Professional Documents
Culture Documents
June 2021
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
Document Control
Revision History
Issue Date Purpose
Version: Final Rev 0 9 June 2021 Final review
Version:
Version:
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
Separately Volumes
Annex A: Scheme Characteristics for Each Site
Table of Contents
Document Control.................................................................................................................................... i
Acknowledgements................................................................................................................................ vi
Acronyms and Abbreviations ................................................................................................................ vii
Executive Summary................................................................................................................................. 1
Objectives ........................................................................................................................................... 1
Phasing of Study.................................................................................................................................. 1
Methodology....................................................................................................................................... 1
Summary of Results ............................................................................................................................ 2
Preferred Sites .................................................................................................................................... 3
Next Steps ........................................................................................................................................... 6
1 Introduction .................................................................................................................................... 7
1.1 Objectives................................................................................................................................ 7
1.2 Summary of Phase A ............................................................................................................... 7
1.3 Screening for Phase B ............................................................................................................. 9
1.4 Data Acquisition .................................................................................................................... 11
2 Scheme Design .............................................................................................................................. 13
2.1 Methodology......................................................................................................................... 13
2.2 Critical Factors....................................................................................................................... 15
2.3 Scheme Integration with Grid ............................................................................................... 17
2.4 Grid Interconnection ............................................................................................................. 19
3 PV Plant Sizing and Energy Generation Analysis ........................................................................... 24
3.1 Methodology......................................................................................................................... 24
3.2 Area of FSE, Floats and Panels .............................................................................................. 25
3.3 Solar Resource ...................................................................................................................... 26
3.4 PV Output.............................................................................................................................. 28
3.5 Energy output uncertainties and innovations ...................................................................... 29
ii
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
List of Tables
Table 1: Characteristics of top ranked sites ............................................................................................ 3
Table 2: Description of six top-ranked sites............................................................................................ 5
Table 3: Long list of reservoirs considered in Phase A Study .................................................................. 8
Table 4: Reservoirs included in Phase B Study...................................................................................... 10
iii
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
Table 50: LCOE for each site for High Energy Case (15% energy uplift) ............................................... 57
Table 51: Weighted Average Cost of Capital ........................................................................................ 58
Table 52: Financial Internal Rate of Returns of Projects ....................................................................... 59
Table 53: FIRR of Projects if the Tariff is Escalated at Local Inflation ................................................... 60
Table 54: FIRR of Projects if the Tariff is Escalated at Half of Local Inflation ....................................... 61
Table 55: FIRR of Projects is Electricity Generation Increase by 15% .................................................... 62
Table 56: FIRR of Projects if the Tariff is Escalated at Half of Local Inflation and Electricity Generation
Increase by 15% .................................................................................................................................... 62
Table 57: Power criterion MCA parameters ......................................................................................... 66
Table 58: Solar Resource criterion MCA parameters............................................................................ 66
Table 59: Technical complexity criterion MCA parameters .................................................................. 67
Table 60: System integration criterion MCA parameters ..................................................................... 68
Table 61: Environmental impact criterion MCA parameters ................................................................ 68
Table 62: Social impact criterion MCA parameters .............................................................................. 69
Table 63: Economic performance criterion MCA parameters .............................................................. 70
Table 64: Values for MCA criteria ......................................................................................................... 70
Table 65: Unweighted MCA score for each criterion ............................................................................ 71
Table 66: MCA weighting for each criterion ......................................................................................... 72
Table 67: Weighted MCA scores for each criterion .............................................................................. 72
Table 68: Unweighted MCA scores - Sum and Normalised .................................................................. 73
Table 69: Ranked Unweighted Normalised MCA Scores ...................................................................... 73
Table 70: Weighted MCA scores - Sum and Normalised ...................................................................... 74
Table 71: Weighted MCA scores by rank .............................................................................................. 75
List of Figures
Figure 1: Location of top ranked sites..................................................................................................... 6
Figure 2: Map showing location of reservoirs considered in Phase B .................................................. 11
Figure 3: Map of FSE interconnections with CEB Grid .......................................................................... 21
Figure 4: Flowchart for sizing FSE facilities ........................................................................................... 25
Figure 5: Methodology flow chart for MCA analysis ............................................................................ 65
Figure 6: MCA radar chart for Ulhitiya .................................................................................................. 76
Figure 7: MCA radar chart for Kaudulla ................................................................................................ 77
Figure 8: MCA radar chart for Castlereigh ............................................................................................ 77
Figure 9: MCA radar chart for Maduru Oya .......................................................................................... 78
Figure 10: MCA radar chart for Parakrama Samudra ........................................................................... 78
Figure 11: MCA radar chart for Rajangana ........................................................................................... 79
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
Acknowledgements
The authors would like to acknowledge the assistance of the following in preparation of this report:
• Staff of Ceylon Electricity Board, the Irrigation Department of Sri Lanka and the Mahaweli
Authority of Sri Lanka for providing data on the reservoirs and hydropower plant which they
own and operate.
• The World Bank team in Sri Lanka for coordinating data gathering, and for assessment of the
environmental and social aspects of the floating solar energy projects.
• Mr Swetha Perera of RMA Energy for the financial analysis in this study.
• Other members of World Bank’s water and energy teams for their contributions.
vi
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
viii
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
Executive Summary
Objectives
The objective of this study is to identify and select potential sites for grid-scale floating solar energy
(FSE) projects on Sri Lanka’s reservoirs.
The target size for these potential FSE projects is 100 MWp, which is considered an appropriate scale
to make a significant contribution to expansion and decarbonisation of the electricity system, and to
attract international finance.
Preference is given to projects which can operate conjunctively with existing hydropower plant; the
hydropower plant would increase or decrease its output to compensate for variations in the output
of the FSE, to provide continuous generation to the grid.
Phasing of Study
The study has been undertaken in two parts:
• Phase A comprises an evaluation of the amount of renewable energy required to meet Sri
Lanka’s stated renewable energy and climate change mitigation objectives, the contribution
it can make to decarbonisation, and the potential of Sri Lanka’s inland water bodies to
accommodate large-scale FSE. Some 40 sites were identified which might have potential for
FSE, and of these, around half were considered to have potential for schemes of the scale
targeted by this project.
• Phase B, the subject of this report, comprises an evaluation of 23 reservoirs to determine
whether they could accommodate grid-scale FSE, and a multi-criteria analysis to rank these
sites, taking into account seven key criteria,
The results of Phase A have not been repeated in this report, and hence the Phase A Report should
be read in conjunction with this report.
Methodology
The methodology adopted for the Phase B studies comprised of the following:
• Data gathering and collation of the reservoir and hydropower characteristics for the 23
reservoirs under consideration, which are under the ownership of Ceylon Electricity Board,
Mahaweli Authority of Sri Lanka and the Irrigation Department of Sri Lanka.
• Review of the reservoir characteristics, to refine the assessment of the suitability of the
reservoirs to accommodate FSE, and to determine the reservoir area that can reasonably be
covered by FSE facilities. Of the 23 sites under consideration, 21 were assessed to be
suitable for FSE construction.
• Using the analysis of the Global Solar Atlas, determine the installed capacity of FSE and the
estimated annual energy generation. For large reservoirs, the installed capacity is restricted
to around 100 MWp.
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
• Conceptual design of the FSE facilities, taking account of environmental and social conditions
and the extent and location of the reservoir during dry periods.
• Estimates of the capital cost of the FSE facilities, supporting infrastructure and transmission,
and estimates of the annual operating cost.
• Economic analysis to establish the levelized cost of energy from the proposed FSE facilities,
including evaluation of carbon emission and evaporation reduction benefits.
• Financial analysis to determine likely tariff requirements.
• Assessment to identify environmental and social impacts common to all sites, and the
particular E&S issues at each site.
• Multi-criteria analysis of the 21 sites, taking account of the technical, economic,
environmental and social assessments undertaken in the study.
Summary of Results
The Phase B assessment covered 23 sites. Of these, 21 are considered to have potential for FSE
development. Two reservoirs, Kotmale and Rantambe, have insufficient water surface when drawn
down in dry periods to accommodate any significant FSE.
The powerstation of Victoria Hydroelectric project is located at the upstream end of Randenigala
reservoir, and hence the FSE associated with this is located on Randenigala reservoir rather than
Victoria reservoir.
A water surface area of around 1 hectare can accommodate 1 MWp of floating solar energy,
although the net area of panels is only about 56% of this area. In Sri Lankan conditions the plant
factor ranges from 14.7% to 16.5%, meaning that 1 MWp of FSE will deliver between 1285 and 1440
MWh of energy to the grid.
There is potential to develop 100 MWp FSE at 14 of the 21 feasible sites, and three reservoirs can
accommodate FSE in the range 65 to 85 MWp. Two sites can only accommodate around 20 MWp,
and the remaining two only have sufficient area when drawn down for 10 MWp.
Several of the reservoirs are located in or on the edge of national parks and protected areas. The
environmental impacts typically relate to the impact of FSE on wildlife, including elephants and fish.
It has generally been possible to locate the transmission lines outside national parks. The
preliminary environmental assessment suggests that most schemes can be developed providing they
are carefully located. However, where a large percentage of the reservoir surface area is covered by
floats, greater impacts will be expected.
With little land-take, the expected social impacts are small. However, most of the FSE are in areas of
scenic beauty frequented by tourists, and hence sensitive location of the FSE facilities is required.
There are significant health and safety issues when constructing and operating FSE over water,
which will require careful design and implementation of rigorous health and safety plans.
The specific cost of the FSE ranges between $770 and $890 per MWp excluding transmission, roads
and land acquisition, and between $830 and $1230 / MWp when these are taken into account. The
projects at the higher end of this scale are small schemes with disproportionately large transmission
costs.
2
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
The levelized costs of energy (LCOE) ranges from $70 to $105 / MWh in the base case without
consideration of water and carbon benefits. The range is $42 to $76 / MWh when these positive
externalities are taken into account.
If the discount rate is reduced from 9% to 4% to more closely reflect the national cost of borrowing,
the LCOE falls to $49 to $71 /MWh without externalities.
For the financial analysis it is assumed that the FSE will be developed using Project Finance. Various
financing scenarios have been considered, mixing debt and equity from domestic and international
sources. The basic analysis evaluated the financial internal rate of return (FIRR) of all the schemes
under a flat SLR 15 / kWh tariff, and concluded that the projects would not be financially viable. This
results largely from the assumed depreciation of SLR against the USD, increasing the cost of
international debt service in USD terms. The FSE projects generally become financially viable if the
tariffs are escalated in line with the assumed SLR depreciation, meaning the tariff is constant is USD
terms.
Preferred Sites
The multi-criteria analysis (MCA) evaluated the 21 sites using weighted scores for the various
technical, economic, environmental and social criteria, and ranked the aggregate scores. The top six
sites are as follows:
1. Ulhitiya
2. Kaudulla
3. Castlereigh
4. Maduru Oya
5. Parakrama Samudra
6. Rajangana
The key characteristics of these top-ranked sites are shown in Table 1, and a description of the sites
is given in Table 2.
Table 1: Characteristics of top ranked sites
Carbon MCA
Specific
Capacity Energy Benefit
Rank Name Cost Score MCA Radar Chart
(MWp) (GWhpa) (tCO2
(USD/KWp) (out of 5)
pa)
Power
5
Econo… 4
3 Solar…
2
1
1 Ulhitiya 110.0 157.5 847 110,233 3.8 Social
0
Compl…
Enviro… Syste…
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
Power
5
4
Econo… 3 Solar…
2
1
2 Kaudulla 105.8 151.0 875 105,667 3.7 Social
0
Compl…
Enviro… Syste…
Power
5
4
Econo… 3 Solar…
2
1
3 Castlereigh 100.7 130.1 889 91,972 3.5 Social
0
Compl…
Enviro… Syste…
Power
5
Econo… 4
3 Solar…
2
1
4 Maduru Oya 110.0 156.3 907 109,413 3.5 Social
0
Compl…
Enviro… Syste…
Power
5
4
Econo… 3 Solar…
2
Parakrama 1
5 102.6 147.9 844 103,523 3.5 0
Samudra Social Compl…
Enviro… Syste…
Power
5
4
Econo… 3 Solar…
2
1
6 Rajangana 102.5 145.1 886 101,570 3.5 Social
0
Compl…
Enviro… Syste…
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
4 Maduru Oya Maduru Oya is a very large reservoir, with a surface area of 64 sq km, in
the centre-east of Sri Lanka. It has a reasonably small operating range of
14 metres and a very large water surface area, even when drawn down in
the dry season. The reservoir is in a national park and the FSE will
therefore require sensitive development. A 110 MWp FSE is proposed,
which would occupy some 5% of the reservoir surface area at MOL.
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
dry season, would be occupied by the FSE, which would have 102 MWp
installed capacity.
Next Steps
Further review of these sites tends to confirm their ranking, without exceptionally low scores against
any criteria that might be a barrier to development. Hence the top four of these sites are
recommended for the next stage of pre-feasibility study. The schemes ranked 5th and 6th are
considered to be good reserve schemes if problems are encountered with the top four.
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
1 Introduction
1.1 Objectives
The objective of this study it to identify and select preferred sites for development of large-scale
floating solar energy (FSE) facilities of the order of 100 MWp. Preference is given to sites where the
FSE can be co-located and operated conjunctively with existing hydropower plant, as this will
facilitate integration of the FSE into the electricity system.
If co-location is not viable, recognition is given to sites where the FSE can be operated conjunctively
or in close coordination with downstream or neighbouring hydropower projects, and to sites which
are well integrated into the national power grid through direct connection to the 220 kV grid.
In Phase A the potential and need for FSE in Sri Lanka was evaluated. In this Phase B study the
available sites are compared in order to select preferred schemes to take forward to pre-feasibility
study using multi-criteria analysis (MCA).
In order to evaluate and score the characteristics for each site, conceptual designs, analysis of the
photovoltaic (PV) resources, cost estimation, preliminary environmental and social assessment and
economic analysis have been undertaken.
• Sri Lanka has a growing electricity demand, and has already developed its most economical
hydropower resources.
• Until recently, the main option for meeting the growing demand was construction of
additional thermal power projects.
• The falling cost of photovoltaic (PV) solar generation, combined with the new technology of
locating PV facilities on the water surface of reservoirs, offers a new option for providing
affordable electricity in a sustainable manner.
• Electricity demand will grow from around 17,000 GWh to 42,000 GWh, and peak power
demand from 3,000 MW to just over 7,000 MW from 2020 to 2039.
• Some 11,000 MW of new generation capacity is planned to meet the increased demand and
replace aging plant by 2039.
• Under its plan, CEB aims to generate 50% of electrical energy from renewable sources by
2030, although only under conditions of favourable hydrology; in a year of average
hydrology only 35% of energy generation will come from renewable sources.
• The Government of Sri Lanka (GoSL) has recently stated its intent for 80% of electricity to
come from renewable sources by 2030, although this is not yet incorporated in the LTGEP.
• Sri Lanka has over 2,900 km2 of large inland water bodies. Using only 10% of this surface
area for FSE would provide enough energy to meet the total forecast national electricity
demand in 2039.
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
• FSE in Sri Lanka is not constrained by the available resource, but by the ability of the grid to
absorb this energy while maintaining security of supply and grid stability. Existing
hydropower and planned pumped storage can help integrate variable renewable energy.
• There is seasonal complementarity between PV and hydro: solar output is highest in January
to April when hydro generation is low, and hydro production is highest in June, July,
November and December when solar output is low.
• In countries with similar PV resources to Sri Lanka, the Levelized Cost of Energy (LCOE) from
land-based PV is typically around US¢5 per kWh (excluding interconnection and
infrastructure); based on this, LCOE of FSE in Sri Lanka may be around 15% to 20% more (i.e.
around US¢ 6 /kWh). In this Phase B study the LCOE is evaluated for each site.
• Some 40 reservoirs were identified in a long-list that might have potential for FSE, which
were screened to around half that number for evaluation by multi-criteria analysis in
Phase B.
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
Further screening was considered to eliminate any sites with obvious environmental or technical
impediments, but it was concluded that all 23 sites should be considered in the multi-criteria
analysis (MCA). These sites are shown in Table 41. Two sites, Kotmale (10) and Rantambe (18) were
excluded prior to FSE design and MCA as they have been found to have very small surface areas
when drawn down to supply irrigation demand in extremely dry periods.
1
The numbering of these reservoirs has been changed since the Phase A studies, and the revised numbering is
used consistently for identification of sites throughout Phase B.
9
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
10
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
Parakrama Samudrya
Rajangana Reservoir (16) Reservoir (15)
Mahaweli River
Kalawewa Reservoir (6)
This data was supplemented by information in the public domain, including the websites of these
three organisations.
Early in the data acquisition it became apparent that the two critical factors for deployment of FSE
projects on Sri Lanka’s reservoirs were the operating range of the reservoirs and the surface area of
the reservoir when drawn down to its minimum level for irrigation.
Most of the reservoirs in Sri Lanka are used primarily for irrigation, and have the ability to be drawn
down until almost empty to supply irrigation water in very dry years. Several of the reservoirs of the
Mahaweli Cascade also generate hydropower with the released water, but the minimum level for
hydropower generation is typically higher than for irrigation release. Hence the surface area at the
minimum level for irrigation is the parameter that governs how much FSE can be installed.
Another limiting factor for installation of FSE is the range of water levels. For these reservoirs it is the
difference between full supply level (with an allowance of 2.0 m for flood surcharge) and the
minimum drawdown level for irrigation. Current anchorage systems can typically cope with a range
11
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
of up to 35m using elasticated moorings. More sophisticated anchorage systems, possibly requiring
new technology, are required for greater ranges.
As a consequence there was a focus on obtaining accurate data for the surface area and water level
range data, which is shown in Table 5.
Table 5: Key reservoir characteristics for FSE
As there is an intent for the FSE projects to operate in conjunction with existing hydropower plant,
the key characteristics of these plants were also obtained, as shown in Table 6. This data was used
in evaluating whether there is potential for conjunctive operation of FSE and hydro at the sites2.
The blank cells in Table 6 indicate there is no hydropower at the reservoir. The zero values for
Blackpool HEP at Gregory Lake indicate that this mini hydro has been decommissioned.
2
See section 2.3.1 for discussion of conjunctive operation.
12
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
2 Scheme Design
2.1 Methodology
The assessment undertaken in Phase A indicates that under typical solar irradiation in Sri Lanka, a
water surface area of around 1 hectare (ha) is required to accommodate 1 MWp of floating solar
energy facility. Since the aim of this study is to identify prospective FSE facilities of around 100 MWp
installed capacity, 23 reservoirs have been identified where this might be achieved.
In most of the analysis of the reservoirs, the parameters and characteristics for all 23 sites are
presented. However since the analysis determined that FSE would not be possible at Kotmale
(scheme 10) and Rantambe (scheme 18), designs have not been carried out at these two sites.
Hence design parameters are not presented in the tables for these two sites, and the rows are left
blank.
The design process assesses the smallest surface area of these reservoirs when they are drawn down
to their minimum operating level during extremely dry periods. In multi-purpose reservoirs the
13
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
minimum level is generally governed by the irrigation outlet, which is typically lower than the
hydropower outlet.
In reservoirs where the surface area is close to 100 ha at minimum operating level (MOL), it is
assumed that virtually all of this residual area can be used for FSE. Where the minimum area is
greater than 100 ha, it is assumed that only around 100 ha will be used initially for FSE.
In order to identify where the residual pond will be located, use has been made of the timeline
facility on Google Earth Pro. This enables historic satellite photos to be examined, including some
taken during very dry periods when water levels are low. The location and shape of the reservoirs
during these dry periods is the primary factor in determining the shape and location of the FSE on
each reservoir.
At this stage no attempt has been made to form the FSE facility into islands3 – only the overall shape
and location on the reservoir have been identified. These layouts are presented in the description of
each site in Annex A. Reasonable margins have been allowed within the designated area for
arrangement and spacing of islands, and for the space on the floats for walkways, inverters and
other scheme components, as shown in Table 7. It is particularly important with FSE for walkways to
be provided to allow for cleaning of panels.
Table 7: Area occupied by floats and panels
Having assessed the area and location of the FSE facility, use has been made of the Global Solar Atlas
(GSA)4 to assess the estimated energy production from the area allocated to the FSE. The process is
described in section 3.
Having identified the location of the FSE facility to suit the residual location of the reservoir when
drawn down to its lowest level, the location of the land-based facilities was selected taking into
account various factors including:
3
FSE facilities are typically grouped into islands, where a number of floats are linked together, physically and
electrically, to form convenient sized sub-units. These islands are shaped and located to fit within the overall
shape of the facility.
4
GSA is an on-line resource developed by ESMAP, an affiliate of World Bank Group, and Solargis.
14
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
On the large reservoirs, where there was scope to move the FSE, the location of the FSE also took
these factors into account. Where there is room the FSE has been kept away from spillways where
there might be high flow velocity during floods, although this has not always been possible.
The above assessments have been made solely on the basis of remote sensing using existing
mapping and satellite imagery. It will need to be reviewed at later stages of project studies.
Where the reservoirs are located in the hilly areas of central Sri Lanka, the steep sided valleys mean
that high dams have been used to optimise the water storage. As a consequence these dams have
large operating ranges – for example 75 metres at Kotmale and 55 metres each at Victoria and
Randenigala.
The current limit for water level variation for the design of anchors for floating solar projects is
around 35 metres, although design innovations are being developed to for a greater range.
The combination of a large water level range with potentially high wind speeds during tropical
cyclones present significant challenges for
FSE designers. Seaflex anchor limits
For the initial FSE projects in Sri Lanka it will “At Seaflex we have supplied customized, site-
be prudent to select sites that lie within the specific mooring systems designed by our in-
range of existing proven technology, which house engineers to locations all around the world
will facilitate development and financing. since 1987. Floating solar systems secured with
From Table 8 it can be seen that 19 of the 23 Seaflex have survived hurricane-strength winds,
reservoirs under consideration have an and we have documented references
operating range that is within the limits of dimensioned for 35-meter water level variations
current anchor technology, with only and 90-meter depths. We have the products,
Samanalawewa, Victoria, Randenigala and knowledge, and experience to securely moor
Kotmale outside these limits. your application.”
Source: Seaflex website (www.seaflex.net)
5
The head in a hydropower scheme is the difference in water elevation between the reservoir and the turbine
discharge point, which provides the pressure to drive the turbines.
15
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
As most of the reservoirs under consideration are operated to provide water for irrigation, they can
be drawn down to low levels in dry periods, as illustrated in Table 8. Since the FSE facility needs to
be located in the part of the reservoir that remains as open water at this minimum level, it
inherently means that the FSE is generally located in the deepest part of the reservoir. The
exception to this is where a large pond remains at maximum drawdown, giving more flexibility for
the location of the FSE facility.
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
of at least 100 ha is needed to achieve the target installed capacity of 100 MWp. The water surface
area at MOL irrigation is shown by rank of size in Table 9, indicating that 14 of the 23 reservoirs have
sufficient residual area when drawn down to allow a 100 MWp FSE to be developed.
Table 9:Water surface area at Minimum Operating Level (irrigation)
In order to permit conjunctive operation, the hydropower plant must have particular characteristics
as follows:
• Adequate storage so that water can be retained when the hydro plant is ramped down,
rather than being spilled to waste. This will normally be the case for reservoirs with
sufficient area for FSE, but may not if the hydro is operated at a constant level. Loss of
17
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
water may also occur if the reservoir is full and spilling. For the reservoirs under
consideration in this study, there is generally ample storage, although some water loss may
occur at times of floods when the reservoirs are full. Although this represents some loss of
energy, it tends not to have great value as the system will probably have surplus energy.
• The hydro plant needs to be able to operate flexibly, without restrictions on the amount or
duration of flow release that prevent it from following the FSE output. For the reservoirs
under consideration in this study, only Victoria is able to operate without such restrictions.
All of the MASL and ID owned reservoirs are operated giving priority to irrigation flow, and
hence the timing of water release is dictated by irrigation requirements6. Victoria also
provides irrigation water, but it has the large Randenigala reservoir immediately
downstream that can re-regulate the flow pattern. Castlereigh and Moussakele are operated
giving priority to hydropower generation, but as they are each at the head of hydropower
cascades, complex operating rules would be required to ensure that the generation from
downstream hydro plant is not disrupted. Provided that these rules are established, FSE at
Castlereigh and Moussakele reservoirs would be able to operate conjunctively with the
downstream hydro plant in their respective cascades.
• The hydro plant must not be required for other system support services. Hydro schemes
provide services other than energy generation including inertia, frequency response, voltage
management and reactive power. If the plant is required to be generating to provide these
services, it may not be able to vary its output for conjunctive operation. Some of the
hydropower plant in Sri Lanka are required to operate to provide grid stability and other
services, and this aspect will need to be studied in detail during feasibility studies.
In practice only Victoria HEP can be operated conjunctively with FSE most of the time, as it has a
large re-regulating reservoir downstream. At all of the other hydropower stations, the need to
release irrigation water may require the hydro plant to operate simultaneously with the FSE, or
otherwise, to release water without generating. More detailed studies at pre-feasibility stage may
find more opportunities for conjunctive operation, such as at Randenigala, Bowatenna and
Samanalawewa, but at this stage it is assumed that conjunctive operation would not be possible.
In order to achieve this the operation of both hydropower and FSE plant should not be constrained
by the characteristics of the power grid.
As the amount of variable renewable generation on the Sri Lanka grid increases, it is likely that
battery energy storage systems (BESS) will need to be provided to cope with very short-term
6
More detailed studies may identify potential to re-regulate flow in downstream off-channel tanks and
reservoirs, or for conjunctive operation to be possible at certain times of year.
18
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
generation and demand variations. The BESS may be co-located with the generation plant (e.g. at
the substation of FSE facilities) or more likely close to the main load centres.
The ability of the FSE to integrate efficiently into the power system, and to operate conjunctively
with remote hydro plant and BESS will be greatest if it has a strong connection to the grid. This is
most likely to be achieved if the FSE is connected directly to the 220 kV grid, or connected to a
132kV grid substation that has a direct link to the 220 kV grid.
In Table 10 each site is assessed for its potential to operate conjunctively with a co-located hydro
scheme, operate with downstream or nearby hydro plant, and whether it shas a strong direct link to
the 220kV grid through its grid connection point. These parameters are used in the multi-criteria
analysis as measures of the ability of the FSE to integrate into the power system.
Table 10: Conjunctive operation and system integration
19
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
2.4.1 Assumptions
For the purpose of this study, the FSE projects are assumed to be connected to the nearest grid
substation that is likely to have adequate capacity.
Three transmission voltages are used to match that of the existing grid in Sri Lanka: 33 kV, 132 kV
and 220 kV. No system studies have been undertaken, and the voltage selected for each site has
been selected based on the author’s experience of similar projects and the nature of the grid, taking
account of power transfer requirements and transmission line length. The outcome is that schemes
with installed capacity of less than 20 MWp are connected by 33 kV lines, with the larger schemes
connected at 132kV or above.
Where possible, use is made of existing transformer capacity. This is possible where the FSE can
operate conjunctively with a co-located hydro scheme, or where the grid substation has
transformers of adequate capacity feeding the local demand, and the electricity flow direction is
reversed by connecting generation to the demand side.
The planned projects, typically with around 100 MWp installed capacity, are sizeable relative to the
loads on most of the rural grids. The output from FSE facilities can vary rapidly due to cloud cover,
and since they do not have built-in inertia, there is potential to introduce disturbance if connected to
weak transmission systems. Hence the strongest possible connection points have been chosen, with
direct access to the 220 kV grid if possible.
20
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
21
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
There are other options for connection of the FSE facilities to the grid that would reduce the cost: in
particular there are opportunities to make “Tee-connections” to the 132 kV grid where it passes
close to the FSE site. This would reduce the length of transmission line required, and hence reduce
the cost. However it has not been common practice in Sri Lanka to connect generation plant to the
grid in this way, so investigation of this option is deferred until future stages of study. Some of the
options that may be considered in future studies are shown in Table 12.
Table 12: Transmission options
22
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
In practice it has been possible to avoid construction of any major new roads. All of the sites are
located adjacent to existing roads. A notional allowance has been made for 0.5 km of access road
for each site for a spur from the existing road and local site roads. Provision for this is included in
the cost estimate, and an allowance for the road wayleave is also included in the area of land to be
acquired.
23
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
As well as the floating facilities there is a requirement for some land-based facilities including
substations. A provision for the cost of acquiring land is included in the financial model, based on an
area requirement of 100 m2/MVA of substation capacity.
Inverter stations can also be located on land, with an area requirement of 25 m2/MVA of inverter
capacity. However in view of the relatively large size of the proposed facilities, and the electrical
losses that would be incurred in long, low voltage dc cables, it is assumed at this stage that the
inverters will be located on floats.
Control buildings and operators’ facilities will be included within the land-based substations.
Design of the FSE facilities is carried out for 21 of the 23 reservoirs, since Kotmale and Rantambe
were found to have insufficient area at MOL to accommodate significant FSE. However for
completeness the PV resource at these two sites is included in the relevant tables.
3.1 Methodology
The methodology used for design of the floating solar energy systems, and for estimating the energy
output, is illustrated in the flowchart in Figure 4.
The first stage of the process is to determine the area that is available for the FSE facility, the area of
floats and the net area of panels, as described in section 2.1.
The number of panels that can be located in this area is determined by dividing the area by the
selected panel size. For this study 72 cell panels have been adopted, which are 1.96m long x 0.99 m
wide, giving an area of 1.94 m2.
From the GSA, the energy output to the grid (PVout) per MWp at the project location is determined,
and the output to the grid in kWh/m2 is calculated. Based on this, and the selected panel size in m2,
the theoretical output in Wp per panel is calculated. Since panels are typically available in 5 Wp
increments, the theoretical output is rounded down to selected one of the standard panels.
Knowing the number of panels that can be located at the site and the output of each panel, the
Installed Capacity can be calculated.
From the GSA tool the capacity factor for FSE at the location can be calculated, and when applied to
the Installed Capacity, this yields the estimated energy production.
24
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
Is area at MOL
significantly no Determine % of residual area
greater than that can be used for FSE
100 ha?
yes
Determine % of surface
required for ~100 ha of FSE
Designs have been carried out for 21 of the 23 sites. As can be seen in Table 13, two reservoirs,
Kotmale and Rantambe, have insufficient surface area when drawn down, to accommodate any
significant FSE. Being in hilly terrain there is little prospect of the floats being able to settle on the
reservoir bed. Hence no design parameters are presented for these sites.
25
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
Table 14, which also describes the section of the reservoir of this location.
Table 14: Location of sites analysed in GSA
26
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
The initial analysis for each site is undertaken for a notional 1000 kWp (i.e. 1 MWp) FSE project to
facilitate the comparison of the resources at each site. The results of this analysis are presented in
Table 15.
Table 15: PV data from GSA for 1 MWp FSE
27
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
The sites are ranked in terms of solar resource in Table 16 on the basis of Global Tilted Irradiation
(kWh/ m2)
Table 16: Solar resource by rank (GTI)
3.4 PV Output
The results of the PV simulation modelling are shown in Table 17.
Full details of the simulation are presented in Annex B, which contains the detailed reports
generated by the Global Solar Atlas for each site. Among the data in these reports are:
28
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
7
Capacity factor is the actual energy generation from the plant divided by the theoretical energy if the plant
generated at its installed capacity all the time (i.e. 8760 hours per year).
29
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
location in Sri Lanka show that the FSE output is around 8% less than for ground mounted PV,
according to the GSA.
There is a general perception that FSE produces more energy than the land-based equivalent.
However the GSA takes a cautious approach due to the novelty of the technology. In particular the
GSA is conservative about the ability achieve the optimum inclination of the panels, and the
propensity for panel output to be reduced by bird-fouling.
At higher latitudes the optimum tilt to maximise PV output can be as steep as 40o. With FSE, panels
can only be tilted up to 15o, meaning that PV output is reduced relative to ground mounted PV,
where the tilt is not constrained. In Sri Lanka the optimum tilt angle is around 8o. While it should be
possible to mount the FSE panels at this optimum angle, it will increase the vulnerability of the FSE
facilities to high wind speeds, and a balance may need to be struck between the optimum tilt angle
and reducing wind loading.
On some of the early FSE facilities the incidence of bird fouling has been high, with waterfowl
attracted to the floating facilities for safe nesting. On small facilities this has significantly reduced the
energy output due to coverage of a substantial proportion of the panel area with excrement,
requiring regular mechanical cleaning. It is not clear whether large FSE for example the 750,000
square metres of floats for a 100 MWp facility, will be similarly affected.
For the purposes of this study, which focuses on comparison between the different sites, the GSA
energy outputs have generally been adopted. However a sensitivity case, where the FSE output is
increased by 15% above the GSA calculation, is presented in the LCOE and Financial analysis.
There are a number of innovations that may enhance energy output from FSE facilities in the future
including:
• Active cooling: The output of PV panels is rated at 25oC and panels typically lose 0.4% of
output per degree above 25oC. Since the panel temperature can reach 65 oC, it implies a loss
of some 15% of energy relative to the rated output. Panels located over water in FSE
facilities benefit from some natural passive cooling, which is taken into account in the GSA
analysis. However active cooling could significantly reduce the panel temperature further
and therefore increase the energy output. Trials to date have focused on mist sprays, but
these leave a film of salts when the water evaporates, tending to be counter-productive.
Active cooling by pumping reservoir water through heat exchangers when the panels are
hot, may be a more productive solution.
• Tracking: Trials are underway using winches to rotate islands of panels through the course of
the day to track the sun, thereby increasing the energy output. These winches can also be
used to rotate the islands for optimal alignment during storms to minimise wave and wind
loading.
• Mechanised cleaning: Currently panel cleaning is undertaken using rotating brushes and
water pumped from the reservoir to remove dirt, including bird excrement. These cleaning
machines are manually guided, and cable and hose management is labour-intensive. In
future automation could reduce the cost of this process. However in the interim the process
can be facilitated by provision of adequate walkways and built-in hose and cable connectors,
ensuring that regular cleaning can be carried out.
30
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
These options for increasing FSE output can be investigated during the pre-feasibility and feasibility
studies to ensure more accurate estimates of the FSE energy production.
The studies consider the generic impacts of floating solar energy projects when undertaken in the Sri
Lankan environment. Location and project-specific assessment has been carried out, taking into
account factors such as:
Summaries of the findings are presented in sections 4.3 and 4.4, and the project-specific assessment
is presented for each site in Annex A.
The environmental and social analyses form a key input to the multi-criteria analysis (MCA). Each
site has been marked for five environmental and five social categories, and these marks have been
weighed and normalised for input to the MCA. The marks for each site are shown in the tables in
sections 4.3.6 and 4.4.6 respectively for the environmental and social assessments.
The environmental and social analysis provides a means of comparison of the sites for the MCA
analysis, and helps with scoping the studies that will be required in later stages of project
development.
In general, where the coverage by floats is a low percentage of the surface area at MOL, the sites are
likely to have a lower impact than where it is a high percentage.
31
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
Table 18: Area of MOL and of FSE components as percentage of FSL are
32
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
11 Maduru Oya 5% 3% 3%
12 Minneriya 95% 65% 53%
13 Moragahakanda 15% 10% 8%
14 Moussakele 60% 41% 33%
15 Parakrama Samudra 16% 11% 9%
16 Rajangana 32% 22% 18%
17 Randenigala 15% 10% 8%
18 Rantambe
19 Samanalawewa 32% 22% 18%
20 Senanayake Samudra 75% 51% 42%
21 Uda Walawe 15% 10% 8%
22 Ulhitiya 10% 7% 6%
23 Victoria 90% 61% 50%
4.3.1 Ecology
Many of the reservoirs are located in ecosystems of high and complex biodiversity, including all
categories of flora and fauna. Exiting studies have identified important mammal, fish and migrant
bird species that will require further study and conservation.
The shading from panels, especially where a high percentage of the reservoir is covered, may affect
aquatic plants, algae and zooplankton, with consequent impacts on reservoir ecology.
As well as impacts of the proposed FSE on wildlife during construction and operation, the impacts of
wildlife on the project components will need to be considered. This includes damage by elephants
seeking water, and waterfowl seeking nesting sites on the floats.
High levels of sedimentation is a feature of several reservoirs, and the impacts of this on the project
components will need to be addressed. Additionally, any plans for de-silting the reservoirs will need
to be considered when selecting sites for the FSE.
33
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
from pollution from improper solid waste disposal. Some reservoirs are noted to be affected by
runoff from agricultural areas of from industries. Heavy metals are also observed in some reservoirs.
There is concern that shading from the FSE will reduce sunlight and oxygen levels, potentially leading
to anaerobic decomposition of biomass and waste. This issue will require further study.
Development of FSE within protected areas is not necessarily precluded, provided that it is done
with sensitivity. In the preliminary designs, attempts have been made to ensure that the FSEs are
close to existing infrastructure, and that land-based facilities, including transmission lines, do not
impinge on the protected areas.
This issue will need to be studied further if any of these sites are selected for development.
Care will be needed when constructing the workers’ camps, construction facilities and access roads
to ensure they do not interfere with reservoir users, including tourists, and that waste is disposed of
in an acceptable manner.
An issue for all of the sites, which has therefore not been included in the MCA analysis, is the end-of-
life recycling and disposal of the FSE components, including replacement of failed components
during the operating life of the schemes. Plans will need to be developed within the environmental
and social management plans.
34
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
The weightings used in the environmental sub-analysis are shown in Table 22:
Table 22: Weightings for environmental sub-analysis
The weighted and normalised scores from the environmental sub-analysis are shown in Table 23.
35
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
These weighted and normalised scores from Table 23 are presented in Table 24 in ranked order,
with Rank 1 being the site with lowest negative environmental impact.
Table 24: Ranked environmental assessment scores
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
11 Kaudulla 2.84
12 Moussakele 2.84
13 Rajangana 2.81
14 Uda Walawe 2.52
15 Chandrika Lake 2.45
16 Bowatenna 2.32
17 Kantale 2.13
18 Senanayake Samudra 1.68
19 Victoria 1.68
20 Kalawewa 1.48
21 Minneriya 1.32
22 Kotmale
23 Rantambe
4.4.1 Resettlement
Resettlement is not regarded as a significant issue for the FSE projects. No population will be
displaced for the panels, and it is anticipated that none will be required for the land-based facilities.
The lack of population displacement and minimal land required for land-based facilities is a key
advantage of FSE over other generation technologies.
The development of FSE on reservoirs in unlikely to interfere with irrigation or hydropower, although
the drawdown of reservoirs for these functions, as discussed in section 2.2.1, is a key factor when
considering the installation of FSE.
Shading of the reservoir by FSE has potential to affect the quality of water: shading has been used to
improve water quality, but the impact will need to be assessed at the individual sites.
Reduction in evaporation increases the amount of water available for irrigation, water supply and
hydroelectric generation, as discussed in section 6.2.2.
Several of the reservoirs are used for commercial fisheries. Assessment will be required to ensure
compatibility between the FSE location and the area used for fisheries. Studies are also required on
37
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
the impacts of shading on the ecosystem that supports the fish, and the dissolved oxygen (DO) levels
in the water. Some of the impacts are expected to be beneficial, and others detrimental.
Cultural property generally does not have a significant impact on development of FSE, but further
studies will be required at the selected sites.
FSE plant includes long lengths of high current cabling, and both high and low voltage equipment.
The relative movement of floats and pontoons can abrade and loosen cables, and the presence of
water can aggravate the hazard.
The risks associated with working over water are significant, especially with moving floats and
pontoons with small walkways.
Implementation of well-defined health and safety plans will be necessary, both during construction
operation, including restriction of access to appropriately qualified personnel.
The health and safety risks peculiar to individual sites generally relate to different uses of the
reservoirs, such as by fishermen, and the use of reservoirs for washing and bathing.
Some of the reservoirs are known to host crocodile populations, and these may be a significant
threat to personnel involved in construction and operation. Other wildlife, including elephants, will
also pose a threat at some locations.
Sensitive location of the FSE facilities and land-based structures will be required to minimise the
impact on tourist and leisure facilities, and to reduce the visual impact from popular tourist viewing
points.
38
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
The weightings used in the social impact sub-analysis are shown in Table 26:
Table 26: Weightings for social impact sub-analysis
Characteristic Resettlement Economic Cultural Property Health and Safety Leisure and
Activities Tourism
Weightings 0.5 0.6 0.5 0.9 0.4
The weighted and normalised scores from the environmental sub-analysis are shown in Table 27.
Table 27: Social impact sub-analysis weighted and normalised scores
39
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
These weighted and normalised scores from Table 27 are presented in Table 28 in ranked order,
with Rank 1 being the site with lowest negative socio-economic impact.
Table 28: Ranked socio-economic assessment scores
40
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
5 Cost Estimation
5.1 Methodology
Capital cost (capex) and operating cost (opex) estimates have been developed for each site based on
its characteristics, using unit rates for each component. For the floating solar facilities, the rates are
derived from the Floating Solar Handbook8, adjusted for expected rates in 2021, and disaggregated
to provide greater granularity. For other components, such as transmission lines and substations, the
rates are derived from experience of unit rates in Sri Lanka, verified in discussion with domestic
contractors.
All costs are presented in USD, as this is the currency in which most international cost data is
available.
The cost of anchors has been adjusted by a factor to take account of the complexity that results from
the operating range of the reservoir. Reservoirs with a very small operating range of less than
5 metres are not adjusted, and the adjustment factor increases with the operating range, as shown
in Table 30. The cost model includes a facility to manually adjust the complexity, and this has been
8
World Bank Group, ESMAP and SERIS. 2019. Where Sun Meets Water: Floating Solar Handbook
for Practitioners. Washington, DC: World Bank.
41
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
used on Iranamadu to allow for the cost of bed preparation to allow the floats to rest on the dry
reservoir bed.
Table 30: Anchor complexity cost adjustment factors
The unit rates used to estimate the cost of substations and transmission lines to interconnect each
site are shown in Table 31. These rates are applied to the transmission line lengths as shown in Table
11. The substation rates are applied as required for the components at each substation, as follows:
• Civil works costs are included for each new substation or switchyard, but are not required
when expanding an existing substation.
• Line bays are necessary for each line in and line out of a substation at the appropriate
voltage level.
• Transformer costs are applied to the MVA rating of the required transformers.
Table 31: Unit rates for substation and transmission lines
The short lengths of access road have been priced at USD 300,000 per km.
42
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
The estimated cost of land acquisition is shown in Table 32 in USD per ha. The sites are located
across a wide area of Sri Lanka, and land costs will vary at each site, and for different areas at each
site. For a study at this level it is only practical to use an average figure. However, land costs for
floating solar tend not to be significant. For this study the land costs are typically 1% or less of
capital cost, with the exception of Kalewewa and Kantale which have long transmission lines for
small projects.
Table 32: Unit rates for land acquisition
43
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
The total project cost for each site is shown in Table 34. This cost includes the cost of the FSE facility
in Table 33 together with the cost of the grid interconnection, access roads and land required for the
permanent works.
Table 34: Estimated cost of FSE projects including interconnection
In Table 35 the estimated project cost is summarised, and the percentage for each major component
is presented. The specific cost per unit installed capacity is derived by dividing the total project cost
by the installed capacity. It can be seen that the specific cost varies significantly from 830 to 1277
USD/kWp, with the smaller schemes generally having higher specific cost. This is primarily due to the
smaller schemes having a relatively higher cost of interconnection to the grid.
Table 35: Summary of project costs and components
44
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
In Table 36 the sites are shown ranked low to high by specific cost (USD/kWp). When comparing FSE
sites with similar capacity factors, the specific cost provides a reasonable indicator of the relative
economic performance of the sites in the absence of economic modelling. However in Sri Lanka
there is sufficient difference between the solar resource and energy output at each site for the
ranking based on levelized costs of energy (LCOE), as shown in Table 46 to differ from that in Table
36, and hence LCOE is preferred for the economic comparison.
Table 36: Sites ranked by specific cost (USD/kWp)
45
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
11 Moussakele 895.7
12 Iranamadu 899.1
13 Maduru Oya 907.0
14 Moragahakanda 913.8
15 Gregory Lake 915.7
16 Victoria 926.2
17 Randenigala 939.7
18 Kalu Ganga 945.4
19 Samanalawewa 964.6
20 Kalawewa 1,267.9
21 Kantale 1,276.7
22 Kotmale
23 Rantambe
A summary of the estimated O&M cost is shown in Table 38. The costs range from USD 0.19 for
small FSE facilities to USD 1.96 for the largest and most costly site. These costs are used in the
economic and financial models.
46
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
6 Economic Analysis
6.1 Methodology
The methodology used to assess and compare the relative economic performance of the FSE sites is
based on the Levelized Cost of Energy. This metric determines the net present value of the
expenditure stream divided by the net present value of the energy expected to be generated.
For the purposes of this study, in order to allow all of the sites to be modelled and compared, a
simplified methodology using annuitized capital expenditure is adopted as follows:
((𝐶 × 𝐶𝑅𝐹) + 𝑂𝑓 )
𝐿𝐶𝑂𝐸 = + 𝑂𝑣 + (𝐻𝑅 × 𝑃𝑓 )
(8760 × 𝐶𝐹)
Where:
𝐶𝐹 = 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑓𝑎𝑐𝑡𝑜𝑟
𝑂𝑣 = 𝑉𝑎𝑟𝑖𝑎𝑏𝑙𝑒 𝑜𝑝𝑒𝑟𝑎𝑡𝑖𝑜𝑛 𝑎𝑛𝑑 𝑚𝑎𝑖𝑛𝑡𝑒𝑛𝑎𝑛𝑐𝑒 𝑐𝑜𝑠𝑡 (USD/MWh)
47
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
For floating solar energy projects the variable operating cost is effectively zero, and no fuel is used to
create electricity, hence:
((𝐶 × 𝐶𝑅𝐹) + 𝑂𝑓 )
𝐿𝐶𝑂𝐸 =
(8760 × 𝐶𝐹)
The Capital Recovery Factor is the annuity formula, which is the same as Excel’s PMT function, giving
repayment of capital at a constant annual rate for a given interest and loan term in years, and is
derived from the following formula:
𝑖 × (1 + 𝑖)𝑡
𝐶𝑅𝐹 =
((1 + 𝑖)𝑡 − 1)
Where:
𝑖 = 𝑖𝑛𝑡𝑒𝑟𝑒𝑠𝑡 𝑟𝑎𝑡𝑒
𝑡 = 𝑝𝑎𝑦𝑚𝑒𝑛𝑡 𝑝𝑒𝑟𝑖𝑜𝑑 (𝑠𝑒𝑟𝑣𝑖𝑐𝑒 𝑙𝑖𝑓𝑒) in years
A base case interest rate of around 9% is commonly used for LCOE analysis. However, this is a high
economic interest rate when evaluating projects in terms of national benefit, when perhaps a rate
closer to the national cost of borrowing9 might be more appropriate. High interest rates weigh
heavily against high capex/low opex technologies, such as FSE, in favour of low capex/high opex
technologies, such as coal and gas-fired generation. A sensitivity case of 4% is therefore also
presented, which may be more appropriate when evaluating technologies in the context of the
national economy.
The Capital Cost (capex), Operating Cost (opex) and Capacity Factors vary for each site, as shown in
Table 33 (capex), Table 38 (opex) and Table 17 (capacity factor).
In addition to the base case economic analysis that considers capex, opex and energy benefit,
sensitivity cases have been carried out considering the values of carbon emission displacement and
water savings through reduced evaporation.
9
The current (April 2021) IBRD Flexible Loan Rate for Sri Lanka for USD loans ranges from LIBOR+0.8% for up to
8 years, to LIBOR+1.02% for 18-20 years Lending Rates & Fees (worldbank.org). 6-month USD LIBOR (the
reference rate) is currently at historically low levels around 0.2%, although it has not exceeded 3% in the past
decade.
48
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
• The benefit from displacing generation that is more carbon intensive, hence reducing the
overall CO2 emissions.
• The reduction in evaporation from the reservoir surface, saving water for other productive
uses.
These benefits can be taken into account by reducing the LCOE as follows:
((𝐶 × 𝐶𝑅𝐹) + 𝑂𝑓 )
𝐿𝐶𝑂𝐸 = − 𝐵𝑐 − 𝐵𝑤
(8760 × 𝐶𝐹)
Where
The shadow price of carbon has taken account of various advisory sources. World Bank11
recommends arrange from USD 40 to USD 80 per tCO2 for 2020, increasing over time. ADB and some
of the European institutions recommend a rate closer to USD 40 per tCO2. The adopted value of USD
40 per tCO2 is at the bottom end of World Bank’s range, and is therefore considered conservative.
Table 40: Carbon displacement parameters
10
The average carbon intensity in 2017 from Figure 10.1 of the LTGEP is 700 kg/MWh.
11
Guidance note on shadow price of carbon in economic analysis, Nov 12, 2015.
49
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
irrigation water, and it is likely that most of the water saved from evaporation would be used for
irrigation.
The value of water for irrigation has been estimated12 at US¢ 5.0 per cubic metre in 2020 prices.
The reduction in evaporation is taken as 1.00 metre / square metre of water surface area. This is an
approximation to give a high-level estimate of the additional water available, and an estimate of the
value.
In order to determine the value of additional water for hydropower generation, the hydro energy is
estimated from the power formula:
𝑄×𝐻×𝜂×𝑔×𝜌
𝑃=
10^6
Where:
𝑃 = 𝑝𝑜𝑤𝑒𝑟 𝑖𝑛 𝑀𝑊
12
Balancing Irrigation and Hydropower: A case study from Southern Sri Lanka, Research Report 94, 2005. Value
Rs 1 to Rs 5 – say Rs 3 in 2005 = US¢ 3 or approximately US¢ 5 in 2020.
50
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
Based on the methodology in section 6.2.2 and the characteristics of the reservoirs, hydro plant and
FSE facilities, the secondary benefits associated with reduced evaporation have been calculated.
In Table 43 the value of water resulting from reduced evaporation when used for irrigation is
presented for each site.
Table 43: Value of water saved when used for irrigation
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
In Table 44 the value of water resulting from reduced evaporation when used for generation in
downstream hydropower plants is presented for each site. This is based on 80% of the saved water
being used for generation, since some may be spilled to waste.
Table 44: Calculation of hydro benefit from water saving
52
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
16 Rajangana 0.70
17 Randenigala 0.75 Randenigala, 111 155 0.009
Rantambe
18 Rantambe Rantambe
19 Samanalawewa 0.68 Samanalawewa, Uda 330 418 0.025
Walawe
20 Senanayake Samudra 0.69
21 Uda Walawe 0.68 Uda Walawe 10 13 0.001
22 Ulhitiya 0.75
23 Victoria 0.46 Victoria, Randenigala, 301 256 0.015
Rantambe
For use in the LCOE analysis the value of the water savings for irrigation and hydro in USDm pa need
to be combined and converted into the water benefit (Bw) in USD/MWh. The results of this
calculation for each site are shown in Table 45.
Table 45: Water benefit from irrigation and hydro
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
The rank of the sites by LCOE without external benefits for the 9% interest rate base case is shown in
Table 47.
Table 47: Rank of sites by LCOE for Base Case (9% interest rate)
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
55
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
The rank of the sites by LCOE without external benefits for the 4% interest rate sensitivity case is
shown in Table 49. The values are substantially reduced, by an average of 31% compared with the
higher interest rate base case, but the ranking remains the same.
Table 49: Rank of sites by LCOE for Base Case (4% interest rate)
56
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
20 Kantale 70.4
21 Kalawewa 70.7
22 Kotmale
23 Rantambe
57
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
7 Financial Analysis
Financial evaluation of the 21 projects was carried out in nominal terms to assess the financial viability
of each project separately for three financing arrangements:
(i) 70% of the capital cost financed with debt in United States Dollars (USD) and the
remaining 30% financed with equity in Sri Lanka Rupees (SLR) (Financing Arrangement 1),
(ii) 70% of the capital cost financed with debt in SLR and the remaining 30% financed with
equity in SLR (Financing Arrangement 2), and
(iii) 50% of the capital cost financed with debt in SLR, 30% of the capital cost financed with a
grant and the remaining 20% financed with equity in SLR (Financing Arrangement 3).
Cost of equity was estimated as 20.46% using the Capital Asset Pricing Model with beta estimated for
the power sector in the Colombo Stock Exchange (1.09), 8-year treasury bond rate (7.39%15) as the
risk-free rate and 11.98%16 as the equity risk premium.
The Weighted Average Cost of Capital (WACC) estimated for the three financing arrangements are
provided in Table 51.
13
https://fred.stlouisfed.org/series/USD12MD156N
14
AWPLR of March 2021, Central Bank of Sri Lanka,
https://www.cbsl.lk/eResearch/Modules/RD/SearchPages/CMB_LendingAndDeposit.aspx, 1st April 2021
15
8 year treasury bond auction on 16th January 2021, Central Bank of Sri Lanka, www.cbsl.gov.lk
16
Country Default Spreads and Risk Premiums, Aswath Damodaran, January 8, 2021,
http://pages.stern.nyu.edu/~adamodar/New_Home_Page/datafile/ctryprem.html, referred on 15th March
2021
58
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
Considering the high capital cost and low plant factors compared to ground mounted solar PV plants,
the analysis assumed a flat electricity tariff of SLR 15 per kWh throughout the entire operational life
of twenty years17.
Name FIRR
Bowatenna 7.49%
Castlereigh 5.27%
Chandrika Lake 8.12%
Gregory Lake 5.51%
Iranamadu 6.72%
Kalawewa 7.18%
Kalu Ganga 5.93%
Kantale 7.39%
Kaudulla 7.79%
Maduru Oya 7.67%
Minneriya 7.85%
Moragahakanda 6.51%
Moussakele 4.70%
Parakrama Samudra 8.02%
Rajangana 7.62%
Randenigala 5.82%
17
PPAs for renewable energy projects are awarded only for twenty years as the Sri Lanka Sustainable Energy
Authority Act of 2007 does not permits issuance of Energy Permits for periods longer than twenty years.
59
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
Samanalawewa 5.36%
Senanayake Samudra 7.16%
Uda Walawe 7.55%
Ulhitiya/Ratkinda 7.87%
Victoria 5.60%
Comparison of results provided in Table 52 with WACC of the three financing arrangements reveal
that only the floating solar PV systems on Chandrika Lake and the Parakrama Samudra are financially
viable and only in Financing Arrangement 3. None of the projects will be financially viable in Financing
Arrangement 1 and Financing Arrangement 2.
Name FIRR
Bowatenna 16.79%
Castlereigh 14.77%
Chandrika Lake 17.35%
Gregory Lake 15.07%
Iranamadu 15.91%
Kalawewa 16.68%
Kalu Ganga 15.23%
Kantale 16.87%
Kaudulla 17.07%
Maduru Oya 16.97%
Minneriya 17.12%
Moragahakanda 15.73%
Moussakele 14.28%
Parakrama Samudra 17.27%
Rajangana 16.92%
Randenigala 15.00%
Samanalawewa 14.59%
60
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
Comparison of FIRRs with WACC reveal that all 21 projects are financially viable in all three financing
arrangements if the tariff is escalated at local inflation.
Name FIRR
Bowatenna 12.41%
Castlereigh 10.36%
Chandrika Lake 12.99%
Gregory Lake 10.63%
Iranamadu 11.59%
Kalawewa 12.24%
Kalu Ganga 10.88%
Kantale 12.44%
Kaudulla 12.70%
Maduru Oya 12.59%
Minneriya 12.75%
Moragahakanda 11.40%
Moussakele 9.85%
Parakrama Samudra 12.90%
Rajangana 12.54%
Randenigala 10.69%
Samanalawewa 10.27%
Senanayake Samudra 12.08%
Uda Walawe 12.44%
Ulhitiya/Ratkinda 12.77%
Victoria 10.49%
Comparison of results provided in Table 54 with WACC reveal that all 21 projects are financially viable
on in the Financing Arrangement 3. Financing arrangements 1 and 2 will produce mixed results in the
project portfolio.
61
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
estimated the FIRR for each project assuming the electricity generation will increase by 15%. Results
are presented in Table 55.
Table 55: FIRR of Projects is Electricity Generation Increase by 15%
Name FIRR
Bowatenna 10.41%
Castlereigh 8.10%
Chandrika Lake 11.06%
Gregory Lake 8.39%
Iranamadu 9.53%
Kalawewa 10.17%
Kalu Ganga 8.73%
Kantale 10.39%
Kaudulla 10.73%
Maduru Oya 10.61%
Minneriya 10.79%
Moragahakanda 9.32%
Moussakele 7.52%
Parakrama Samudra 10.96%
Rajangana 10.55%
Randenigala 8.55%
Samanalawewa 8.08%
Senanayake Samudra 10.04%
Uda Walawe 10.45%
Ulhitiya/Ratkinda 10.81%
Victoria 8.33%
Comparison of FIRRs with WACC indicate that all floating solar PV projects except for the project on
the Moussakele Reservoir are financially viable in Financing Arrangement 3. The Financing
Arrangement 1 and Financing Arrangement 2 produce mixed results.
7.5.4 Scenario 4: The Tariff is Escalated at Half of Inflation and Electricity Generation
Increases By 15%
The combined effect of Scenarios 2 and 3 were analysed and results are provided in Table 56
Table 56: FIRR of Projects if the Tariff is Escalated at Half of Local Inflation and Electricity Generation Increase by 15%
Name FIRR
Bowatenna 15.15%
Castlereigh 12.94%
Chandrika Lake 15.77%
Gregory Lake 13.25%
Iranamadu 14.21%
62
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
Kalawewa 15.01%
Kalu Ganga 13.47%
Kantale 15.22%
Kaudulla 15.45%
Maduru Oya 15.35%
Minneriya 15.51%
Moragahakanda 14.02%
Moussakele 12.40%
Parakrama Samudra 15.67%
Rajangana 15.29%
Randenigala 13.23%
Samanalawewa 12.78%
Senanayake Samudra 14.77%
Uda Walawe 15.16%
Ulhitiya/Ratkinda 15.53%
Victoria 13.02%
Similar to the Scenario 1, all 21 projects are financially viable in all three financing arrangements if
the tariff is escalated at half the local inflation and electricity generation increases by 15%.
Small renewable energy projects of the order of 1 MW can be developed by Sri Lankan companies
using balance sheet finance. As well as potentially reducing the required return on equity, the cost of
debt is likely to be lower for balance sheet finance than for project finance used for larger projects
such as these FSE projects. This is because the debt is secured against the corporate balance sheet
rather than the future project revenue, hence reducing the risk to the lenders. Hence it would not be
expected that the larger, project-financed FSE will achieve tariffs as low as the 1 MW sized projects.
Participation of multi-lateral or foreign development banks or lending agencies, other than the World
Bank19, in financing renewable energy projects developed by the private sector has been minimal. The
private sector has relied upon local commercial banks for SLR denominated debt mainly to avoid the
foreign exchange risk involved with repayment of foreign currency denominated debt as the tariff is
18
Mini-hydro, wind, ground mounted solar PV and rooftop solar PV
19
Energy Services Delivery Programme and the Renewable Energy for Rural Economic Development
Programme of the World Bank played a vital role in capacity development and financing renewable energy
projects from mid 1990s until about 2010. Credit that was available through the programmes was disbursed
through local commercial banks as SLR denominated loans to project developers.
63
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
denominated in SLR and because the funding requirements are small and are will within the funding
capacities of local commercial banks.
Except for the floating solar PV project on the Kantale Reservoir, all other projects are larger than
10 MW and most of them are larger than 60 MW requiring investments in excess of USD 50 million.
At a debt-to-equity ratio of 70:30, the debt requirement will be higher than USD 35 million. Local
commercial banks had been hesitant to finance wind power projects and ground mounted solar PV
projects at the early stages of development mostly due to banks not being familiar with the technology
and risks involved. Local commercial banks may react similarly to floating solar PV projects as well.
Hence, development of floating solar PV projects would require participation of international funding
agencies as lenders and guarantee providers.
While the aim of the MCA is to rank the projects against the set of criteria, the results cannot be
used without further review. For example, a site that has high scores against most criteria but a very
low score against one criterion may present greater developmental risk than a lower scoring site
that has average scores against all criteria.
8.1 Methodology
The methodology for the MCA is presented in Figure 5, and summarised below.
64
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
8.1.1 Criteria
For this study seven criteria have been selected as follows:
• Power
• Solar Resource
• Technical Complexity
• System Integration
• Environment
• Social
• Economics
The criteria have been selected to be reasonably independent and to cover the range of attributes
that will determine the preference between sites. The criteria are not fully independent, since the
solar resource and complexity have impacts on energy production and cost, which feed into the
economic analysis. This is taken into account in the weighting of the criteria, with reduced weighting
for criteria that overlap.
The scores allocated are integer values out of 5, with 5 being the most preferred and 0 the least
preferred. For some criteria a low value is better (for example LCOE), and these criteria are
considered to be ascending. For other criteria a high value is preferred (for example Global Tilted
Irradiation), and these are considered to be descending.
65
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
Thresholds are defined for the transition values between scores – for example the 3-4 threshold for
installed capacity is 70 MWp, and the 4-5 threshold is 90 MWp. Hence sites with installed capacity
between 70 and 90 MWp score 4, and above 90 MWp score 5.
When scores are aggregated the totals exceed 5, and hence they are normalised such that the
maximum value that can be attained is 5.
8.2.1 Power
The parameter used for the Power criterion is the installed capacity in MWp. In order to make a
meaningful contribution to the renewable energy needs of the Sri Lankan power system and to
attract international finance, grid-scale installations are required. A target installed capacity of
100 MWp has been adopted for this study. Hence sites with installed capacity above 90 MWp are
awarded maximum scores (5), and below 5 MWp score zero. The MCA parameters for the Power
criteria are shown in Table 57
Criterion Power
Parameter Installed capacity
Unit MWp
Ascending or descending D
Weight 0.7
Threshold 0-1 5
Threshold 1-2 20
Threshold 2-3 50
Threshold 3-4 70
Threshold 4-5 90
The MCA parameters for Solar Resource are shown in Table 58.
Table 58: Solar Resource criterion MCA parameters
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
The MCA parameters for the Technical Complexity criterion are shown in Table 59.
Table 59: Technical complexity criterion MCA parameters
Criterion Complexity
Parameter Reservoir operating range
Unit m
Ascending or descending A
Weight 0.7
Threshold 0-1 45
Threshold 1-2 35
Threshold 2-3 25
Threshold 3-4 15
Threshold 4-5 10
The assessment for enhanced grid integration is shown in Table 10, and the marks assigned are as
follows:
Conjunctive with Hydro 2 marks for ability to operate conjunctively with a co-located
hydro plant.
Conjunctive d/s Hydro 1 mark for ability to operate conjunctively with downstream
hydro plant (alternative to full marks above)
Strong link to 220 kV 1 mark for direct connection to 220 kV grid, or to a substation
with direct connection to the 220 kV grid.
67
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
All of the FSE schemes have been designed to integrate well with the grid by connection to a grid
substation which should have adequate export capacity. Hence a basic mark of 2 is awarded to all
schemes, and the enhanced integration marks are added to this score, giving a maximum score of 5.
The MCA parameters for the System Integration criterion are shown in Table 60.
Table 60: System integration criterion MCA parameters
Ecology
Hydrology and Water Quality
Pollution and Contamination
Protected Areas
Construction Impacts
The marking of the environmental characteristics is presented in section Error! Reference source not f
ound., and the parameters for the environmental impact criterion are shown in Table 61.
Table 61: Environmental impact criterion MCA parameters
Criterion Environment
Parameter Environmental Impact
Unit 0
Ascending or descending D
Weight 1
Threshold 0-1 0.5
Threshold 1-2 1.5
Threshold 2-3 2.5
Threshold 3-4 3.5
68
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
The five social impact characteristics that have been marked are:
Resettlement
Economic Activities
Cultural Property
Health and Safety
Leisure and Tourism
The marking of the social impact characteristics is presented in section 4.3.6Error! Reference source n
ot found., and the parameters for the environmental impact criterion are shown in Table 62.
Table 62: Social impact criterion MCA parameters
Criterion Social
Parameter Social Impact
Unit 0
Ascending or descending D
Weight 1
Threshold 0-1 0.5
Threshold 1-2 1.5
Threshold 2-3 2.5
Threshold 3-4 3.5
Threshold 4-5 4.5
8.2.7 Economics
The economic performance of the schemes is assessed in terms of the Levelized Cost of Energy
(LCOE). For the purposes of the MCA, the base case with 9% interest rate and no externalities taken
into account is used.
In order to compare the relative performance of the schemes, the thresholds for marking used
bands based on the standard deviation from the mean, derived from statistical analysis of the LCOE
data. The thresholds selected are:
• Mean – 1 SD
• Mean – 0.5 SD
• Mean + 0.5 SD
69
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
• Mean + 1 SD
• Mean + 3 SD
Criterion Economics
Parameter Levelized Cost of Energy (base
case)
Unit USD/MWh
Ascending or descending A
Weight 1
Threshold 0-1 107.3
Threshold 1-2 89.1
Threshold 2-3 84.6
Threshold 3-4 75.5
Threshold 4-5 71.0
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
71
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
The unweighted scores in Table 65 are factored by the weightings in Table 66, to produce the
weighted scores shown in Table 67.
Table 67: Weighted MCA scores for each criterion
72
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
In Table 69 the normalised scores from Table 68 are presented by rank, with the highest score (most
preferred) ranked number 1.
Table 69: Ranked Unweighted Normalised MCA Scores
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
74
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
In Table 71 the normalised scores from Table 70Table 68 are presented by rank, with the highest
score (most preferred) ranked number 1. This table represents the final outcome of the multi-
criteria analysis, and provides the basis for selection of sites to take forward to the next stage of
study.
Table 71: Weighted MCA scores by rank
1 Ulhitiya
2 Kaudulla
3 Castlereigh
4 Maduru Oya
5 Parakrama Samudra
6 Rajangana
75
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
MCA Scores
Power
5
4
Economics 3 Solar Resource
2
1
0
Social Complexity
Environment System…
76
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
MCA Scores
Power
5
4
Economics 3 Solar Resource
2
1
0
Social Complexity
Environment System…
MCA Scores
Power
5
4
Economics 3 Solar Resource
2
1
0
Social Complexity
Environment System…
77
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
MCA Scores
Power
5
4
Economics 3 Solar Resource
2
1
0
Social Complexity
Environment System…
MCA Scores
Power
5
4
Economics 3 Solar Resource
2
1
0
Social Complexity
Environment System…
78
McWILLIAMS energy
Floating Solar Energy Review
Phase B Study: Multi-criteria Analysis
Final Rev0 June 2021
MCA Scores
Power
5
4
Economics 3 Solar Resource
2
1
0
Social Complexity
System
Environment
Integration
On the basis of the results of the MCA and this assessment, it is recommended that the four top-
ranked sites are taken forward to the pre-feasibility stage.
1. Ulhitiya
2. Kaudulla
3. Castlereigh
4. Maduru Oya
These sites are considered likely to produce economic and sustainable FSE projects with low
technical, environmental and social risks. The remaining two sites of the top six may be kept in
reserve in case unforeseen impediments to development of the top four are encountered.
The Pre-feasibility studies will confirm the technical viability of the FSE projects, evaluate the cost
and economics and provide more detailed assessments of the environmental and social impacts,
regulatory regime and development options.
79
McWILLIAMS energy