You are on page 1of 4

Doc. No.

: EEPL/ELE/33 KV/F-2
CHECK LIST FOR 33KV TRANSMISSION POLE LINE Rev No. 00
Date: 30.04.2023
Project Name : Date:
Package Name: Drawing No:
Contractor Name: Customer Name:
Scope: 33 kV Electrical Line Erection (Internal/ External) Name of Feeder:

From Location: To Location: Length of the Line inspected:

Total No of Poles: No of CPs: No of SPs/ PPs:

Sr. Type of Checks Pole- 1 Pole- 2 Pole- 3 Pole- 4 Pole- 5 Pole- 6 Pole- 7 Pole- 8 Pole- 9 Pole- 10
Description of Checks
No
Pole type
Pre-Erection
Carryout the dimensional checks of poles, channels,
angles, conductors, insulators, hardware's &
Visual/ Measurements/
1 accessories before erection & ensure correct supply
as per work order/ approvals Test Reports

Check no damages, dent, bend, rust for line


2 materials Visual

Check Bitumen paint done at bottom, 1/6th of the


3 pole length (If mentioned in approved drawings) Visual/ Measurements

Check peg marking of poles as per survey


4 Visual
drawing/points
Check the Pole bore depth & diameter as per
5 approved drawing Visual/ Measurements

Check if water found in bore, dewatering should be


6 done before concreting Visual
Pole Erection
Check dia of base round plates & fixing
Visual/
1 arrangement done at bottom of poles before
concreting (As per drawing) Measurements

Check for pole positioning with min.cover from all Visual/


2
sides & vertical alignment Measurements
Check concreting grade & work done as per Uniformity, No cracks/
3 drawing
damages
Check during concreting, poking rod used for
4 compaction Uniform and compacted

Check Pole coping & Muffing done as as per Visual/


5 drawing
Measurements
Check white wash done for pole copping if
6 mentioned in drawing Visual

7 Check curing of pole concreting Visual


Check distance between the poles as per
8 Visual/Measurements
survey/drawing
Hardware Fitting
Check mounting, fixing of pole channels, cross-
arms, angles, conductors, insulators, hardware's &
Visual/
1 other accessories done as per approved drawing
Measurements

Check for stay concreting,


2 stay sets rigidness, fitment & tightness Visual

Check all the bolted joints should be tightened


properly by providing suitable size GI bolts, nuts,
3 with flat & spring washers Visual

Check rating, fixing, binding & tighness of insulators


4 with accessories are done properly Visual
Span Stringing work
Check the Surface condition of conductor for any
1 damages/ untwisting Visual

Check the size & type of stringing conductor as per Visual/


2
drawing/specification Measurements
Check the conductors shall be continuously
observed for loose or broken strands during
stringing.
3 Repair of conductors shall be carried out with Visual
repair sleeves & not more than one repair sleeve
will be used in one span
Check the mid span joints on the conductor shall be
compression type & check no joints shall be made
4 in spans crossing over main roads, railway line and Visual
small river spans

Check for proper tensioning & sag of line span


5 Visual

Check for proper Phase to Phase/Phase to Ground Visual/


6
clearance as per drawing Measurement
Check Jumpering done as per drawing with suitable
7 hardware/clamps Visual
fitments & tightess of nut, bolts
Check for pole earthing done as per drawing
8 Visual

Check tree cutting & tree trimming done through


9 entire route of line Visual
Accessories Works
Check and ensure for Guarding work at road/ line
1 Visual
crossing
Check fixing of anti climbing device
(min 1.2M length), Danger board, Bird guard, Phase Visual/
2
plates,Bird Reflector as per drawing Measurement

3 Check for Pole & Feeder numbering Visual


Pre-Commissioning
Check completeness of line for pre-commissioning
1 Visual

2 Check IR test for completed line Measurement


Comments/Remarks:

Contractor ER-Project ER-Quality Customer


Signature
Name & Designation
Name of Company
Date

You might also like