To Date…………
The Engineer
Dear Sir
May we draw your attention to an apparent ambiguity between the description given in
Bill of Quantities Item …………………and the contradictory specification item page
number…………. (or say between figured and scaled dimensions for …………..).
Should any such instruction cause extra cost, which could not have been reasonably
foreseen we assume that you will be certifying an additional sum to cover the amount
involved.
Yours faithfully
…………………………
Contractor Ltd