QUOTATION

REQUEST TAG / SERVICE LOCATION

Ibu TINA
UPS 93E RS EATON RS.MITRA KELUARGA CIKARANG
MIKA COOPERATE

REF. NO CUSTOMER WORK TYPE DESCRIPTION OF WORK

RS MITRA KELUARGA PROJECT PERBAIKAN


Q03910523-MKC.R2 RELOKASI UPS 80 kVa - Op II
MODIFIKASI LAIN-LAIN
GROUP

PRICE
TOTAL
NO DESCRIPTION QTY UNIT UNIT
IDR IDR

1 PREPARATION
- Transportation and accomodation 1 ls 1,000,000.00 1,000,000.00
- Reporting and documentation 1 ls 500,000.00 500,000.00

2 UPS & PANEL REMOVAL AND DISMANTLE


UPS 93E RS 80 kVa, UPS Battery, UPS Panel, DC Panel, Cabble & Tray c/w. material suport, 1 ls 12,500,000.00 12,500,000.00
consumable parts and moving cost to Mika Cikarang

3 UPS & PANEL REINSTALLATION


- Fedder NYY 4x70mm ex.supreme c/w. installation, material support & consumable parts 60 m' 983,500.00 59,010,000.00
- Install UPS unit , UPS Battery, Panel UPS, Panel DC, c/w. re-wiring, terminasi & material support 1 ls 17,500,000.00 17,500,000.00
- Testing & Commissioning 1 ls 3,500,000.00 3,500,000.00

4 VAC INSTALLATION
- IU/OU AC Split Wall - Cap. 9000 Btu/H/ 1PK (ex. Gree Type GWC-9M005) 1 unit 3,525,000.00 3,525,000.00
- Pipe, Refrigerant, Insulation, Saklar, Support, Fitting & Accessories 1 ls 2,125,000.00 2,125,000.00
- Installation, Coring, Material Support & Consumable Parts 1 ls 1,255,000.00 1,255,000.00
- PB Radiation Cover for drain connection 1 ls 1,700,000.00 1,700,000.00

5 PANEL ROOM INSTALLATION (2,5m X 1,8m)


- Gypsum Partisi 12mm, 2 sisi rangka baja ringan 9.92 m2 258,200.00 2,561,344.00
- Sliding Single Door Alumunuium Frame (200x120cm) c/w. rail, handle & accessories 1 ls 2,950,000.00 2,950,000.00
- Painting & Finishing 19.84 m2 68,200.00 1,353,088.00
- Lighting Installation LED Downlight c/w. saklar, material support, consumable parts 2 ttk 385,200.00 770,400.00
- Relokasi TL Lamp 1 ttk 255,000.00 255,000.00

TOTAL IDR 110,504,832.00


DISKON IDR 9,504,832.00
TOTAL EXCL. PPN IDR 101,000,000.00
PPN 11% IDR 11,110,000.00
TOTAL INCL. PPN IDR 112,110,000.00

KETERANGAN :
- Work periode & Deliverry Time 10 days
- Installation Warranty 6 month after BAST
- Term of Payment : 40 % Down Payment, 60% after sign BAST

Bekasi, 26 Mei 2023


PT. KREASI INDO PROSPEK

Beby Ayu Astari


Direktur