit
15 Pek. Pasang Kusen UPVC + Pintu PJ2 2.00 Unit
16 Pek. Pasang Pintu Kaca Tempered t=12 mm Type PU 1.00 Unit
17 Pek. Pasang Kusen UPVC + Jendela J1 34.00 Unit
18 Pek. Pasang Kusen UPVC + Jendela J2 35.00 Unit
19 Pek. Pasang Kusen UPVC + Jendela J3 4.00 Unit
20 Pek. Pasang Kusen UPVC + DK1 2.00 Unit
21 Pek. Pasang Kusen UPVC + Bouvenlight BV1 3.00 Unit
22 Pek. Pasang Kusen UPVC + Bouvenlight BV2 39.00 Unit
23 Pek. Pasang Kusen UPVC + Bouvenlight BV4 3.00 Unit
24 Pek. Pemasangan Wall Guard 91.20 m1
25 Pek. Pemasangan Railling Tangga 13.10 m1

LANTAI - 2
1 Pek. Pintu Besi + Pintu P1 47.00 Unit

Page 7
PEKERJAAN YANG SUDAH DI PEKERJAAN YANG BELUM DI
NO. URAIAN PEKERJAAN VOL. SAT. KERJAKAN KERJAKAN KETERANGAN
VOL. SAT. VOL. SAT.
2 Pek. Pasang Kusen UPVC + Pintu P2 9.00 Unit
3 Pek. Pasang Kusen UPVC + Pintu P3 7.00 Unit
4 Pek. Pasang Kusen UPVC + Pintu P3' 4.00 Unit
5 Pek.. Pintu Allumunium Type P4 7.00 Unit
6 Pek.. Pintu Allumunium Type P5 13.00 Unit
7 Pek. Pasang Kusen UPVC + Pintu P6 1.00 Unit
8 Pek.. Pasang Kusen UPVC + Pintu PD1 1.00 Unit
9 Pek.. Pasang Kusen UPVC + Pintu PD2 2.00 Unit
10 Pek. Pasang Kusen UPVC + Pintu PS1 3.00 Unit
11 Pek. Pasang Kusen UPVC + Pintu PS2 2.00 Unit
12 Pek.. Pasang Kusen UPVC + Pintu PJ3 3.00 Unit
13 Pek. Pasang Kusen UPVC + Jendela J3 2.00 Unit
14 Pek. Pasang Kusen UPVC + Jendela J4 4.00 Unit
15 Pek. Pasang Kusen UPVC + Jendela J5 43.00 Unit
16 Pek. Pasang Kusen UPVC + Jendela J6 38.00 Unit
17 Pek. Pasang Kusen UPVC + Jendela J6' 4.00 Unit
18 Pek. Pasang Kusen UPVC + Jendela J7 4.00 Unit
19 Pek. Pasang Kusen UPVC + Jendela J8 4.00 Unit
20 Pek. Pasang Kusen UPVC + Bouvenlight BV1 4.00 Unit
21 Pek. Pasang Kusen UPVC + Bouvenlight BV2 42.00 Unit
22 Pek. Pasang Kusen UPVC + Bouvenlight BV6 4.00 Unit
23 Pek. Pemasangan Wall Guard 139.32 m1
24 Pek. Pemasangan Railling Tangga 13.10 m1
25 Pek.. Pasang Kusen UPVC + Pintu PJ4 2.00 unit

LANTAI - DAK
1 Pek. Pintu Besi UPVC + Pintu P1 1.00 Unit
2 Pek.. Pasang Kusen UPVC + Pintu PD2 2.00 Unit
3 Pek. Pasang Kusen UPVC + Bouvenlight BV3 4.00 Unit
4 Pek. Pemasangan Railling Tangga 4.50 m1

C PEKERJAAN TANAH, PELAPIS LANTAI & PELAPIS DINDING


LANTAI - 1
1 Pek. Plesteran Area Yang Akan Di Vinyl t. 1.5 mm , 1,060.35 M2
2 Pek. Acian Area Yang Akan Di Vinyl 1,060.35 M2
3 Pek. Urugan Pasir Bawah Lantai t = 5 cm 7.34 M3

Page 8
PEKERJAAN YANG SUDAH DI PEKERJAAN YANG BELUM DI
NO. URAIAN PEKERJAAN VOL. SAT. KERJAKAN KERJAKAN KETERANGAN
VOL. SAT. VOL. SAT.
4 Pek. Lantai Vinyl Anti Bakteri - JT Vinyl t= 2 mm 1,060.35 M2
5 Pek. Lantai Homogenius Tile polish 60 x 60 (L2) 71.79 M2
6 Pek. Lantai Homogenius Tile Unpolish 60 x 60 (L3) 75.11 M2
7 Pek. Dinding Homogenius Tile 30x60 Cutting Size (Toilet) (l4) 196.92 M2
8 Pek. Dinding Homogenius Tile 60x60 depan Lift 16.80 M2
9 Pek. Lantai Keramik 30 x 30 (L5) 7.62 M2
10 Pek. Dinding Keramik 30 x 30 (L6) 23.55 M2
11 Pek. Lantai Homogenius Tile Tangga 30 x 60 Fin. Gutter 3 Strip (L7) 21.26 M2

LANTAI - 2
1 Pek. Urugan Pasir Bawah Lantai t = 5 cm 4.94 M3
2 Pek. Plesteran Area Yang Akan Di Vinyl t. 1.5 mm 1,225.81 M2
3 Pek. Acian Area Yang Akan Di Vinyl 1,225.81 M2
4 Pek. Lantai vinyl Sheet + naik ke dinding 10 cm (L1) 1,225.81 M2
5 Pek. Lantai Homogenius Tile polish 60 x 60 (L2) 20.95 M2
6 Pek. Lantai Homogenius Tile Unpolish 60 x 60 (L3) 91.15 M2
7 Pek. Dinding Homogenius Tile 30x60 Cutting Size (Toilet) (l4) 265.32 M2
8 Pek. Dinding Homogenius Tile 60x60 depan Lift 16.80 M2
9 Pek. Lantai Keramik 30 x 30 (L5) 6.60 M2
10 Pek. Dinding Keramik 30 x 30 (L6) 23.55 M2
11 Pek. Lantai Homogenius Tile Tangga 30 x 60 Fin. Gutter 3 Strip (L7) 21.26 M2
12 Pek. Waterproofing Toilet P3 ( Soprasun , Atap Teduh Lestari ) 136.35 M2

LANTAI - 3
1 Pek. Urugan Pasir Bawah Lantai t = 5 cm 7.13 M3
2 Pek. Lantai Homogenius Tile Unpolish 60 x 60 (L3) 142.63 M2
3 Pek. Waterproofing Plat Dak Beton, Duo Composite Membrance ( Atap Teduh Lestari ) 299.92 M2
4 Pek. screed lantai 5 cm 299.92 M2

D PEKERJAAN PLAFOND
LANTAI - 1 ELEVASI +3.20
1 Pek. Rangka Plafond Hollow 40x40 1,171.49 M2
2 Pek. Plafond Gypsum Water Resistant 9mm 126.22 M2
3 Pek. Plafond PVC ( Shunda Plafond ) 959.60 M2
4 Pek. Plafond Spandrel Jarak 10 Cm 85.68 M2
5 Pek. Shadowline Ujung Plafond 586.45 M1

Page 9
PEKERJAAN YANG SUDAH DI PEKERJAAN YANG BELUM DI
NO. URAIAN PEKERJAAN VOL. SAT. KERJAKAN KERJAKAN KETERANGAN
VOL. SAT. VOL. SAT.

LANTAI - 2 ELEVASI +7.20 & ATAP


1 Pek. Rangka Plafond Hollow 40x40 1,536.53 M2
2 Pek. Plafond Gypsum Water Resistant 9mm 145.87 M2
3 Pek. Plafond PVC ( Shunda Plafond ) 1,390.66 M2
4 Pek. Shadowline Ujung Plafond 1,212.67 M1
5 Pek. Wiremesh M.8 ( Diatas Plafound Plafond ) 625.73 m2

E PEKERJAAN PENGECATAN DAN LABURAN


LANTAI - 1
1 Pek. Pengecatan Dinding Exterior 209.05 M2
2 Pek. Pengecatan Dinding Interior 1,260.40 M2
3 Pek. Pengecatan Plafond 126.22 M2

LANTAI - 2
1 Pek. Pengecatan Dinding Exterior 143.98 M2
2 Pek. Pengecatan Dinding Interior 1,498.78 M2
3 Pek. Pengecatan Plafond 145.87 M2

LANTAI - 3
1 Pek. Pengecatan Dinding Exterior 211.76 M2
2 Pek. Pengecatan Dinding Interior 140.84 M2
3 Pek. Pengecatan Plafond 195.81 M2

F PEKERJAAN SANITARY UNIT


LANTAI - 1
1 Pas. Kloset Duduk Type CW 421 J/ SW 420 JP, with TCW07S 5.00 Unit
2 Pas. Kloset Jongkok Type CE 7 10.00 Unit
3 Pas. Jet Washer Type THX 20 NBW (White) 5.00 Unit
4 Pas. Wastafel Kotak Type LW 647 CJT1 13.00 Unit
5 Pas. Floor Drain Type TX 1 EB 20.00 Unit
6 Pas. Shower Full Set (3 Way Column Set) Panas Dingin Type TX493SRS / Germany Brilliant 2.00 Unit
7 Pas. Head Shower 11.00 Unit
8 Pas. Kitchen Sink 1.00 Unit

Page 10
PEKERJAAN YANG SUDAH DI PEKERJAAN YANG BELUM DI
NO. URAIAN PEKERJAAN VOL. SAT. KERJAKAN KERJAKAN KETERANGAN
VOL. SAT. VOL. SAT.
9 Pas. Dinding Kaca Acrylic 13.92 m2
10 Pas. Kran Dinding F 800 Y - Onda 15.00 Unit
11 Pas. Bak Spoelhoek Ex. Nayati 2.00 Unit

LANTAI - 2
1 Pas. Kloset Duduk Type CW 421 J/ SW 420 JP, with TCW07S 7.00 Unit
2 Pas. Kloset Jongkok Type CE 7 13.00 Unit
3 Pas. Jet Washer Type THX 20 NBW (White) 7.00 Unit
4 Pas. Wastafel Kotak Type LW 647 CJT1 12.00 Unit
5 Pas. Floor Drain Type TX 1 EB 24.00 Unit
6 Pas. Shower Full Set (3 Way Column Set) Panas Dingin Type TX493SRS / Germany Brilliant 2.00 Unit
7 Pas. Head Shower 11.00 Unit
8 Pas. Kitchen Sink 1.00 Unit
9 Pas. Dinding Kaca Acrylic 13.92 m2
10 Pas. Kran Dinding F 800 Y - Onda 19.00 Unit
11 Pas. Bak Spoelhoek Ex. Nayati 1.00 Unit

G PEKERJAAN FASADE
1 Pek. Allumunium Composite Panel PVDF 5005 t= 0.5 mm 317.54 m2
2 Pek. Pasangan Keramik Dinding Interlok 30x60, dCastillo Crema - GL638022 1,102.10 m2
3 Pek. Pasangan Batu Alam / Andesit Keliling Gedung + Coating Cat Pernis 180.68 m2
4 Pek. Canopy Kaca Tempered 12mm Double CNP, Hollow Galvanish + Acesoris Fin Cat 93.28 m2
5 Pek. Pasang Huruf Stainless Steell "RAWAT JIWA INTENSIF" t. 40 cm 1.00 Unit

H PEKERJAAN ATAP
1 Pek. Rangka Atap Baja Ringan Profil Z.220 GIGA STEEL 1,478.41 m2
2 Pek. Alumunium Foil + lapisan peredam ex. Teknobuild ( superbtex QRM06 ) 1,478.41 m2
3 Pek. Penutup Atap Single Bitumen 1,478.41 m2
4 Pek. Pasang Roofmesh 75x75 t=1.2 mm Galvanis 1,478.41 m2
5 Woodplank GRC tebal 8cm Lebar 30cm 263.00 m1
6 Pek. Pasang Talang Air Hujan Zincalum 202.20 m1

I PEKERJAAN INTERIOR MELEKAT


RUANG SEKLUSI

Page 11
PEKERJAAN YANG SUDAH DI PEKERJAAN YANG BELUM DI
NO. URAIAN PEKERJAAN VOL. SAT. KERJAKAN KERJAKAN KETERANGAN
VOL. SAT. VOL. SAT.
1 Pek. Dinding + Rangka Hollow 4x4 cm + Multiplek + Kulit Peded 309.23 m2
2 Pek. Floor Foam 5 cm Fin Leather 90.40 m2

RUANG KEPALA & RUANG STAFF


1 Pek. Dinding Fin. Wallpaper 70.55 m2

RUANG RAPAT
1 Pek. Treatment Dinding multi 9 mm lap HPL Warna Terang + Rangka Hollow 4x4 cm 10.53 m2
2 Pek. Treatment Dinding multi 9 mm lap HPL Warna Gelap + Rangka Hollow 4x4 cm 7.65 m2
3 Pek. Dinding Fin. Wallpaper 18.20 m2

RUANG LOBBY
1 Meja Resepsionis Fin. HPL 3.22 m2
2 Pek. Treatment Dinding multi 9 mm lap HPL Warna Terang + Rangka Hollow 4x4 cm 8.64 m2
3 Pek. Pemasangan Kaca polos 8mm + stiker 3.24 m2
4 Pek. Pemasangan Tulisan stainless steel "RAWAT JIWA INTENSIF" t. 20 1.00 Unit
5 Pek. Dinding Fin. Wallpaper 38.55 m2

RUANG RAWAT
1 Meja Nurse Station Fin. HPL 26.64 m2

RUANG PASIEN
1 Pek. Dinding Fin. Wallpaper Vinyl Anti Bakteri - JT Vinyl t= 2 mm Lantai 1 670.76 m2
2 Pek. Dinding Fin. Wallpaper Vinyl Anti Bakteri - JT Vinyl t= 2 mm Lantai 2 1,885.14 m2

A PEKERJAAN ELEKTRIKAL
PEKERJAAN PANEL
1 Sambungan Baru Tegangan Rendah 105,000.00 VA
Kapasitas 105000 VA
Termasuk Kabel, Sistem Proteksi, Galian, dan Perapihan Kembali

All Panel Inculding Volt, Amp, Frec Metering, And Indicator Lamp

LV - MDP RSJ Cisarua 1.00 set

Page 12
PEKERJAAN YANG SUDAH DI PEKERJAAN YANG BELUM DI
NO. URAIAN PEKERJAAN VOL. SAT. KERJAKAN KERJAKAN KETERANGAN
VOL. SAT. VOL. SAT.
SDP LP/PP Lantai 1 1.00 set
SDP LP/PP Lantai 2 1.00 set
SDP UTILITAS GROUND OUTDOOR IP 65 1.00 set
SDP UTILITAS ROOF TOP OUTDOOR IP 65 1.00 set
NYFGBY 4 x 16 MM2 53.00 m
NYA 1 x 10 MM2 53.00 m
NYFGBY 4 x 16 MM2 59.00 m
NYA 1 x 10 M2 59.00 m
NYFGBY 4 x 25 MM2 36.00 m
NYA 1 x 16 M2 36.00 m
NYFGBY 4 x 10 MM2 67.00 m
NYA 1 x 6 MM2 67.00 m

B PEKERJAAN INSTALASI KEBEL FEEDER

C PEKERJAAN KABEL TRAY HOT DEEP GALVANIS


1 Kabel Tray 300/ 50 mm + Aksesoris Elektrikal Elektronik 266.18 m
2 Kabel Tray 300/ 50 mm + Aksesoris Air Bersih 195.06 m
3 Kabel Ladder 400/100 mm Horizontal Dalam Shaft 17.42 m

D PEKERJAAN PENERANGAN
LANTAI - 1
a Lampu LED Panel 32 Watt 4 x 1 Ft 33.00 unit
b Lampu Down Light LED Slim 14 Watt 6" 63.00 unit
c Lampu Down Light LED Slim 8 Watt 4" 24.00 unit
d Lampu Emergency TL LED 1 x 14 Watt Waterpoof 12.00 unit
e Lampu Exit 8 W ACR (Dua muka) c/w Power Pack 2.00 unit
f Saklar Tunggal Cover Metalik with LED 61.00 unit
g Saklar Ganda Cover Metalik with LED 21.00 unit
h Stop kontak 16 Amp 21.00 unit
i Stop kontak Putar 16 Amp with Cover 14.00 unit
j Stop kontak 16 Amp With Cover 19.00 unit
Stop kontak HDMI dan Proyektor 1.00 unit
k Instalasi Penerangan 134.00 ttk
l Instalasi Stop kontak 53.00 ttk
m Exhaust Fan 10 ",150 CFM,Toilet, Ducting dan Instalasi 53.00 Unit

Page 13
PEKERJAAN YANG SUDAH DI PEKERJAAN YANG BELUM DI
NO. URAIAN PEKERJAAN VOL. SAT. KERJAKAN KERJAKAN KETERANGAN
VOL. SAT. VOL. SAT.
n AIR Conditioner 1.5 PK Dual Cool 3.00 Unit
o Pipa Refrigrant 29.00 m1

LANTAI - 2
KAMAR DAN OFFICE
Garansi Lampu LED SLIM + ARMATUR Minimal 4 Thaun
a Lampu LED Panel 32 Watt 4 x 1 Ft 31.00 unit
b Lampu Down Light LED Slim 14 Watt 6" 70.00 unit
c Lampu Down Light LED Slim 8 Watt 4" 27.00 unit
d Lampu Emergency TL LED 1 x 14 Watt Waterpoof 12.00 unit
e Lampu Exit 8 W ACR (Dua muka) c/w Power Pack 3.00 unit
f Saklar Tunggal Cover Metalik with LED 68.00 unit
g Saklar Ganda Cover Metalik with LED 20.00 unit
h Stop kontak 16 Amp 23.00 unit
i Stop kontak Putar 16 Amp with Cover 13.00 unit
j Stop kontak 16 Amp With Cover 21.00 unit
Stop kontak HDMI dan Proyektor 1.00 unit
k Instalasi Penerangan 143.00 ttk
l Instalasi Stop kontak 58.00 ttk
m Exhaust Fan 10 ",150 CFM,Toilet, Ducting dan Instalasi 15.00 Unit
n AIR Conditioner 1.5 PK Dual Cool 3.00 Unit
o Pipa Refrigrant 29.00 m1

LANTAI - ROOFTOP
- Lampu Spot Light LED 30 Watt IP 66 4.00 unit
- Lampu V-Shape LED 2x16 Watt 8.00 unit
- Saklar Tunggal Cover Metalik with LED 1.00 unit
- Saklar Ganda Cover Metalik with LED 2.00 unit
- Stop kontak 16 A 3.00 unit
- Instalansi Penerangan 12.00 ttk
- Instalansi Stop kontak 3.00 ttk

E PEKERJAAN PENANGKAL PETIR DAN GROUNDING


1 Penangkal petir jenis Elekro statis CAT 2 (Radius protection 150 m) Include Tower 5 Meter 1.00 Set

Page 14
PEKERJAAN YANG SUDAH DI PEKERJAAN YANG BELUM DI
NO. URAIAN PEKERJAAN VOL. SAT. KERJAKAN KERJAKAN KETERANGAN
VOL. SAT. VOL. SAT.
Dipasang di Rooftop inci, cable BC, Support & Accessories
Perijinan
2 Grounding penangkal petir incl. cable, Aksesoris & civil works 1.00 ttk
3 Grounding panel incl. cable , Aksesoris & civil works 4.00 ttk

B PEKERJAAN ELEKTRONIKAL
A PEKERJAAN CCTV DAN PROYEKTOR
1 NVR 32 Chanel c/w IP Smart Phone Acces ,Kapasitas 2 Terra sek. Samsung, Sony, Panasonic 4.00 set
TV LED MONITOR 43" 4.00 Unit
Switch hub 16 port 3 com/linksys 8.00 unit
UPS 1 kVA 4.00 unit

2 LANTAI - 1 (IP CAMERA WISENET)


- IP Camera Bullet 2 MP Outdoor True Day/Night Vision Motion Detector 53.00 unit
- Instalasi CCTV 53.00 ttk

3 LANTAI - 2 (IP CAMERA WISENET)


- IP Camera Bullet 2 MP Outdoor True Day/Night Vision Motion Detector 61.00 unit
- Instalasi CCTV 61.00 ttk

LANTAI - DAK (IP CAMERA WISENET)


- IP Camera Bullet 2 MP Outdoor True Day/Night Vision Motion Detector 1.00 unit
- Instalasi CCTV 1.00 ttk

4 Testing Commisioning 1.00 lot

B PEKERJAAN SISTEM DATA DAN TELEPON


1 LANTAI - 1 & LANTAI - 2
Wifi High Power Reuter 300-600 mbps
Instalasi
2 Server CPU DDR3, Intel Xeon E3 3,3 GHz, Memory 8 GB,DVD RW, I Terra HDD 1.00 Unit
cw Monitor 21 inch SEK. Asus, HP, LENOVO
Wifi High Power Acces Point 600 mbps 2.00 unit
Closed Rack 19 " 30 U 1.00 Unit
Switch Hub 24 port 1.00 unit
UPS 2 KVA 1.00 unit
Instalasi WIFI 2.00 ttk

Page 15
PEKERJAAN YANG SUDAH DI PEKERJAAN YANG BELUM DI
NO. URAIAN PEKERJAAN VOL. SAT. KERJAKAN KERJAKAN KETERANGAN
VOL. SAT. VOL. SAT.

3 IP PABX 6 Line - 16 Extention KX TES824 1.00 Unit


Pesawat Master Telephone Rekomendasi KX T7730 1.00 Unit
Pesawat Single Telephone Rekomendasi KX T505 10.00 Unit

LANTAI - 1
4 Switch JUNIPER Network EX2300-24T 1.00 pcs
5 Access Point (Wifi) Access Point Ruijie RG-AP710 3.00 pcs
6 Rak Wallmount Wallmount Rack 6U Single Door 1.00 pcs
7 UPS APC 1200VA 1.00 pcs
8 Kabel Fiber Optik 12 Core Server Center to Server Ged Samsung Sony Panasonic 100.00 meter
9 Socket Lan Schneider, Panasonic 14.00 pcs

LANTAI - 2
10 Switch JUNIPER Network EX2300-24T 1.00 pcs
11 Access Point (Wifi) Access Point Ruijie RG-AP710 3.00 pcs
12 Rak Wallmount Wallmount Rack 6U Single Door 1.00 pcs
13 UPS APC 1200VA 1.00 pcs
14 Socket Lan Schneider, Panasonic 15.00 pcs

C PEKERJAAN SOUND SYSTEM


1 Sound System Sentral
AM/ FM Tunner 1.00 set

2 LANTAI - 1
Ceiling Speaker (6 W) 8" 50.00 unit
Outdoor Speaker 20 Watt 2.00 unit
TBSS 1 1.00 unit
Volume Control 48.00 unit
Instalasi Speaker(NYMHY 2X1.5 dalam pipa conduit 20mm) 50.00 ttk
3 LANTAI - 2
Ceiling Speaker (6 W) 8" 57.00 unit
Outdoor Speaker 20 Watt 2.00 unit
TBSS 1 1.00 unit
Volume Control 57.00 unit
Instalasi Speaker(NYMHY 2X1.5 dalam pipa conduit 20mm) 57.00 ttk

Page 16
PEKERJAAN YANG SUDAH DI PEKERJAAN YANG BELUM DI
NO. URAIAN PEKERJAAN VOL. SAT. KERJAKAN KERJAKAN KETERANGAN
VOL. SAT. VOL. SAT.
III PEKERJAAN MEKANIKAL
A PEKERJAAN PLUMBING
I SITE PLAN
1 Pompa Transfer Bak Utama (Rumah Pompa) RSJ ke Groundtank Gedung
Sentrifugal Pump include Panel dan WLC 2.00 Set
Pipa Transfer Air Bersih dari Kolam Sumber RS (include Accessories, galian dan penimbunan)
2
ke Groundtank
HDPE 2 inc 110.00 m
Gate valve 2 inc (incl.Box Valve) 2.00 unit
Bak Kontrol (Concrete dengan Penutup) 3.00 Lot
3 Kran Taman
HDPE 1 inc 60.00 m
HDPE 3/4 inc 21.00 m
Stop Kran 3/4 inc 2.00 unit

4 Septic Tank Biofil 8 M3 , Blower (Galian incl. pondasi concrete) 1.00 unit

Resapan Buis Beton 1.5 x 3 Meter 1.00 unit


PVC AW 4 inc 15.00 m
PVC AW 6 inc 10.00 m

a Pek. Galian Tanah 12.67 m2


Baja Tulangan Weirmesh M10 562.34 kg
Bekisting, Pas. Bata Merah, t. 1/2 Bata, 1 PC : 5 PP 41.60 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 7.23 m3
c Penutup Manhole Chequered Plate Uk. 100x100 cm t=2,3mm 0.69 kg
d Pek. Waterproofing Plat Dak Beton, Duo Composite Membrance ( Atap Teduh Lestari ) 16.52 m2
5 Tangki Ground Air Bersih FRP 8 M3 (2200x2300x1600 mm) 1.00 unit
HDPE 2 inc 25.00 m
HDPE 1 1/2" inc 49.00 m
Gate Valve 2 inc 2.00 unit
Gate Valve 1 inc (Drain) 1.00 unit
Sentrifugal Multi Stage Pump include Panel dan WLC 2.00 Set
Rumah Pompa (Sangkar Besi Atap) 2 x 2 Meter Galvanis 1.00 Lot
Tipe Sentrifugal 2.00 unit
8 Torn FRP Rooftop Silinder 4 M3 2.00 Unit
Pompa Celup 3 Phase Pump include Panel dan WLC 2.00 Unit

Page 17
PEKERJAAN YANG SUDAH DI PEKERJAAN YANG BELUM DI
NO. URAIAN PEKERJAAN VOL. SAT. KERJAKAN KERJAKAN KETERANGAN
VOL. SAT. VOL. SAT.
PVC AW 2 " (2 Tarikan) 120.00 Meter
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 984.72 kg
Bekisting, Pas. Bata Merah, t. 1/2 Bata, 1 PC : 5 PP 5.80 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 6.00 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 3,095.89 kg
Bekisting Plat Dinding 204.88 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 17.40 m3
Pek. Water Stop PVC Lebar 230mm-320mm 17.20 m1
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 647.84 kg
Bekisting dengan Papan 3x20 35.80 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 6.00 m3
d Tangga Stainless Steel 1.00 unit
e Penutup Manhole Chequered Plate Uk. 100x100 cm t=2,3mm 1.22 kg
f Pek. Waterproofing Membran Soprasun P3 95.60 m2
PPR PN 10, 1/2 inc 2.48 m
PPR PN 10, 3/4 inc 79.20 m
PPR PN 10, 1 inc 113.07 m
#REF! Valve (Class 125 psi) & Accessories 3.00 unit
PVC AW 1 1/2 inc 44.00 m
PVC AW 2 inc 75.00 m
PVC AW 3 inc 310.64 m
PVC AW 4 inc ( Air kotor ) 38.88 m
PVC AW 4 inc ( Riser ke Resapan & Pembuangan) 21.04 m
PVC AW 6 inc ( Riser Pipa Air Kotor dan Ke Biotek) 48.00 m
Floor Drain 50 mm 48.00 bh
Clean Out 80 mm 35.00 bh
PVC AW 1 1/2 inc 7.00 m
PVC AW 2 inc (riser ) 7.00 m
PVC AW 4 inc 260.00 m
Roof Drain Grill 34.00 Unit
PPR PN 10, 1/2 inc 2.85 m
PPR PN 10, 3/4 inc 91.20 m
PPR PN 10, 1 inc 116.21 m
Gate Valve 1 inc 3.00 unit
PVC AW 1 1/2 inc 44.00 m
PVC AW 2 inc 75.00 m
PVC AW 3 inc 426.95 m

Page 18
PEKERJAAN YANG SUDAH DI PEKERJAAN YANG BELUM DI
NO. URAIAN PEKERJAAN VOL. SAT. KERJAKAN KERJAKAN KETERANGAN
VOL. SAT. VOL. SAT.
PVC AW 4 inc ( Air kotor ) 96.43 m
Floor Drain 50 mm 58.00 bh
Clean Out 80 mm 43.00 bh
- PPR PN 10, 1 inc 81.36 m
- PPR PN 10, 1 1/2 inc 15.77 m
1 Pressure Safety Main Valve, Fitting & Asesories 1.00 Lot
2 Pilar hydrant ( two way ) + termasuk support dan pondasi 2.00 Unit
* dia. 100 mm ( 4" ) 80.00 Meter
* Gate valve dia. 50 mm ( 2") 2.00 Buah
* Pressure gauge 2.00 Buah
3 Hydrant Outdoor 2.00 Buah
4 Hydrant box ( type Indoor ) lengkap 4.00 Unit
* dia. 100 mm ( 4" ) 45.00 Meter
* dia. 50 mm ( 2" ) 97.00 Meter
* dia. 40 mm ( 1,5" ) 38.00 Meter
* Gate valve dia. 50 mm ( 2") 4.00 Buah
* Pressure gauge 4.00 Buah
5 APAR Kapasitas 6 Kg 12.00 Buah
APAR Kapasitas 12 Kg 8.00 Buah
MCFA 10 Zone, Anounciator (c/w battery & rectifier) , SEMI ADDRESABLE 1.00 set
Smoke Detector 63.00 unit
Manual Call Point 1.00 unit
Fire Bell 1.00 unit
Indicator Lamp Outdoor 1.00 unit
Intalasi Smoke ( NYA 2x1.5 mm dalam pipa conduit 20 mm2 ) 63.00 ttk
Intalasi Fire Bell dan indicator lamp ( NYA 2x1.5 mm dalam pipa conduit ) 3.00 ttk
TBFA 1.00 unit
Testing & komisioning 1.00 Lot
Smoke Detector 71.00 unit
Manual Call Point 1.00 unit
Fire Bell 1.00 unit
Indicator Lamp Outdoor 1.00 unit
Intalasi Smoke ( NYA 2x1.5 mm dalam pipa conduit 20 mm2 ) 71.00 ttk
Intalasi Fire Bell dan indicator lamp ( NYA 2x1.5 mm dalam pipa conduit ) 3.00 ttk
TBFA 1.00 unit
Testing & komisioning 1.00 Lot
a Type Bed Lift Elevator SIGMA 1.00 unit

Page 19
PEKERJAAN YANG SUDAH DI PEKERJAAN YANG BELUM DI
NO. URAIAN PEKERJAAN VOL. SAT. KERJAKAN KERJAKAN KETERANGAN
VOL. SAT. VOL. SAT.
1 Pek. Galian Tanah Biasa Kedalaman ± 1,00 m 3.65 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 893.86 Kg
Bekisting Balok Struktur 42.36 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-225 3.18 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 397.56 Kg
Bekisting Balok Struktur 18.24 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-225 1.82 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 597.51 Kg
Bekisting Balok Struktur 39.52 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-225 1.98 m3
Pek. Urugan Kembali Bekas Galian Pondasi 1.37 m3
Pek. Base Plat t = 12 mm 614.76 Kg
Pek. Angkur baud + mur ø 16 mm p = 40 cm 44.00 bh
Pek. Pasang Baud + Mur Rangka Kuda Kuda ø 2 inch 55.00 bh
Pek. Pasang Baud + Mur Perkuatan Tiang Selasar 44.00 bh
Pek. Urugan Pasir Bawah Lantai t = 5 cm 14.03 m3
Pek. Lantai Homogenius Tile Rustic 60 x 60 280.61 m2
Pek. Rangka Plafond Hollow 40x40 410.40 m2
Pek. Plafond Gypsum Water Resistant 9mm 410.40 m2
Pek. Kolom Kayu Borneo super 6x12 Double 0.74 m3
Pek. Rangka Atap Kayu 410.40 m2
Pek. Rangka Kuda Kuda Kayu 2.88 m3
Pek. Penutup Atap Genteng morando glazur 410.40 m2
Pek. Penutup Nok Genteng bubung morando glazur 76.00 m1
Pek. Listplang Kayu 3x30 cm 152.00 m1
Instalasi Penerangan 52.00 titik
Saklar Ganda Cover Metalik with LED 26.00 bh
Lampu Downlight Outdoor LED 18 watt + Box white 52.00 bh
1 Pek. Galian Tanah Biasa Kedalaman ± 1,00 m 0.48 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 222.23 Kg
Bekisting Balok Struktur 10.48 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-225 0.79 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 52.31 Kg
Bekisting Balok Struktur 2.40 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-225 0.24 m3
Baja Tulangan Deform/Ulir, BJTD, fy 400 MPa 238.49 Kg

Page 20
PEKERJAAN YANG SUDAH DI PEKERJAAN YANG BELUM DI
NO. URAIAN PEKERJAAN VOL. SAT. KERJAKAN KERJAKAN KETERANGAN
VOL. SAT. VOL. SAT.
Bekisting Balok Struktur 22.80 m2
Cor Beton Ready Mix, f'c = 26,4 MPa, K-225 1.14 m3
Pek. Urugan Kembali Bekas Galian Pondasi 0.18 m3
Pek. Base Plat t = 12 mm 38.89 Kg
Pek. Cover Base Plate Stainless Steel 10.00 bh
Pek. Angkur baud + mur ø 16 mm p = 40 cm 20.00 bh
Pek. Urugan Pasir Bawah Lantai t = 5 cm 1.20 m3
Pek. Lantai Homogenius Tile Rustic 60 x 60 23.60 m2
Pek. Pengecatan Kolom Beton 22.80 m2
Pek. Struktur Atap Stainless Steel Hollow 10x5 cm 24.00 m2
Pek. Penutup Atap Kaca Tempered t=12mm + Fin. Sandblasted Sticker 39.00 m2
Instalasi Penerangan 8.00 titik
Saklar Ganda Cover Metalik with LED 4.00 bh
Lampu Downlight Outdoor LED 18 watt + Box white 8.00 bh
1 Pek. Urugan Tanah 30cm 121.98 m3
2 Pek. Urugan Tanah Subur 10cm 22.76 m3
3 Pek. Rabat Beton + ramp Selasar t = 15 cm 8.04 m3
4 Pek. Rumput Gajah Mini 333.07 m2
5 Pek. Saluran Keliling Gedung U-ditch 30x30x120 333.79 m1
6 Pek. Pemasangan Plastik Cor Rabat Beton 26.80 m2
7 Pek. Lantai Kerja t = 5 cm 1.34 m3
● Pek. Urugan Sirtu 5 cm 7.98 m3
● Baja Tulangan Wiremesh M8 1 Layer 869.26 kg
● Bekisting Papan Jalan Beton 16.56 m2
● Cor Beton Jalan Ready Mix, f'c = 26,4 MPa, K-300, t=20 cm 31.91 m3
● Pek. Pemasangan Plastik Cor Jalan 159.53 m2
● Baja Tulangan Polos, BJTP, fy 240 MPa 41.08 kg
● Bekisting Tangga 2.67 m2
● Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 0.58 m3
1 Pek. Galian Tanah Sedalam 1 m 2.42 m3
● Baja Tulangan Polos, BJTP, fy 240 MPa 102.75 kg
● Bekisting 2.00 m2
● Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 1.12 m3
3 Pek. Urugan Tanah Kembali 0.88 m3
4 Pek. Kolom Baja WF 350 X 175 X 7 X 11 1,918.53 kg
5 Pek. Pasangan Kanopi Kaca Tempered 12 mm, Lap. Sunblas, Rangka Hollow 50x100 41.10 m2

Page 21
PEKERJAAN YANG SUDAH DI PEKERJAAN YANG BELUM DI
NO. URAIAN PEKERJAAN VOL. SAT. KERJAKAN KERJAKAN KETERANGAN
VOL. SAT. VOL. SAT.
6 Pek. Allumunium Composite Panel (ACP) PVDF Alloy 5005 30.29 m2
1 Pek. Galian Tanah Sedalam 1 m 8.45 m3
● Baja Tulangan Polos, BJTP, fy 240 MPa 1,003.20 kg
● Bekisting 21.12 m2
● Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 5.81 m3
● Baja Tulangan Polos, BJTP, fy 240 MPa 966.24 kg
● Bekisting 28.16 m2
● Cor Beton Ready Mix, f'c = 26,4 MPa, K-300 1.41 m3
4 Pek. Urugan Tanah Kembali 7.44 m3
5 Pek. Kolom Baja H Beam 300.300.10.15 5,940.80 kg
6 Pek. Balok Baja WF 250.125.6.9 1,098.75 kg
7 Pek. Balok Baja WF 150.175.5.7 315.00 kg
8 Pek. Plat Bordes t = 10 mm 40.40 m2
9 Pek. Angkur baud + mur ø 16 mm p = 40 cm 96.00 bh
10 Pek. Base Plat t = 12 mm 24.89 kg
11 Pek. Voute 88.80 kg
12 Pek. Mur Baut M24 84.00 bh
13 Pek. Rangka Pembagi Hollow 50x50 , Modul 50x50 7.04 m2
14 Pek. Hollow Rangka Tangga 8.64 m2
15 Pek . Kisi Kisi Hollow 74.67 m2
16 Pek. Pasangan Kanopi Kaca Tempered 12 mm, Lap. Sunblas, Rangka Hollow 50x100 24.93 m2
17 Pek. Pemasangan Railling Tangga 24.00 m1

Page 22
PEKEERJAAN ARSITEKTUR
B PEKERJAAN KUSEN UPVC DAN RIALLING
Lantai -1
Pek. Pintu Besi + Pintu P1
Pek. Pasang Kusen UPVC + Pintu P2
Pek. Pasang Kusen UPVC + Pintu P3
Pek.. Pintu Allumunium Type P4
Pek.. Pintu Allumunium Type P4'
Pek.. Pintu Allumunium Type P5
Pek. Pasang Kusen UPVC + Pintu P6
Pek.. Pasang Kusen UPVC + Pintu PD1
Pek. Pasang Kusen UPVC + Pintu PD2
Pek. Pasang Kusen UPVC + Pintu PD3
Pek. Pasang Kusen UPVC + Pintu PD4
Pek. Pasang Kusen UPVC + Pintu PS1
Pek. Pasang Kusen UPVC + Pintu PS2
Pek.. Pasang Kusen UPVC + Pintu PJ1
Pek. Pasang Kusen UPVC + Pintu PJ2
Pek. Pasang Pintu Kaca Tempered t=12 mm Type PU
Pek. Pasang Kusen UPVC + Jendela J1
Pek. Pasang Kusen UPVC + Jendela J2
Pek. Pasang Kusen UPVC + Jendela J3
Pek. Pasang Kusen UPVC + DK1
Pek. Pasang Kusen UPVC + Bouvenlight BV1
Pek. Pasang Kusen UPVC + Bouvenlight BV2
Pek. Pasang Kusen UPVC + Bouvenlight BV4
Pek. Pemasangan Wall Guard
Pek. Pemasangan Railling Tangga
Lantai -2
Pek. Pintu Besi + Pintu P1
Pek. Pasang Kusen UPVC + Pintu P2
Pek. Pasang Kusen UPVC + Jendela PJ1

Lantai -3
Pek. Pasang Kusen UPVC + Pintu PD2
Pek. Pintu Utama
Pek. Pintu Besi UPVC + Pintu P1
Pek. Pemasangan Kusen UPVC + Pintu PD2
Pek. Pemasangan Kusen UPVC + Bouvenlight BV3
Pek. Pemasangan Railing Tangga

C PEKERJAAN PELAPIS LANTAI & PELAPIS DINDING


Lantai -1
Pek. Lantai Vinyl Natiu Bakteri - JT Vinyl t=2mm
Lantai -2
Pek. Lantai Vinyl Sheet + Naik ke dinding 10 cm (L1)
Pek. Dinding Homogenius Tile 30x60 Cutting Size (toilet) (I4)

E PEKERJAAN PENGECATAN & LABURAN


Lantai -1
Pek. Pengecatan Dinding Exterior
Pek. Pengecatan Dinding Interior
Pek. Pengecatan Railing Tangga
Lantai -2
Pek. Pengecatan Dinding Exterior
Pek. Pengecatan Dinding Interior
Pek. Pengecatan Railing Tangga
Lantai -3
Pek. Pengecatan Dinding Exterior
Pek. Pengecatan Dinding Interior
Pek. Pengecatan Railing Tangga
B PEKERJAAN ELEKTRONIKAL
A PEKERJAAN CCTV DAN PROYEKTOR
Lantai 1 (IP CAMERA WISENET)
IP Camera Bullet 2 MP Out Door True Day/Night Visiion Motion Detector
Instalasi CCTV

Lantai 2 (IP CAMERA WISENET)


IP Camera Bullet 2 MP Out Door True Day/Night Visiion Motion Detector
Instalasi CCTV

Lantai Atap/Dak (IP CAMERA WISENET)


IP Camera Bullet 2 MP Out Door True Day/Night Visiion Motion Detector
Instalasi CCTV

D PEKRERJAAN PENERANGAN
Lantai-Roof Top
Lampu Spot Light :ED 30 Watt IP 66
Lampu V-Shape LED 2x16 Watt
Saklar Tunggal Cover Metalik With LED
Saklar Ganda Cover Metalik With LED
Stop Kontak 16 A
Instalasi Penerangan
Instalasi Stop Kontak
PEKERJAAN PLUMBING
Pipa Pembuangan Wastafel
Wastafel

PEKERJAAN INTERIOR MELEKAT


RUANG SEKLUSI
1 Pek. Dinding + Rangka Hollow 4x4 cm + Multiplek + Kulit Peded
2 Pek. Floor Foam 5 cm Fin Leather
RUANG RAPAT
1 Pek. Treatment Dinding multi 9 mm lap HPL Warna Terang + Rangka Hollow 4x4 cm
2 Pek. Treatment Dinding multi 9 mm lap HPL Warna Gelap + Rangka Hollow 4x4 cm
3 Pek. Dinding Fin. Wallpaper
RUANG LOBBY
1 Meja Resepsionis Fin. HPL
2 Pek. Dinding Fin. Wallpaper

101.25
Kontrak
Sudah Dikerjakan
Belum Dikerjakan
Harga satuan Jumlah Harga
Satuan Volume

Unit 39.00 35.00 4.00 Rp 4,967,300.00 Rp 19,869,200.00


Unit 9.00 0.00 9 Rp 4,224,400.00 Rp 38,019,600.00
Unit 7.00 Rp 4,625,700.00
Unit 5.00 Rp 702,500.00
Unit 2.00 Rp 615,100.00
Unit 13.00 Rp 626,300.00
Unit 1.00 Rp 2,340,000.00
Unit 1.00 Rp 2,154,000.00
Unit 2.00 0.00 2 Rp 8,024,900.00 Rp 16,049,800.00
Unit 1.00 0.00 1 Rp 2,742,800.00 Rp 2,742,800.00
Unit 2.00 Rp 3,120,100.00
Unit 3.00 Rp 963,400.00
Unit 2.00 0.00 2 Rp 902,100.00 Rp 1,804,200.00
Unit 2.00 0.00 2 Rp 4,968,600.00 Rp 9,937,200.00
Unit 2.00 Rp 4,289,000.00
Unit 1.00 Rp 12,298,200.00
Unit 34.00 34.00 Rp 1,196,900.00
Unit 35.00 16.00 19 Rp 1,053,700.00 Rp 20,020,300.00
Unit 4.00 Rp 3,365,700.00
Unit 2.00 Rp 9,958,700.00
Unit 3.00 1.00 2 Rp 1,166,200.00 Rp 2,332,400.00
Unit 39.00 35.00 4 Rp 2,019,900.00 Rp 8,079,600.00
Unit 3.00 Rp 2,081,900.00
m1 91.20 Rp 704,700.00
m1 13.10 Rp 166,200.00

Unit 47.00 37.00 10.00 Rp 4,967,300.00 Rp 49,673,000.00


Unit 9.00 8.00 1.00 Rp 4,224,400.00 Rp 4,224,400.00
Unit 2.00 1.00 1.00

Unit
Unit 1.00 0.00 1.00 Rp -
Unit 2.00 0.00 2.00 Rp -
Unit 4.00 0.00 4.00 Rp -
m1 4.50 0.00 4.50 Rp -

m2 1060.35 874.08 186.27 Rp 250,200.00 Rp 46,605,404.52 46.14 3.09


m2 1060.35 874.08 186.27 Rp 250,200.00 Rp 46,605,404.52
m2 265.32 0.00 265.32 Rp 391,200.00 Rp 103,793,184.00

m2 209.05 209.05 0.00 Rp 35,000.00 Rp -


m2 1260.40 1158.90 101.50 Rp 127,500.00 Rp 12,941,250.00
m2

m2 143.98 143.98 0.00 Rp 42,800.00 Rp -


m2 1498.78 1307.53 191.25 Rp 370,000.00 Rp 70,762,500.00
m2

m2 211.76 0.00 211.76 Rp 42,800.00 Rp 9,063,328.00


m2 140.84 0.00 140.84 Rp 35,000.00 Rp 4,929,400.00
m2

Unit 53.00 39.00 14.00 Rp 2,324,480.00 Rp 32,542,720.00


titik 53.00 39.00 14.00 Rp 259,500.00 Rp 3,633,000.00

Unit 61.00 13.00 48.00 Rp 2,324,480.00 Rp 111,575,040.00


titik 61.00 13.00 48.00 Rp 259,500.00 Rp 12,456,000.00

Unit 1.00 0.00 1.00 Rp -


titik 1.00 0.00 1.00 Rp -

Unit 4.00 0.00 4.00 Rp 168,700.00 Rp 674,800.00


Unit 8.00 0.00 8.00 Rp -
Unit 1.00 0.00 1.00 Rp 62,400.00 Rp 62,400.00
Unit 2.00 0.00 2.00 Rp 75,300.00 Rp 150,600.00
Unit 3.00 0.00 3.00 Rp 56,900.00 Rp 170,700.00
titik 12.00 0.00 12.00 Rp 277,100.00 Rp 3,325,200.00
titik 3.00 0.00 3.00 Rp 345,300.00 Rp 1,035,900.00

titik 2.00 0.00 2.00


Unit 1.00 0.00 1.00
Unit 6.00 6.00
m2

Rp 613,210,131.04
142.5726 43.7
NO URAIAN PEKERJAAN VOLUME SATUAN

I PEKERJAAN DINDING DAN LANTAI


PEMASANGAN VINYL 1000 M2
VINYL 25 ROLL
WELDING 7 ROLL
II PEKERJAAN KUSEN DAN RAILLING

PEKERJAAN PINTU BESI

PEKERJAAN UPVC

PEKERJAAN PENGECATAN RAILLING TANGGA


III PEKERJAAN INTERIOR MELEKAT
R. SEKLUSI
PEMASANGAN HPL 20 ROLL
LEM 8 KALENG
IV PEKERJAAN SANITER
WASTAFEL TOTO 1 BUAH
SPOLL HOOK 2 BUAH
V PEKERJAAN ELEKTRIKAL
CCTV 60 UNIT
AC 6 UNIT
VI PERJAAN ELEKTRONIK
DATA INTERNET
KABEL BC 35 150 M
LAMPU DONLET 80 TITIK
HARGA UPAH JUMLAH KEBUTUHAN MATERIAL

Rp 70,000.00 Rp 70,000,000.00 25 ROLL


Rp 4,440,000.00 Rp 111,000,000.00
Rp 1,000,000.00 Rp 7,000,000.00 7 ROLL

Rp 50,000,000.00 Rp 50,000,000.00

Rp 50,000,000.00 Rp 50,000,000.00

Rp 50,000,000.00 Rp 50,000,000.00
Rp 200,000.00 Rp 4,000,000.00
Rp 730,000.00 Rp 5,840,000.00

Rp 800,000.00 Rp 800,000.00
Rp 1,100,000.00 Rp 2,200,000.00

Rp 1,000,000.00 Rp 60,000,000.00
Rp 23,000,000.00

Rp 95,000.00 Rp 14,250,000.00
Rp 90,000.00 Rp 7,200,000.00

Rp 455,290,000.00
KETERANGAN

JT VINYL

22 PINTU KAMAR 6 PINTU DOBEL, JENDELA,AKRILIK KUNCI


DAUN PINTU DAN HEANDEL

MERK CONCH - TERPASANG KACA, ACLYRIC, JENDELA KISI

AVIAN WHITE COLOUR

SISA 6 KAMAR

14 KG

1,5 PK

12 WATT PILIPP