Professional Documents
Culture Documents
PLANNING COMMISSION
PC-1 FORM
1. Name of the CONSTRUCTION 04 NOS DAMS IN NAGARPARKAR AREA
Project (THAR REGION).
2. Location The small dam sites are located in Nagarparkar area, about 530 km
east of Karachi town in Sindh near south eastern border with India.
3. Authorities
Responsible for
(iii) Operation and Executive Engineer Small Dams, Division Nagarparkar, Irrigation
Maintenance Department, Government of Sindh
5. (i) Project The Government of Sindh has put great emphasis on the supply of
Objectives and its irrigation and potable water to the population in urban, suburban and
relationship with remote areas. The Irrigation Department, Government of Sindh has
Sector Objectives established Sindh Small Dams Organization (SDO) during 2007 to
carry out studies, and execute construction of Small Dams at feasible
sites within the province. For this purpose the SDO Sindh has already
carried out studies in the regions of Kohistan and Nagarparkar. They
have also initiated construction of about scores of small dams,
retention weirs and bunds both in Kohistan and Nagarparkar areas.
About 6 small dams have been successfully been completed and
yielding the benefits, While the work on 4 schemes is in progress and
expected to be start benefits shortly.
More than 80,000 people live in Nagarparkar area who are poorest
among the poor & 90% of the population is living below the poverty
line.
Drip Irrigation system and Water outlet will be added to the six (6)
existing dams. Four dams which were constructed by some NGO’s in
stone masonry and are now damaged shall be replaced with properly
designed concrete gravity dams.
Capacity of Mean
Catchment
Sr Dam / Bund Reservoir / Annual
Area
No Name/Number Pond Flows
Sq. Km Acre-Ft Acre-Ft
Climatic Conditions
o
Mean Temperature C Evaporation (mm)
Month
Maximum Minimum Maximum Minimum
January 7.80 3.20 80.70 32.30
February 15.30 4.50 103.14 42.00
March 24.20 5.00 147.26 90.20
April 32.20 10.20 211.00 145.50
May 37.80 17.40 280.27 209.20
June 45.20 31.00 329.53 272.50
July 47.80 33.20 323.81 276.30
August 41.40 31.40 304.15 240.00
September 37.20 15.00 244.00 178.20
October 32.10 13.70 215.51 162.70
November 22.10 8.90 155.51 87.50
December 10.80 2.90 100.08 37.40
Inflows at Dam site
The size of storage for any dam depends on inflows available at the
proposed dam or bund site, and total demand for the reservoir to
meet the specific need for which the reservoir is being planned.
Monthly flows of Nagarparkar dams and weir have been worked out
using available rainfall data at Nagarparkar for the period 1926-2009.
The estimated flows are used to working out the reservoir sizes.
Monthly inflows estimated using SCS method and considering the
catchment areas of bunds. Total annual inflow 11537Acre-ft or about
14.23 MCM is calculated for all three categories of proposed dam
weir sites. The highest annual inflow for a single dam / bund is
estimated for Veerawah Bund on Chhariasar Nai which is calculated
as 3,100Acft.
The analysis has shown that the total amount of water reaching into
the proposed reservoirs of all categories A, B and C in an average
year is about 8,955 acre-ft. However, due to limited capacities of
bunds and high evaporation rate in the area about 5,127 acre-ft is
going out of spillways and to evaporation losses, 1,396 acre-ft of
water is recharging the ground water and 2,429 acre-ft is supplied for
the human and animal consumptions.
The maximum amount of water supplied from the Vera Vah reservoir
is about 1930 acre-ft, while the minimum amount of water supplied
from the Khetlai bund is about 2.85 acre-ft.
Sedimentation
Where
qs = sediment annual rate (m3/ km2/yr)
A = the catchment area (km2)
Kb = the ratio between the fractional sediments
(bed load) and the suspended sediments. The
value of Kb varies between 22% and 29%.
6.3 Topographic Topographic surveys of the dam/weir sites and reservoir areas were
Surveys carried out using Total Station and computerized survey techniques.
Degilaized maps for dam site as well as for the reservoir area have
been prepared. GPS coordinates were taken from the equipment for
each works site and these were used for both horizontal and vertical
survey control. The maps were prepared on 1:1,000 scale and have
contours at 1 ft. interval.
Elevation area capacity relation curves for the proposed reservoir
were evolved using the surveyed reservoir area maps. Area and
capacity curves thus developed were used in the reservoir sizing and
carrying out detailed reservoir operations.
Soils
The undulating flat plain is covered with variable soils mainly derived
by erosion and residual weathering of the granites, granite gneisses
and amphibolites.
Residual Soils
Piedmont Deposit
Aeolian Sand
Another physical feature of this arid region are level plains (Playas)
underlain by clays alternating with salt and gypsum, deposited in
broad shallow basin. The deposition is accomplished by inflowing
mud laden local streams after cloudburst. There are numbers of such
shallow depressions and low mounds.
Topography
The central 16km Karoonjhar hill, which rises steeply above the
undulating plain from elevation of 15m to 350m.
Other low level plain grading into Rann of Kutch in north northwest
east and southeast.
Geotechnical Investigation
The rock drilling at site of Khanajo Wandio dam indicates that most of
the strata is granite both pink and black, with likely unconfined
compressive strength of more than 100MPa. The granite is highly
jointed and consequently highly pervious with lugeon value of more
than 100 lugeon (>10-3cm/sec) determined by water pressure tests.
This will require extensive grouting to make the foundation tight and
6.5 Dam Design prevent excessive seepage
Aspects
Most of the work in each scheme is related with the improvement and
upgrading of existing bund. However, the construction of new bunds
and introduction of concrete spillway are also included in the overall
scheme. The dams at Kalidas, More, Tadhio and Miskem Jehan are
essentially concrete gravity weirs. The design features of various
structures are described below.
Embankments
The downstream slopes have been provided with 1ft thick stones
layer over 0.5ft thick gravel bedding as protection against rain
erosion.
The embankment will be constructed of impervious fill containing
particles more than 15% passing Nr. 200 sieve. Embankment will
be constructed in 6” to 12” thick layer compacted by vibratory roller
of 8 – 10 tons. The desired density shall be 98% of the maximum
standard Proctor density.
A downstream toe drain with proper filter and drainage layers have
been provided to intercept the seepage flows and avoid migration
of fines.
Spillways
L= 8/3*(Q)1/2
The exit gradient has been calculated using Khosla method. A safe
exist gradient of 1:6 has been adopted in design.
The concrete cutoff wall has been provided both on upstream and
downstream of the spillway to protect against scour.
Outlet Structure
In class A dams, NGO dams and six existing dams the outlet conduit
with a flow control valve has been provided. At a later stage this outlet
can be connected with a pipeline for drip irrigation and supply of
drinking water.
Structural Design
The stability analysis of both the earthen and concrete sections have
been checked against, sliding, overturning, seepage and uplift
pressures. Necessary safety factors indicated in the literature for
each type of structures have been adopted in the design.
6.6 High Drip Irrigation system may be introduced as a part of the project in
Efficiency the area. This system of irrigation is best suited in arid and semi arid
Irrigation System zones of the world where water is scare and evaporation rate is very
(HEIS) high. During the course of study it was found that with introduction of
this system on 400 acres of land about 38 million rupees of revenue
could be generated every year. It is recommended that a pilot drip
irrigation scheme may be developed as part of present works. For this
purpose an area bout 20 acres each in the vicinity of Vera Vah and
Chanida Bunds may be developed. This pilot scheme shall be based
on cropping of few vegetables and after success of this Pilot Program
on vegetables, the cotton crop may be considered at next. Later if
successful the drip Irrigation system will be added Kalidas dam and
Miskeen Jahan Khoso dam which have relatively larger storage than
the others. .
iii) Provide
technical Covered under 06
parameters i.e.
input and output
of the Project.
Also discuss
technological
aspects of the
Project
iv) Provide
details of civil Covered under 06
works,
equipment,
machinery and
other physical
facilities
required for the
Project
v) Indicate
government Covered under 06
issues of the
sector relevant
to the Project
and strategy to
resolve them
7. Capital Cost
Estimates
Rs(Millions)
Project Cost Rs. 635.000
iii) Schedule
completion period 3.0 years
iv) In case of
revised project Not Applicable
provide
- History of
project approval Not Applicable
year wise PSDP
allocation,
releases and
expenditure.
- Item-wise year-
wise actual 2011-12 2012-13 2013-14
Physical (%) 25% 48% 27%
expenditure and
Financial Million Rs 100 332.792 202.208
physical progress
- Justification for
revision of PC-I
and variation in Not Applicable
scope of project if
applicable
- Item-wise
comparison of
revised cost with
the approved cost Not Applicable
and give reason
for Variation.
Exchange rate
used to work out
FEC in the Not Applicable
original and
revised PC-I’s
8. Annual
Operation &
Maintenance
Cost
Item-wise annual The annual Operation and Maintenance cost has been estimated as
operating cost (5%).of present cost i.e. Rs. 31.750 millions.
based on
proposed
capacity
utilization be
worked-out for 5
years and
sources of its
financing
9. Demand and
Supply Analysis
i) Existing The existing water storage capacity is inadequate for the expanding
Capacity of population of Nagarparkar. The present supply is bout 2700Acre-ft,
Services and its about 3,330,450m3 which comes to about 10 gallon per capita per
Supply day, which is less than minimum recommendation of WHO (70 liters
/ 15 gallon per capita). It is needed therefore that water storage
capacity of dams/bund should be enhanced to increase water
supply level in the area.
iv) Designed The Project will enhance the storage capacity of rainwater in
Capacity & Nagarparkar area to about 5300 acre-ft.
Output of the
Proposed
Project
10 Financial Plan
a) Equity:
Indicate the amount of equity to be financed from each source:
Sponsors own Nil
resources
Federal 635.00 Million
Government
Provincial Nil
Government
DFI’s Banks Nil
General Public Nil
Foreign Equity Nil
(Indicate
partner
agency)
NGO/s Nil
Beneficiaries
Others Nil
Total (Rs: 635 million) 100%
b) Debit:
Indicate the
local and
foreign debit,
interest rates,
grace period
and repayment
period for each Does not apply in view of Para 10 (a) above
loan
separately.
The loan
repayment
schedule be
also annexed
The economic benefits and costs are worked out on the basis of
market prices using this approach the following results are
obtained.
The traditional water rights in respect of the nais are not well
defined in the command area and are total different from the flood
irrigation practice in other parts of the province. The communities
have never used the flood water for irrigation purpose, the main
reason being that the command areas have used either direct rain
or wells. The flood water of the river goes waste in the Arabian
Sea without proper utilization.
After the construction of dams the whole target area would get the
sustainable water availability and there would be no issue of
conflicts over water use.
(b) Demography
(vii) Employment
(x) Cultivation
(xi) Livestock
Employment
Analysis
xii) Employment (a) During Construction Stage
generation (direct
and indirect) Professional and Technical: 30
Administrative, Executive and Managerial: 10
Skilled Workers: 80
Unskilled Workers: 150
Sensitivity
Analysis
xiii) Impact of delays on Delay in implementation of the project will cause increase in
project cost and project cost due to present trend of increase in cost of
viability construction materials such as cement and steel, and increase in
labour salaries and rent of construction equipment due to
increase in the cost of petrol and diesel.
12 Implementation
Schedule
Indicate starting The project Phase-1 is foreseen to be completed in a period of 2
and completion years.
data of the project The construction schedule is attached as Annex-C
Item wise /year As per Annex-C as indicated above
wise
implementation
schedule in line
chart corrected
with the phasing
of physical
activities
13 Management Structure:
13.1 Administrative Irrigation and Power Department, Government of Sindh would be
arrangements for the Administrative Authority for the execution of the Project.
implementation of
project
The project will be implemented through the existing technical
staff of Small Dams Organization comprises a Superintending
Engineer (BS-19), three (03) No Executive (BS-18) along with
adequate field supervisory and office staff.
The salary allowed to them is as per pay scales prescribed by
Government of Sindh.
c) Project Support Steering committee and Project Director / Chief Engineer Small
& Monitoring Team Dams Organization Sindh, Hyderabad along with staff of Small
Dams Organization Sindh would support and monitor the
execution of the project.
13.3 Steps taken to Funds for project implementation will have to be managed by
make proposal provincial Government in accordance with phasing to ensure
implement able and completion of proposed scheme within scheduled time.
early completion
13.4 The manpower The requisite man-power connected with implementation of the
requirements by Project would be met with from the available skill and experienced
skills during field supervisory and office staff of the Small Dams Organization,
execution and Sindh.
operation of the
project the provide
The job description, Staff is already available and no further salary is required
qualification, age
and salary of each
job be provided
13.5 Physical and other Infrastructure has already been provided. These will be managed
facilities required through Contractors.
for project
13.5.2 Materials, spares There are three main components of the Project i.e. (i) Earthwork
and supplies and and (ii) Structure (Concrete) and (iii) Drip Irrigation system with
equipment for of piping works, Solar powered pumps and related accessories.
project.
13.6 In the case of The work for structures and earth embankments will be under
improved material taken by the contractors who will engage their own machinery.
and equipment for
execution, indicate
Approved by SECRETARY
Irrigation Department
Government of Sindh
Karachi