Professional Documents
Culture Documents
This dewatering plan is developed to address the water ponding issues experienced at Tanjung
Adang Site.
1. Observation
a. Water ponding at site with level recorded at 5.5mCD high at trial pits
b. Main ponding areas are at platform 10,14 and 18
c. Other ponding areas are at pockets of areas at platform 21,22 and at USM areas
d. Ongoing surcharge at platform 1-6, 7,8,9,19,20,23,24,25,26
a. Very unusual observation to identify water ponding on reclamation area with sand material
b. Source of the problem suspected that water is blocked between the
USM area which consists of clay material at a stretch of 300m
and at south side where revetment and geotube (clay could silted up this area)
installed.
surcharge removed platform at P10,14 and P18 with trial pits carried out to confirm.
Water appears in surface could be from heavy down pour and collected within the
circumference of surcharge identified in 1(d)
c. High water table recorded at 5.6mCD is above than the base level of road and drainage. The
condition impedes the construction of road and drainage at ROAD 2 and ROAD 3.
a. Heavy ponding water observed at platform 10,14 and 18 impedes the construction of road
and drainage at Road 3.
b. Same issue could take place at platform 1-6 and affects Road 2 construction and drainage
start
4. Early Approach
A few approach was taken to address this problem since early November 2022
5. Solutions
Main water ponding area is observed between platform 10,14 and 18 (surcharge
removal area)
The water volume is estimated for 6 panels which is P10,P14,P18, P4, P5 and P6
Area 60000 m2
(P4,P5,P6,
Each P10,P14.P18) panel is estimated with water
ponding volume of approximately 3150m3.
Water volume
Differences 1.4 m
Effective capacity (0.1_) 25 m3/hour Based on the water permeability rate. (not
pumping capacity )
- water volume collected at pit and pump
immediately
Days to complete with 7.875 days The period shall drop half with other 50%
4 pumps dewatering taken by soil drains
Dia 0.3 m
Length 400 m
Volume 360 m3
m3/
120
Effective (20%) hour