Connection Conditions
0C.6.2.13
C0C.6.2.13.1
CC.6.2.14
cC.7
Users to comply Quality of Supply Requirements
Users of the Distribution System must not generate Voltage
disturbances at a level that would affect other Users. Users should, in
their own interest, select equipment that is capable of functioning
satisfactorily in the presence of Voltage ranges and disturbances at the
levels that can be expected on the Distribution System as stated in
PC422.
The Distribution System shall comply with the emission limits, which are
set out in PC.4.2.3 (Harmonics) and PC 4.2.4 (Phase unbalance).
User's power quality requirement
User’s developments shall meet the following power quality requirement
assessed at the Connection Point:
1. Harmonic distortion shall be not more than permitted in the most
recent approved version of SASO IEC.61000-3-6;
2. Voltage fluctuations shall be within the limits defined in the most
recent approved version of SASO IEC 61000-3-7;
3. phase unbalance of currents shall not exceed 1% for Users
Connected at MV;
4, Users with transformers which Connect their installation to the
Distribution System shall ensure that the DSP’s requirements for
Voltage stability of the Distribution System are complied with
Special conditions for Power Producers-are presented in PC.6.10.
Metering and Telemetry
‘The User may be required to provide such Voltage, current, Frequency,
Active Power and Reactive Power pulses as are considered necessary
by the DSP to ensure adequate system monitoring. Details will be specified
in the User's Connection Agreement.
Centrally Dispatched Generating Units, shall provide signals to the TSP
as required by the Saudi Arabian Grid Code (SAGC).
If itis agreed between the parties that the DSP shall control the switchgear
‘on the User's system, the DSP shall install the necessary tele control
cutstation. Notwithstanding the above, it shall be the responsibility of the
User to provide the necessary control interface for the switchgear of the
User which is to be controlled.
Metering principles applying to certain Users Connected to the
Distribution System shall be specified in User's Connection
‘Agreements.
Specific metering arrangements depend on the load type, size and nature
of the installations being Connected and are specified in the Metering
Code forming part of this Distribution Code.
SITE RELATED CONDITIONS
In the absence of agreement between the parties to the contrary,
construction, commissioning, contral, Operation and maintenance
responsibilities follow ownership.
‘The Saudi Arabian Distribution Code 95