You are on page 1of 21

The current issue and full text archive of this journal is available at

www.emeraldinsight.com/1463-5771.htm

BIJ
17,2 Analyzing the dynamics of the
global construction industry:
past, present and future
232
Abdul Razak Bin Ibrahim
University of Malaya, Kuala Lumpur, Malaysia
Matthew H. Roy
University of Massachusetts Dartmouth, Dartmouth, Massachusetts, USA
Zafar U. Ahmed
Fahad Bin Sultan University, Tabuk, Saudi Arabia, and
Ghaffar Imtiaz
University of Malaya, Kuala Lumpur, Malaysia

Abstract
Purpose – The purpose of this paper is to analyze the production processes utilized by the global
construction industry.
Design/methodology/approach – This paper discusses the history of the construction industry
with a specific focus on the evolution of lean production systems (LPSs) that has a significant impact in
reduction of waste in the light of operational performance. The paper proceeds through a comparison of
the differences between construction and manufacturing processes.
Findings – The construction industry consumes large amounts of natural resources along with
wastage due to inefficient and improper utilization. Numerous factors contribute to this poor
performance, but an efficient means of identification and reduction of waste has always been left aside.
A fully integrated LPS is a way to eliminate much waste in the construction process.
Originality/value – This paper has developed an instrument to measure degree of integration of LPS
principles in the construction industry that can be used globally. It can be used as a checklist for what
to aim at when trying to implement LPS in construction.
Keywords Lean production, Construction industry, Waste
Paper type Research paper

Introduction
The term construction is generally used to describe the activity of the creation of
physical infrastructure, superstructure and related facilities (Wells, 1985). Construction
is also referred to as all types of activities associated with the erection and repair of
immobile structures and facilities (Nam and Tatum, 1988).
The construction industry plays a major and vital role in transforming the
aspirations and needs of people into reality by physically implementing various
Benchmarking: An International construction development projects. Construction projects usually cover infrastructure,
Journal such as roads, dams and irrigation work. Schools, houses, hospitals, airports, railways,
Vol. 17 No. 2, 2010
pp. 232-252 factories and other construction work are some of the examples of the physical
q Emerald Group Publishing Limited foundations as some form of development efforts to improve living standards. Thus,
1463-5771
DOI 10.1108/14635771011036320 the construction industry is undeniably essential to the growth of a nation and a key
sector in the nation’s economy. A country cannot grow if there is no development and Global
infrastructure build to spur the economy. The construction industry is an important construction
factor in the process of development. Its contributions are more than just economic; the
products of construction mentioned above contribute extensively towards the creation industry
of wealth and the quality of life of the population.
Traditional ways of performing and managing construction processes face
unprecedented challenges. The growing competition forces construction organizations 233
to rethink their construction for improving productivity, quality and efficiency (Kärnä
and Jonnonen, 2005). The construction industry may also benefit from best practices in
other industries – for example electricity (Chau, 2009), breweries (Goncharuk, 2009),
healthcare (Duggirala et al., 2008) or new processes – for example quality function
deployment (Miguel and Carnevalli, 2008).
The construction industry as defined by the US Census Bureau (2002) comprises
companies primarily engaged in the construction of buildings and other structures,
heavy construction, additions, alterations, reconstruction, installation, and maintenance
and repairs. Companies engaged in the demolition or wrecking of buildings and other
structures, clearing of building sites and sale of materials from demolished structures
are also included. This industry also includes those establishments engaged in blasting,
test drilling, landfill, levelling, earthmoving, excavating, land drainage and other land
preparation. The industries within this sector have been defined on the basis of their
unique production processes such as earthworks and piling, sub structure and super
structure, mechanical and electrical, etc. As with all industries, the production processes
are distinguished by their use of specialised human resources and specialised physical
capital. Construction activities are generally administered or managed at a relatively
fixed place of business, but the actual construction work is performed at one or more
different project sites (US census Bureau, 1997). The department of Statistics Malaysia
has defined the construction sector as new construction, alteration, repair and
demolition. Installation of any machinery or equipment which is built-in at the time of
the original construction is included, as well as installation of machinery or equipment
after the original construction but which requires structural alteration in order to install
(Department of Statistics Malaysia, 1995).
The construction sector mainly has two classes of end product, first, buildings
associated with offices, hospitals, airports, shopping centres, housing, factories, etc.;
second, the civil works that involve the infrastructure for water supply, irrigation,
transportation, power generation and so forth (Chris, 1998; Gould and Joyce, 2008).

Literature review
The concept of using fewer resources, especially shortening the total time of production
was first highlighted in 1921 ( Journal of Mechanical Engineering, 1921; Clark, 1922;
Miller, 1922). The following two quotes from Ford (1926, p. 826) also show that time
was understood as one of the production inputs in that period:
The time element in manufacturing stretches from the moment the raw material is separated
from the earth to the moment when the finished product is delivered to the ultimate consumer.
Time waste differs from material waste in that there can be no salvage. The easiest of all
waste, and the hardest to correct, is this waste of time, because wasted time does not litter the
floor like wasted material.
BIJ Another similar study by Gilbreth and Gilbreth (1922) found that time is consumed
17,2 in production by two types of activities. These are transformation and
non-transformation activities. The non-transformation activities are transfers, delays
and inspection activities. These two notes in the history reveal that engineers were
looking to eliminate unnecessary steps from production and make effective use of
resources. This elimination of unnecessary elements from production, compounded
234 with the lack of resources (Fawcett, 1989) after the Second World War in Japan, resulted
in the invention of the Toyota Production System, developed by Toyota Motors
and later known as lean production system (LPS) (Schuster, 1993; Wu, 2003). Under the
tutelage of Ohno, an engineer at Toyota Motors is considered the inventor of the Toyota
Production System, which is arguably the pre-eminent manufacturing organization in
the world (Balakrishnan et al., 1996; Becker, 2003; McMohan and Browne, 1998;
Womack et al., 1990; Ohno, 1988). However, the term LPS was coined around 1989 with
the popularity of the book The Machine that Change the World written by researchers
at the Massachusetts Institute of Technology (Boyer, 1996; Krafcik, 1988). The term
itself is used to describe the collection of efficiency improvement.

What is LPS?
The LPS is defined as the reduction of non-value added activities called waste, thereby
reducing time from customer order to the collection of cash (Ohno, 1988). Spear and
Brown (1999, p. 97) have defined it as:
A systematic approach to identifying and eliminating waste (non value added activities)
through continuous improvement by flowing the product at the pull of the customer in
pursuit of perfection.
MIT (2000) defined the LPS as the elimination of waste in every area of production
including customers’ relations, product design, suppliers’ networks and factory
management. Cox and Blackstone (1988) have defined the LPS as a technique that
emphasizes the minimization of the amount of all the resources (including time) used in
the various activities.
The LPS offers the potential for nothing less than revolutionary improvements in
performance and cost. LPS is a technique that reduces the waste inherent in any
business process, and at the same time exceeds performance (Sohal, 1996). LPS is able
to produce more products with higher quality but with fewer resources, and global
competition is associated with the practice of LPS (Santos, 1999). Agbulos and Simaan
(2003) have looked at the LPS as the avoidance, elimination or reduction of waste.
Waste is recognised by LPS as a performance criterion. That is, failure to meet the
unique requirements of a client. In other words, time, space, or material used in
performance of an activity that does not directly contribute value to the finished
product. Waste as a non-value added element is classified as being handling,
transportation, delay, inspection, storage and rework.
The careful review of the literature has shown that LPS brings benefits in business.
The LPS is successful because its main objective is to eliminate waste from all business
processes by using continuous improvement brought by the employees (Emiliani,
2000; Hopp and Spearman, 2001). It has been applied in manufacturing, automotive,
aviation, industrial equipment, furniture, fixtures, consumer goods, ceramics, software
and healthcare (Womack and Jones, 1996; Imtiaz and Ibrahim, 2006; Moore and
Gibbons, 1997) and results showed significant improvements in the operational
performance such as cost, quality, on-time delivery, inventory level and value added Global
per employee (Berry et al., 2003). The interest in LPS is mostly based on the theory as construction
well as empirical evidence that its introduction in a shop, factory or company increases
productivity, reduces lead times and cost, and improves quality (Karlsson and industry
Ahlstrom, 1995; Sriparavastu and Gupta, 1997). The LPS is simply without equal and
can be applied equally in any industry around the globe (Womack et al., 1990).
More recently LPS has been studied in the construction industry, and the seminal 235
author is Lauri Koskela (Koskela, 1992). Later Egan (1998) in Rethinking Construction
Report has advised the UK construction industry to use LPS in the construction
industry. Similarly, Singapore in its Construction 21 (C21) Report (1999) has also
emphasized that the construction industry should use LPS. The other countries such as
the USA, European Union and Australian construction industries are implementing
LPS in construction (Dulaimi and Tanamas, 1999). This study advocates applying the
LPS in the Malaysian construction industry to explore its integration in construction
industry, and its impact on the operational performance in the construction industry.

Research objectives and methodology


This research is applying the principles of LPS from the manufacturing sector into the
construction industry with the aim that LPS is able to enhance operational
performance in construction.
This research has the following objectives:
.
To evaluate the use of LPS principles in construction industry.
. To study the influence of LPS principle on operational performance.

The researchers have used the most popular survey method used to understand the
characteristics of a population. As Roberts (1999) pointed out, the survey method is one of
the most common approaches used in the social sciences to empirically study the
characteristics and interrelationship of sociological and psychological variables, and its
methods and analysis have profoundly influenced the social sciences (Kerlinger, 1986).

Construction industry in the years bygone


Construction is one of the oldest laboratories of the management sciences, particularly in
the field of production management. In 400 BC, Cairo in Persia carried out studies on the
use of movement, layout and transport of materials in construction sites. Moreover, it
was in the construction industry that Gilberth carried out his famous motion studies that
laid down some of the principal foundations of scientific management (Cheetham et al.,
1992; Gilberth, 1911). Construction is a type of production (Heizer and Render, 2005;
Koskela, 2000). Bertelsen and Koskela (2004) have defined construction as a complex
production of a one kind product undertaken mainly at the delivery point by cooperation
within multi-skilled ad hoc teams. This definition of construction indicates at least
four characteristics. Construction is production and it produces a one-of-a-kind product,
it is complex and undertaken through cooperation by a temporary organization.

Current status of the global construction industry


Current theory in the construction industry
Construction is a very old industry. Its culture and many of its methods have their roots
in the periods before explicit scientific analysis. However, especially after the Second
BIJ World War, there have been several different initiatives to understand construction and
17,2 its problems, and to develop corresponding solutions and improvement in methods
such as industrialisation, computer integrated construction, and total quality
management (TQM) (Koskela, 1992). The other operational and tactical techniques
are project planning and control tools, organizational methods, project success factors,
and productivity improvement methods (Koskela, 1992). By far the most general
236 concept seems to be the understanding of construction as a set of activities aimed at a
certain output, i.e. conversion. This activity view of construction is shared both by the
old traditions of construction and the newer methods.
The traditional method of cost estimation is at the heart of this activity view. The
building (or other structure) is divided into its constituent elements, and for each
element, the costs of needed materials and labour (conversion of input to output) is
estimated. This is exactly according to the conversion model. The great influence of
design on construction and operating costs was first pointed out and analyzed in
Paulson (1976). Friedrich et al. (1987) strongly criticized the customary notion that
large projects can be measured by using yardsticks viewed as simple summations
of individual yardsticks taken by discipline, system-by-system, or component-
by-component. Thus, the overall effects of revisions, repairs and rework on large
projects can be very significant, even when the individual effects of specific functions
and disciplines appear small and within normal acceptable practices. A recent study
shows that outsourcing inputs can have negative consequences on organizational
capabilities (Agndal and Nordin, 2009).
Beyond this conversion model, what theories or frameworks have been used in
construction? As odd as it might seem, there are hardly any other theoretical or
conceptual frameworks in general use. Even a rapid glance at the contents of textbooks
on construction management shows that they usually begin with a descriptive account
of a construction project (Barrie and Paulson, 1992; Clough and Sears, 1994) and then
proceed to specific techniques of management and control. No major conceptual or
theoretical analysis of construction is provided at the outset.
Thus, the construction industry is currently practising the conversion or
transformation model of production in the construction jobs. Dominant in the
nineteenth and twentieth centuries this model posses that production is conceptualised
as a transformation of inputs to outputs. That is, a production process receives inputs,
transforms them and exports the outputs to the environment, or into the next process
(Koskela, 1992; Schroeder, 1993; Vonderembse, 1996; Weihrish and Koontz, 1993).
Furthermore, the inputs, conversions or outputs may be integrated with control elements
that monitor and correct system behaviour (Lee and Schniederjans, 1994) (Figure 1).

Features of current practices in construction


Construction is a contract centred activity, with transactional contracts or assignments
defining and balancing the objectives of various participants. Coordination between
organizations or crew is primarily controlled from a central plan that establishes

Input
Figure 1. Output
(Material, Labour, Conversion
Concept of conversion (Products)
Machine etc.)
model
Source: Koskela (1992)
sequence and determines when an activity will start. Costs, errors, and learning occur Global
within activities. Cost reduction results from improving productivity, and project construction
duration is shortened by accelerating activities, or by changing logic to allow
concurrent work. Waste is a cost that can be avoided within the activities, such as industry
rework, or cost due to extended activity duration along the critical paths. As per
Howell and Ballard (1998), the features of current practices in the construction are:
.
Designs as per client(s) requirements, align design to quality, schedule and 237
budget limits.
. Manage by breaking into pieces, estimate duration and resource requirement and
then put logically into critical path method and project evaluation review
technique.
.
Contract for each piece, start notice, monitors. Coordinate project by using
master schedule and daily, weekly and biweekly meetings.
.
Reduce cost by increasing productivity. Improve quality and safety by better and
enforced inspection.
.
Activity centred – Batch and Queue that trades efficiency for apparent security.
.
Inflexible to changes.
.
Control begins with tracking cost and schedule.
.
Improving local productivity/speed leads to unreliable workflow further
reducing project performance.

Deficiencies in the current construction practices


The deficiencies in the current construction practices are: waste activities such as
waiting, storing, inventory, moving materials are generally not modelled, 50 per cent of
activities realised as planned (Ballard and Howell, 1998) and the conversion model
have proven inadequate (Koskela, 1992). In project control, fire fighting ongoing or
looming crises consumes management resources and attention so totally, that there is a
little room for planning, let alone improvement activities:
Managers are too occupied with the complexities involved in getting the work done to think
about, much less to carry out, organized programs for productivity improvement (Oglesby
et al., 1989).
In fact the whole construction culture is characterised by this short-term, action
oriented behaviour: “fire fighters get the laurels” (Ballard, 1989). Developments in
construction technology and market demand and the increasing variety of materials
and components, and requirements for shorter project duration, tend further to
aggravate the inherent problems in construction processes (Koskela, 1992).

Construction vs manufacturing
The construction industry is more complex and uncertain (Antonio, 2002; Gidado,
1996; Howell and Laufer, 1993; Kim and Wilemon, 2003; Wild, 2002; Williams, 1999)
than manufacturing. The construction industry is distinguished by the physical nature
of its production process and in general the large portion of works carried out on site
where the product will be used in post occupancy life of project (Ball, 1988). The end
product of construction is generally fixed, large and the resources are moving in and
BIJ out to products, unlike other sectors where products are moving in and out to the
17,2 resources (Schmenner, 1993) and the workstations have to move through the emerging
wholes, adding pieces as they move (Ballard and Howell, 1998). The construction
client(s) and customers normally have little or no experience in buying a house or other
product from construction and it is a make to order industry, where the majority of
projects are one-off and tailored-made to a particular client’s requirement (Fellows et al.,
238 1983). The client(s) wants durable construction because the investment in this sector is
more than other industries (Gann, 1996).
A comparison with manufacturing shows the key features, which distinguishes
construction from manufacturing, is the uncertainty evident throughout the
construction process (Howell and Ballard, 1995) (Table I).
The authors have carried out a similar comparison by compiling other authors work
shown in Table II. The combination of the various characteristics of construction
confers a peculiar mode of production to it (Ball, 1988; Ballard and Howell, 1998;
Towill, 1997). When this peculiar mode of production is placed in dynamic construction
projects, characterised for quickness, uncertainty and complexity, construction shows
constant reminders that it cannot be transformed into manufacturing.

Global construction industry’s environmental uncertainties


An overview of construction environmental uncertainties is presented in Table III. One
of the first to discuss the environmental uncertainties of construction might have been
Groak (1992). He took the view that advances in construction are often related to the
elimination of uncertainty. Nam and Tatum (1988) came to a similar conclusion in their
analysis of the impact of uncertainties in construction innovation. Warszawski (1990)
compares construction with manufacturing, and argues that, for the sake of efficiency,
industrialised construction should be set as a target. Carassus (1998) takes the view
that fundamental specificity, namely that constructed products are located on a site,
structure most of the other specific characteristics, as presented by him. Even if it is

Start of manufacturing production Start of construction in the field

What Highly defined Evolving as means refines ends


How Highly defined. Operational plan is in Partly defined but details unexamined.
great detail based many trials. Primary Extensive planning remains as situation
sequence of major tasks is inflexible, evolves. Primary sequence only partly
interdependencies are documented and determined by hard logic but many
analyzed. Positions in process determine change. Interdependencies due to
required skills conflicting measurements, shared
resources, and intermediate products
only partly understood. General craft
skills to be applied in a variety of
positions
Assembly Produce one of a finite set of objects Make the only one. The details of what
objective where the details of what and how are and how are not completely known at
known at the beginning of assembly the beginning of assembly
Table I. Improvement Rapid learning during the first units Rapid learning during both planning
Context of manufacturing strategy preparing for production runs and early sub-assembly cycles
and construction
uncertainty Source: Howell and Ballard (1995)
Global
Area Operations management Construction management
construction
Human Job design, payment and incentives, Health and safety, legislation, costs, industry
resource workers motivation safety policies, recruitment and selection,
education and training, communication
Quality TQM, International Standard Economics of quality, quality assurance,
Organisation (ISO) 9000, total quality quality control, ISO 239
control, etc.
Purchasing Logistics; specifications and quo Definition of documents, purchasing and
contracting, control of procurement,
budgeting, estimating
Material/ Management methods, just-in-time, Operations research methods, costs
inventory activity-based-costing system, Kanban, models, linear regression, linear
LPS, material requirement planning I, programming, queuing
material resource planning II, computer-
aided design/computer-aided
manufacturing/computer-aided
engineering/computer integrated Table II.
engineering Comparison of practices
in operations and
Sources: Barrie and Paulson (1992); Fellows et al. (1983); Lee and Schniederjans (1994); Santos (1999); construction
Schroeder (1993); Wild (1995) management

easy to find treatments of construction environmental uncertainties, there is little


accumulation in understanding in this respect. This is illustrated by the fact that
there is no cross-referencing among the sources discussed here. Moreover, related
knowledge is qualitative; there have been few, if any attempts to acquire quantitative
data on the occurrence or impact of these environmental uncertainties.
However, with similar characteristics and environmental uncertainties to
construction, other industries have managed to overtake them and reach excellent
levels of performance as shown in Table IV.

Challenges of the global construction industry


The problems in the construction industry in the form of waste, design, planning,
material control, production control and labour control were first reported by Journal
Mechanical Engineering (1921). There have been several attempts to measure and
improve construction productivity (Siegel, 1980). Walker (1996) also quoted that there
has been a stream of official investigations of various facets of construction. The other
reports on construction problems and their improvement are Emmerson (1962), Banwell
(1964), Tavistock Institute (1965) report, Latham (1994) report and finally rethinking
construction by Egan (1998). The problems and the improvement in the construction
industry were never ignored. Even then the estimates indicated that up to 30 per cent of
construction costs are due to inefficiencies, mistakes, delays and poor communication
(Atkins, 1993; Eaton, 1994; Forbes et al., 2002; Koskela, 2000; Tucker, 1986). The
problems concerning areas in the construction industry are briefly explained below.

Productivity
The prosperity of a nation is recognised as being dependent upon its productivity
levels in comparison to other countries (Hill, 1992). In this context, construction
BIJ Source Peculiarities
17,2
Nam and Tatum (1988) Immobility
Complexity
Durability
High level of social responsibility
Costliness
240 Warszawski (1990) Rugged and harsh work environment
High turnover of workers
Long service life of atypical project
Work dispersed among many temporary locations
Small extent of standardisation
Large number of tasks requiring a high degree of manual skills
necessary to complete a typical construction product
Authority divided between sponsor, designers, local government,
contractor and subcontractor
Groak (1992) Fixity
Uniqueness
Weight
Often sold before built
Bulk or volume
Complexity and temporary organization
Long construction time
High initial and running cost
Longevity in use
Carassus (1998) Artistic creation
Construction of mock up
Located on site
Localised orders of extraordinary diversity
Rules and conventions playing a considerable role
Complex and random work
Hancock (2000) Conflict
Fragmentation
Labour mobility
Subcontracting
Table III. Crisis management
Construction Masculine
environmental Dubois and Gadde (2002) Fragmented
uncertainties Fluid

productivity is one of the economic indicators of success, since this sector has a
substantial impact on gross domestic product (GDP) and employment. Despite its
greater importance, the construction industry regularly demonstrates lower levels of
productivity when compared with the manufacturing industry. Construction
performance affects productivity across all sectors of the economy (Hampson, 1997).
It has been estimated that a 10 per cent increase in construction industry productivity
would result in a 2.5 per cent improvement in GDP (Stoeckel and Quirke, 1992).

Waste
Waste is defined as any activity that adds no value to the product but consumes
resources (Alarcon, 1994; Koskela, 1992; Love et al., 1997). Waste in the construction
industry has been the subject of several research projects around the world in recent
Global
Construction Other sectors
construction
One of a kind product Shipbuilders industry
On site production Car repair (e.g. AA patrol)
Fixed position manufacturing Aeroplane (e.g. Boeing)
Land dependence High street retailers (e.g. Benetton)
Long life expectancy required Elevators manufacturer (e.g. Otis, Kone) 241
Non experienced clients Ambulance (e.g. 999 services)
Merchant/producer role of companies Car factories (ex. Toyota, Nissan)
Overwhelmingly domestic industry Fast food (e.g. McDonald’s)
Temporary organization Sports events (e.g. World Cup-FIFA)
Masculine Mining
Long period for design production Car factories (e.g. Toyota, Nissan)
High cost of the project Chemical industries.
Amplified reaction in economic crisis Entertainment (e.g. Disney production)
Labour intensive Fast Food (e.g. McDonald’s). Table IV.
Fragmented industry Clothe producers (e.g. Levi Strauss) Excellent companies with
similar construction
Source: Santos (1999) characteristics

years (Formoso et al., 1999). The studies not only focussed on the surplus material
quantity (CII, 1986) and the unnecessary material waste (Illingworth and Thain, 1988)
on-site but also related to several activities such as over production, waiting time,
material handling, processing, inventories and movement of workers (Alarcon, 1994;
Formoso et al., 1999). The other main categories of waste during construction processes
are poor quality (rework/repairs/defects), lack of construct-ability, material waste,
delays, waiting, poor material allocation, unnecessary material handling and material
waste (Alarcon, 1995; Alwi, 1995; Koskela, 1993; Lee et al., 1999; Robinson, 1991). As
mentioned above, these categories of waste attributed up to 30 per cent of construction
costs.
The unproductive time waste in construction sites was 24 per cent on average in
Australia, Sweden and The Netherlands (Vershuren, 1980), 43 per cent in Nigeria
(Olomolaiye et al., 1987) and 26 per cent in Brazil (Bicca et al., 1994).
Bossink and Brouwers (1996) found that 9 per cent of total purchased materials end
up as waste and from 1 to 10 per cent of every single purchased construction material
leaves the site as solid waste in the Dutch construction industry. Since materials
account for 50-60 per cent of a construction project cost, any improvement in avoiding
material waste results in major cost savings (Akintoye, 1995; Ibn-Homaid, 2002; Wong
and Norman, 1997). Similar magnitudes of wastage in materials and time are reported
in the Turkish construction industry (Polat and Ballard, 2004). In the UK, Skoyles and
Skoyles (1976, 1987) found wastage of materials ranging from 5 to 10 per cent in
volume. Sjostorm (1998) has said that the construction industry is estimated to
generate approximately 40 per cent of man-made waste. Bell and Stukhart (1987)
reported 10-12 per cent extra in labour costs because of poor material management
systems. Wyatt (1978) stressed the consequences of high levels of waste in both
reducing the future availability of material and energy, and creating unnecessary
demands on the transportation system. The Hong Kong Polytechnic (1993) conducted a
research on construction waste aimed at reducing the generation of waste at source and
proposed alternative methods for the treatment of construction waste in order to reduce
BIJ the demand for final disposal areas. Koskela (1992) also confirmed waste in the
17,2 construction sector as shown in Table V.
Chilean building construction projects experience waste variables such as waiting
time, idle time and travelling time (Serpell et al., 1995). Kaming et al. (1997) identified
lack of material, rework/repair, lack of equipment and supervision delays as factors
influencing productivity in the construction industry. An investigation by Mohamed
242 and Tucker (1996) showed that 25 per cent timesaving is achievable in a typical
construction work package without increasing allocated resources.
Beside this wastage in construction, there are quality failures that have been
estimated to the cost the industry between 2 and 12 per cent of construction turnover in
rework alone (Burati et al., 1992; Ledbetter, 1994; Love, 2002). Marosszeky et al. (2002)
also found about 2-4 per cent of direct and indirect cost defects in four Sydney
construction sites. Waste in the construction industry supply chain is omnipresent
(Luhtala et al., 1994; Vrikjhoef and Koskela, 2000). Poor quality is attributed to be 10-20
per cent of total project cost (Cnudde, 1991). In the USA, the deviation cost averaged
12.4 per cent of the total installed project cost (Burati et al., 1992). In Sweden a study on
design-construct project, the costs of quality failures were found to be 5.4 per cent of
the production costs (Hammarlund and Josephson, 1991; Josephson, 1994). In Norway,
Sjoholt (1998) estimated that the cost due to nonconformity, errors, alterations and
wastage, in the course of building process, were around 10 per cent of the total building
cost.

Image
The construction industry has one of the worst public images among the industrial
sectors. It is considered dirty, dangerous, dull and environmentally insensitive (Ball,
1988; Pheng, 2005; Santos et al., 2000; Santos and Powell, 2001). Joyce (1995) has stated
that the construction industry has the dubious distinction of having the highest
incident rate of fatal accidents and serious injuries of all industries. Furthermore,
construction projects are widely seen as unpredictable in terms of delivery time,
profitability and quality standards. The investments in construction are usually seen
as expensive when compared to other industries (Egan, 1998). The under achievements
of construction are reflected in the growing dissatisfaction that is found both its private
and public sector clients. Building costs too much, takes too long and does not serve
our needs into the future (Howell, 1999).

Waste Cost Country

Quality cost (non-conformance) 12 per cent of total project cost USA


External quality cost (during facility use) 4 per cent of total project cost Sweden
Lack of construct-ability 6-10 per cent of total project cost USA
Poor material management 10-12 per cent of labour costs USA
Excess consumption of materials on site 10 per cent on an average Sweden
Working time used for non-value added activities App. two out of three of total time USA
on site
Table V. Lack of safety 6 per cent of total project costs USA
Waste in the construction
industry Source: Koskela (1992)
Cost and time target failure Global
A British study on commercial building projects in 1984-1986 (NEDO, 1988) found that construction
about one third of projects were completed in time, another one third overran by up to
one month and rest had overruns in excess of one month. Another study in Australia industry
on building projects completed in 1988-1993 found that 14 per cent of projects had a
cost overrun, and 67 per cent a time overrun (CIDA, 1993). Furthermore, it was found
that 73 per cent of projects had variations in scope, representing 9 per cent of the total 243
value of project studies, 2 per cent of projects had variations in scope of greater than
10 per cent and all of these projects had time overruns. A recent study in America
(Konchar et al., 1997) showed that 38-51 per cent of 304 projects considered, depending
on the project delivery type, ended up more than 5 per cent above budget.
A corresponding study in the UK (Bennett et al., 1996) found that 21-32 per cent
projects ended up above budget by more than 5 per cent.
A few real life examples encompassing construction industry problems discussed in
the above paragraphs are appended below.
In Indonesia. Delay to schedule or non-completion of construction job in time is very
significant besides other wastage (Alwi et al., 2002).
In Singapore. The Construction Industry Steering Committee in 1999 have reviewed
state of the industry under C21 challenges and criticized its performance. Wilfred
(1992) in an empirical study in Singapore and Hong Kong found that their construction
industries are facing problems such as exceeding budget, inferior quality and delays in
construction.
In Saudi Arabia. Al-Khalil and Al-Ghafly (1999) stated that delays in construction
job completion are a major problem leading to costly disputes and acrimonious
relationship between parties involve.
In Nigeria. Construction project delays are identified as the principle factors leading
to the high cost of construction (Okpala and Aniekwu, 1988).
In the UK. A new hospital, Cumberland Infirmary building in Carlisle, in 2000. The
hospital has 442 beds and cost UK £87 million. This hospital has received notorious
publicity through sewage spills from sinks in the operating theatres, collapsing
ceilings, walls so thin that shelves could not be installed and flooding of the cardiology
and maternity wards, etc. resulted in massive reworking (Browne, 2001).
In Australia. The budget for the Sydney opera house escalated from AUS $7 million
to AUS $107 million and the construction time from four years to more than 14 years
(Kharbanda and Pinto, 1996). Furthermore, the Royal Commissions (Cole, 2002; Gyles,
1992) found that Australian construction industry substantially under-performs its
potential.
In the USA. The Denver international airport project was planned from 1989 to 1993
with a cost of US $1.7 billion, but its opening was delayed four times and total delay
was 16 months and cost increased to US $4.5 billion (Drexl and Hans, 2002). An
industrial plant costing US $100 million on a fast track construction job was delayed
substantially (Fazio et al., 1988). In a nuclear power plant there was substantial minor
and major reworking cycle or time, reflecting that the quality of work was not in order
(Friedrich et al., 1987).
In Denmark. An office building exceeded the working hours estimated more than
three times (Bertelsen, 2003).
BIJ It is apparent from the above discussion and examples that the construction
17,2 industry is facing problems globally. All these factors make production management
in construction an important and valuable area for research (Koskela, 1993). On the
other hand, production or manufacturing especially LPS has been performing better
than construction productivity. LPS has caused a revolution in manufacturing design,
supply and assembly and applied to construction industry, LPS changes the way work
244 is done throughout the project delivery process.

Summary of findings and conclusions


This study has looked into the background of construction, the current theory in
construction and its deficiencies. It also discussed characteristics and environmental
uncertainties in construction and emphasized how other industries have overtaken
similar characteristics and uncertainties and improved their performance.
The study successfully achieved its objective and found that the construction
industry is using principles of the LPS into construction management, but with
variations. It also revealed that the LPS has influence on the operational performance.
The results also revealed that there is difference in LPS application with respect to
respondent designation and educational level. Finally, it also concluded that there is
difference in operational performance improvement with respect to company size and
respondent designation.
The present study is testing the LPS principles with performance for the first time
in the construction. It also has developed new knowledge by identifying new LPS
principles from an extensive literature survey and applies them to the global
construction industry. The model has implications both for research and practice. For
research, it can be used as a model for operationalizing LPS in construction in order to
be able to study change processes. In practice, the model can be used as a tool to assess
the conversion from conventional construction organization to LPS. This study has
developed an instrument to measure degree of integration of LPS principles in the
construction industry that can be used globally. It can be used as a checklist for what
to aim at when trying to implement LPS in construction.
The findings of this preliminary study must be interpreted in the light of several
limitations. An inherent limitation of this study pertains to its sampling frame, as the
population of the study is limited to Grade Seven construction companies, the results of
this study cannot be generalised to the whole of industry. The second limitation of this
study stems from use of a cross-sectional analysis. A longitudinal analysis would have
been meaningful because it would have provided some measure of how the use of LPS
in construction influences its operational performance. The third limitation side is on
the survey mail as a research methodology because it can establish whether or not a
relationship exits between two variables but is not sufficient to determine the direction
of causality (Babbie, 1982). Furthermore, survey is like a self-report and therefore
truthfulness of reporting is important (Babbie, 1982).
There are number of topics that deserve further investigation in order to advance
knowledge in this area. For future research, the topics are suggested by this research
are; holistic integrative implementation of the LPS, a longitudinal analysis as this
study used cross-sectional analysis and an evaluation to test and improve safety
performance in the construction industry.
References Global
Agbulos, A. and Simaan, M.A.R. (2003), “An application of lean concepts and simulation for construction
drainage operations maintenance crews”, Proceedings of the 2003 Winter Simulation
Conference, Canada. industry
Agnal, H. and Nordin, F. (2009), “Consequences of outsourcing for organizational capabilities:
some experiences from best practice”, Benchmarking: An International Journal, Vol. 16
No. 3, pp. 316-34. 245
Akintoye, A. (1995), “Just in time application and implementation for building material
management”, Construction Management and Economics, Vol. 13, pp. 103-13.
Alarcon, L.F. (1994), “Tools for the identification and reduction waste in construction projects”,
in Alarcon, L.F. (Ed.), Lean Construction, AA Balkema, Rotterdam.
Al-Khalil, M.I. and Al-Ghafly, M.A. (1999), “Important causes of delay in public utility projects in
Saudi Arabia”, Journal of Construction Management and Economics, Vol. 17, pp. 647-55.
Alwi, S. (1995), “The relationship between rework and work supervision of upper structure in the
reinforced concrete building structure”, Proceedings of International Group of Lean
Conference, 10.
Alwi, S., Hampson, K. and Mohamed, S. (2002), “Non-value adding activities: a comparative
study of indonesian and australian construction projects”, Proceedings of International
Group Lean Conference, 10.
Antonio, S.I.C. (2002), “Lean construction: from theory to practice”, Proceedings of International
Group Lean Conference, 10.
Atkins, W.S. (1993), “Strategic study on the construction sector”, final report, Commission of the
EU community DG Industry, International Limited.
Babbie, E. (1982), “Mail and telephone surveys – total design method – Dillman”, Contemporary
Sociology – A Journal of Reviews, Vol. 11 No. 5, pp. 561-3.
Balakrishnan, R., Linsmeier, T. and Venkatachalam, M. (1996), “Financial benefits from JIT
adoption: effects of customer concentration and cost structure”, The Accounting Review,
Vol. 71 No. 5, pp. 1084-99.
Ball, M. (1988), Rebuilding Construction: Economics Change in the British Construction Industry,
Routledge, London.
Ballard, G. (1989), presentation to the Construction Industry Institute Employee Effectiveness
Task Force, March pp. 9-17.
Ballard, G. and Howell, G.A. (1998), “What kind of production is construction?”, paper presented
at 6th Annual International Group Lean Conference.
Banwell, G.H. (1964), The Placing and Management of Contracts for Building and Civil
Engineering Works, Ministry of Public and Building Works, HMSO, London.
Barrie, D.S. and Paulson, B.C. Jr (1992), Professional Construction Management, 3rd ed.,
McGraw-Hill, New York, NY.
Becker, R.M. (2003), Lean Manufacturing and the Toyota Production System, SAE International,
Dearborn, MI.
Bell, L.C. and Stukhart, G. (1987), “Costs and benefits of material management systems”, Journal
of Construction Engineering & Management, Vol. 113 No. 2, pp. 222-34.
Bennett, J., Pothecary, E. and Robinson, G. (1996), Designing and Building a World Class Industry,
Centre for Strategic Studies in Construction, University of Reading, Reading.
Berry, W.L., Christiansen, T., Bruun, P. and Ward, P. (2003), “Lean manufacturing: a mapping of
competitive priorities, initiatives, practices, and operational performance in Danish
BIJ manufacturer”, International Journal of Operations & Production Management, Vol. 23
No. 10, pp. 1163-83.
17,2
Bertelsen, S. (2003), “Complexity – construction in new perspective”, Proceedings of the
International Group Lean Conference 11.
Bertelsen, S. and Koskela, L. (2004), “Construction beyond lean: a new understanding of
construction management”, Proceedings of the International Group Lean Conference 12.
246 Bicca, I., Formoso, C.T. and Scardoehlh, L.S. (1994), Proceedings of the 5th International Seminar
on Structural Masonry for Developing Countries.
Bossink, B.A.G. and Brouwers, H.J.H. (1996), “Construction waste: quantification and source
evaluation”, Journal of Construction Engineering and Management, pp. 55-60.
Boyer, K.K. (1996), “An assessment of managerial commitment to lean production”, International
Journal of Operations & Production Management, Vol. 16 No. 9, pp. 48-59.
Browne, A. (2001), “Filthy, gloomy and chaotic: the reality of a new NHS”, The Guardian, 8 July.
Burati, J., Farrington, J. and Ledbetter, W. (1992), “Causes of quality deviations in design and
construction”, Construction Engineering and Management, Vol. 118 No. 1, pp. 34-49.
Carassus, J. (1998), “Production and management in construction: an economic approach”, CIB
W55-W65 Joint Meeting Proceedings, The University of Reading, Reading.
Chau, V.S. (2009), “Benchmarking service quality in UK electricity distribution networks”,
Benchmarking: An International Journal, Vol. 16 No. 1, pp. 47-69.
Cheetham, D.W., Steel, M.M. and Lewis, J. (1992), “The work of F.B. Gilberth and its relevance to
present construction management”, Proceedings of the 8th Annual Conference,
Association Researchers in Construction Management, Salford, pp. 285-96.
Chris, H. (1998), Project Management For Construction, 1st ed., Prentice-Hall, NJ.
CIDA (1993), A Report on the Time and Cost Performance of Australian Building Projects
Completed 1988-1993, CIDA, Sydney.
CII (1986), Costs and Benefits of Materials Management, University of Texas at Austin
Publication 7-1 CIL, Construction Industry Institute, Austin, TX.
Clark, W. (1922), “Relieving industry of burden”, Journal of Mechanical Engineering, December,
pp. 819-20.
Clough, R.H. and Sears, G.A. (1994), Construction Contracting, Wiley, New York, NY.
Cnudde, M. (1991), “Lack of quality in construction-economic losses”, Proceedings of European
Symposium on Management, Quality and Economics in Housing and Other Building
Sectors, Lisbon, pp. 508-15.
Cole (2002), The Royal Commission into Construction Industry, Commonwealth of Melbourne
Australia, Melbourne.
Cox, J.F. and Blackstone, J.H. (1988), “The educational society for resource management”, APICS
Dictionary, 9th ed., APICS, Falls Church, VA.
C21 Report (1999), Re-inventing Construction, Construction Industry Steering Committee
Ministry of Manpower and Ministry of National Development, Singapore.
Department of Statistics (1995), Annual Survey of Construction Industries, 1993, Department of
Statistics, Kuala Lumpur.
Drexl, N. and Hans, S. (2002), Software and Logistics Problems in Denver International Airport,
Technische Universität München, Munich (in German).
Dubois, A. and Gadde, L.E. (2002), “The construction industry as a loosely coupled system: Global
implications for productivity and innovation”, Construction Management and Economics
Journal, Vol. 20, pp. 621-31. construction
Duggirala, M., Rajendran, C. and Anantharaman, R.N. (2008), “Provider perceived dimensions of industry
total quality management in healthcare”, Benchmarking: An International Journal, Vol. 15
No. 6, pp. 693-722.
Dulaimi, M.D. and Tanamas, C. (1999), “The principles and applications of lean construction in 247
Singapore”, Proceedings of the IGLC 7, Berkeley, CA, USA.
Eaton, D. (1994), “Lean production productivity improvements for construction professions”,
paper presented at 2nd Workshop on Lean Construction, Santiago de Chile.
Egan, J. Sir (1998), Rethinking Construction, The Report of the Construction Task Force to the
Deputy Prime Minister John Prescott, on the scope for improving the quality and efficiency
of UK construction, DETR, Norwich.
Emiliani, M.L. (2000), “Cracking the code of business”, Management Decisions, Vol. 38 No. 2,
pp. 60-79.
Emmerson (1962), Survey of Problems before the Construction Industries, HMSO, London.
Fawcett, S.E. (1989), “The Japanese challenge: a note on the emergence of Japanese
competitiveness”, Operations Management Review, Vol. 7 No. 12, pp. 46-52.
Fazio, P., Moselhi, O., Theberge, P. and Revay, S. (1988), “Design impact of construction fast
track”, Construction Management Engineering and Economics, Vol. 5, pp. 195-208.
Fellows, R., Langford, D., Newcombe, R. and Urry, S. (1983), Construction Management in
Practice, Longman Incharge Construction Press, New York, NY.
Forbes, L.H., Ahmed, S.M. and Barcala, M. (2002), “Adapting lean construction theory for
practical application in developing countries”, Proceedings of First CIB-W107
International Conference South Africa.
Ford, H. (1926), “Mass production”, Encyclopaedia Britannica, 13th ed., Vol. 2, pp. 821-3.
Formoso, C.T., Isatto, E.L. and Hirota, E.H. (1999), “Method for waste control in the building
industry”, Proceedings of International Group of Lean Construction 7, Berkeley, CA, USA.
Friedrich, D.R., Daly, J.P. and Dick, W.G. (1987), “Revisions, repairs and rework on large
projects”, Journal of Construction Engineering and Management, Vol. 113 No. 3,
pp. 488-500.
Gann, D.M. (1996), “Construction as a manufacturing process? Similarities and differences
between industrialized housing and car production in Japan”, Construction Management
and Economics, Vol. 14, pp. 437-50.
Gidado, K.I. (1996), “Project complexity: the focal point of construction production planning”,
Construction Management and Economics, Vol. 14, pp. 213-25.
Gilbreth, F.B. (1911), Motion Study: A Method for Increasing the Efficiency of the Workman,
D. Van Nostrand, New York, NY.
Gilbreth, F.B. and Gilbreth, L.E. (1922), “Process charts and their place in management”, Journal
of Mechanical Engineering, Vol. 70, January, pp. 38-41.
Goncharuk, A.G. (2009), “Improving of the efficiency through benchmarking: a case of Ukrainian
breweries”, Benchmarking: An International Journal, Vol. 16 No. 1, pp. 70-87.
Gould, F.E. and Joyce, N.C. (2008), Construction Project Management, 3rd ed., Prentice-Hall,
Upper Saddle River, NJ.
Groak, S. (1992), The Idea of Building, E & FN Spon, London.
BIJ Gyles, R. (1992), Final Report of the Royal Commission into Productivity in the Building Industry,
Royal Commission into Productivity in the Building Industry in NSW, Sydney.
17,2
Hammarlund, Y. and Josephson, P. (1991), Sources of Quality Failures in Buildings, Department of
Building Economics and Construction Management Chalmers University of Technology,
Gothenburg.
Hampson, K. (1997), “Construction innovation in the Australian context”, paper presented at
248 International Workshop on Innovation Systems and the Construction Industry, IRC,
Montreal.
Hancock, M.R. (2000), “Culture difference between construction professionals in Denmark and
United Kingdom”, Report No. 324, Danish Building Research Institute – SBI, Hørsholm.
Heizer, J. and Render, B. (2005), Operations Management, 7th ed., Pearson Education, Upper
Saddle River, NJ.
Hill, T.J. (1992), Incorporating Manufacturing Perspective in Corporate Strategy, 2nd ed.,
Macmillan, London.
Hong Kong Polytechnic (1993), Reduction of Construction Waste: Final Report, The Hong Kong
Construction Association, Hong Kong.
Hopp, W.J. and Spearman, M.L. (2001), Factory Physics, 2nd ed., McGraw-Hill, New York, NY.
Howell, G.A. (1999), What is Lean Construction?, University of California, Berkeley, CA.
Howell, G.A. and Ballard, G. (1995), “Factors affecting project success in the piping function”,
Proceedings of the 3rd Annual Conference of the IGLC, Albuquerque, NM, USA, pp. 161-86,
available in Alarcon L.F. (Ed.) (1997), Lean Construction, Balkema, Rotterdam.
Howell, G.A. and Ballard, G. (1998), “Implementing lean construction: understanding and action”,
Proceedings of the 6th Annual Conference International Group for Lean Construction,
Guarujá, Brazil.
Howell, G.A. and Laufer, A.L. (1993), “Uncertainty and project objectives: project appraisal”,
Conference Proceedings of International Group of Lean Construction 7.
Ibn-Homaid, N.T. (2002), “A comparative evaluation of construction and manufacturing
materials management”, International Journal of Project Management, Vol. 20, pp. 263-70.
Illingworth, J. and Thain, K. (1988), Material Management – Is It Worth It? Technical Information
Service, Vol. 93, The Chartered Institute of Buildings, Ascot, pp. 1-5.
Imtiaz, G. and Ibrahim, A.R. (2006), “Clean construction by using lean production system”,
Proceedings of International Conference in the Built Environment in 21st Century,
University Technology Mara (UiTM), Shah Alam.
Josephson, P. (1994), Causes of Defects in Buildings, Chalmers University of Technology,
Gothenburg.
Journal of Mechanical Engineering (1921), “Report on elimination of waste in industry”, Journal
of Mechanical Engineering, September, pp. 579-83.
Joyce, R. (1995), The Construction (Design and Management) Regulations 1994 Explained,
Thomas Telford Publications, London.
Kaming, P.F., Olomolaiye, P.O., Holt, G.D. and Harris, F.C. (1997), “Factors influencing
construction time and cost overruns on high rise projects in Indonesia”, Construction
Management and Economics, Vol. 15, pp. 83-94.
Karlsson, C.H. and Ahlstrom, P. (1995), “Assessing changes towards lean production”,
International Journal of Operations & Production Management, Vol. 16 No. 2, pp. 24-41.
Kärnä, S. and Jonnonen (2005), “Project feedback as a tool for learning”, paper presented at
IGLC-13, Sydney.
Kerlinger, F. (1986), Foundations of Behavioural Research, 3rd ed., Holt, Rinehart and Winston, Global
New York, NY.
construction
Kharbanda, O.P. and Pinto, J.F. (1996), What Made Gertie Gallop? Lessons from Project Failures,
Van Nostrand Reinhold, New York, NY. industry
Kim, J. and Wilemon, D. (2003), “Sources and assessment of complexity in NPD projects”, R&D
Management, Vol. 33 No. 1.
Konchar, M.D., Sanvido, V.E. and Moore, S.D. (1997), “The benefits of design-build contracting in 249
the United States. Construction process re-engineering”, Proceedings of the International
Conference on Construction Process Re-engineering, Griffith University, pp. 191-201.
Koskela, L. (1992), “Application of the new production philosophy to construction”, CIFE
Technical Report No. 72, Stanford University, Stanford, CA.
Koskela, L. (1993), “Lean production in construction”, Proceedings of 1st Conference on
International Lean Construction.
Koskela, L. (2000), “An exploration towards a production theory and its application to
construction”, Doctorate dissertation, Helsinki University of Technology, Finland.
Krafcik, J.F. (1988), “Triumph of the lean production system”, Sloan Management Review, Vol. 30
No. 1, pp. 41-51.
Latham, M. Sir (1994), Constructing the Team: Joint Review of Procurement and Contractual
Arrangements in the United Kingdom Construction Industry, HSMO, London.
Ledbetter, W.B. (1994), “Quality performance on successful projects”, Journal of Construction
Engineering and Management, Vol. 120 No. 1.
Lee, S.H., Diekmann, J.E., Songer, A.D. and Brown, H. (1999), “Identifying waste: applications of
construction process analysis”, Conference Proceedings of the International Group of Lean
Construction 7.
Lee, S.M. and Schniederjans, M.J. (1994), Operations Management, Houghton Mifflin, Boston, MA.
Love, P.E.D. (2002), “Influences of project type and procurement method on rework costs in
building construction projects”, Journal of Construction Engineering and Management,
Vol. 128 No. 1, pp. 18-29.
Love, P.E.D., Mandel, P. and Li, Heng (1997), “A systematic approach to modelling the causes
and effects of rework in construction”, paper presented at the 1st International Conference
on Construction Industry Development: Building the Future Together, National University
of Singapore, Singapore.
Luhtala, M., Kilpinen, E. and Anttila, P. (1994), ALOGI: Managing Make to Order Supply Chain,
Helsinki University and Technology, Espoo.
McMohan, C. and Browne, J. (1998), CADCAM: Principles, Practice and Manufacturing
Management, 2nd ed., Addison Wesley, New York, NY.
Marosszeky, M., Thomas, R., Khalid, K., Davis, S. and NcGeorge, D. (2002), “Quality management
tools for lean production: moving from enforcement to empowerment”, Conference
Proceedings of International Group of Lean Construction 10.
Miguel, P.A.C. and Carnevalli, J.A. (2008), “Benchmarking practices of quality function
deployment: results from a field study”, Benchmarking: An International Journal., Vol. 15
No. 6, pp. 657-76.
Miller, F.J. (1922), “Prevention of waste in industry”, Journal of Mechanical Engineering, Vol. 42,
January, pp. 9-10.
MIT (2000), “Transitioning to a lean enterprise: a guide for leaders”, Vols 1/2/3, available at:
http://lean.mit.edu/Products/TTL/TTL-vol1.pdf
BIJ Mohamed, S. and Tucker, S.N. (1996), “Options for applying BPR in the Australian construction
industry”, The International Journal of Project Management, Vol. 14 No. 6, pp. 379-85.
17,2
Moore, S. and Gibbons, A. (1997), “Is lean manufacturing universally relevant? An investigative
methodology”, International Journal of Operations and Production Management, Vol. 17
No. 11, pp. 1131-352.
Nam, C.H. and Tatum, C.B. (1988), “Major characteristic of constructed products and resulting
250 limitations of construction technology”, Construction Management and Economics, Vol. 6,
pp. 133-48.
NEDO (1988), Faster Building for Commerce, National Economic Development Office, London.
Oglesby, C.H., Parker, H.W. and Howell, G.A. (1989), Productivity Improvement in Construction,
McGraw-Hill, New York, NY.
Ohno, T. (1988), Toyota Production System: Beyond Large-Scale Production, Productivity Press,
Portland, OR.
Okpala, D. and Aniekwu, A.N. (1988), “Causes of high costs of construction in Nigeria”, ASCE
Journal of Construction Engineering and Management, Vol. 114 No. 2.
Olomolaiye, P.O., Wahab, A. and Price, D.F. (1987), “Problems influencing craftsmen’s
productivity in Nigeria”, Journal of Building & Environment, Vol. 22, pp. 317-23.
Paulson, B. (1976), “Designing to reduce construction cost”, Journal of Construction Division,
ASCE, Vol. 104, No. CO4, pp. 587-92.
Pheng, S.L. (2005), “Modern-day lean construction principles”, Management Decision, Vol. 43
No. 4, pp. 523-41.
Polat, G. and Ballard, G. (2004), “Waste in Turkish construction: need for lean construction
techniques”, Conference Proceedings of International Group of Lean Construction 12,
Denmark.
Roberts, E.S. (1999), “In defence of the survey method: an illustration from a study of user
information satisfaction”, Accounting and Finance, Vol. 39, pp. 53-77.
Robinson, A. (1991), Continuous Improvement in Operations: A Systematic Approach to Waste
Reduction, Productivity Press, Cambridge, MA.
Santos, A.D. (1999), Application of Flow Principles in the Production Management of Construction
Site, University of Salford, Salford.
Santos, A.D. and Powell, J.A. (2001), “Assessing the level of teamwork in Brazilian and English
construction sites”, Leadership & Organisation Development Journal, Vol. 22 No. 4,
pp. 166-74.
Santos, A.D., Powell, J.A. and Formoso, C.L. (2000), “Setting stretch targets for driving
continuous improvement in construction: analysis of Brazilian and UK practices”, Work
Study, Vol. 49 No. 2, pp. 50-8.
Schmenner, R.W. (1993), Production/Operations Management: From the inside out, 5th ed.,
Prentice-Hall, Upper Saddle River, NJ.
Schuster, L. (1993), Lean Management – Catchword or Necessity in the German Banking System,
RP 93/12, University College of North Wales, Bangor.
Schroeder, R.G. (1993), Operations Management: Decision Making in the Operations Function,
McGraw-Hill, New York, NY.
Serpell, A., Venturi, A. and Contreeas, J. (1995), “Characterization of waste in building construction
project”, in Alarcon, L.F. (Ed.), Lean Construction, AA Balkema, Rotterdam, 1997.
Siegel, I.H. (1980), Keynote Address in: A National Strategy for Improving Productivity in Building
and Construction, National Academy of Sciences, Washington, DC.
Sjoholt, O. (1998), “Managing quality improvement work”, paper presented at Tecnomex’ 98, Global
Mexico.
construction
Sjostorm, C. (1998), “Construction and environment”, paper presented at CIB World Congress,
No. 3, Stockholm. industry
Skoyles, E.R. and Skoyles, J. (1976), “Material wastage: a misuse of resources”, Building Research
and Practice, July/August, pp. 232-43.
Skoyles, E.R. and Skoyles, J. (1987), Waste Prevention on Sites, Mitchell, London. 251
Sohal, A.S. (1996), “Developing a lean production organisation: an Australian case study”,
International Journal of Operations & Production Management, Vol. 16 No. 2, pp. 91-102.
Spear, S.J. and Brown, H.K. (1999), “Decoding the DNA of Toyota production system”, Harvard
Business Review, September-December, pp. 97-106.
Sriparavastu, L. and Gupta, T. (1997), “An empirical study of just in time and total quality
management principles implementation in manufacturing firms in USA”, International
Journal of Operations & Production Management, Vol. 17 No. 2, pp. 1215-32.
Stoeckel, A. and Quirke, D. (1992), “Services: setting the agenda for reform”, paper presented at
the Centre for International Economics for the Service Industries Research Program,
Australian Government.
Tavistock Institute (1965), Interdependence and Uncertainty, Tavistock, London.
Towill, D.R. (1997), Enabling Construction as a Manufacturing Process, Innovation in Civil and
Construction Engineering, Edinburgh, pp. 145-51.
Tucker, R. (1986), “Management of construction productivity”, Journal of Management
Engineering, Vol. 2 No. 3, pp. 148-56.
US Census Bureau (1997), Economics Census 1997: Construction, Economics and Statistics
Administration, US Department of Commerce, Washington, DC.
US Census Bureau (2002), All Other Speciality Trade Contractors: 2002 Economic Census,
Economics and Statistics Administration, US Department of Commerce, Washington, DC.
Vershuren (1980), Productivity in the Building Industry, Management SA Builder.
Vonderembse, M.A. (1996), Operations Management: Concept Methods and Strategies/Mark A
Vonderembse, West Publishing, Minneapolis, MN.
Vrikjhoef, R. and Koskela, L. (2000), “The four roles of supply chain management in
construction”, European Journal of Purchasing & Supply Chain Management, Vol. 6,
pp. 169-78.
Walker, A. (1996), Project Management in Construction, 3rd ed., Blackwell Science, Oxford.
Warszawski, A. (1990), Industrialisation and Robotics in Building: A Managerial Approach,
Harper & Row, New York, NY.
Weihrish, H. and Koontz, H. (1993), Management: A Global Perspective, McGraw-Hill, New York, NY.
Wells, J. (1985), “The role of construction in economics growth and development”, Habitat
International, Vol. 9 No. 1, pp. 55-70.
Wild, A. (1995), Production and Operations Management, Wiley, New York, NY.
Wild, A. (2002), “The unmanageability of construction projects and the theoretical psycho-social
dynamics of project”, Engineering, Construction and Architectural Management, Vol. 9
No. 4, pp. 345-51.
Wilfred, F.K.K. (1992), “Project management with problems”, MSc (Project Management) thesis,
National University of Singapore, Singapore.
BIJ Williams, T. (1999), “The need for new paradigms for complex project”, International Journal of
Project Management, Vol. 17 No. 5, pp. 269-73.
17,2 Womack, J. and Jones, D. (1996), Lean Thinking: Banish Waste and Create Wealth in Your
Corporation, Simon & Schuster, Delran, NJ.
Womack, J.P., Jones, D.T. and Roos, D. (1990), The Machine that Changed the World, Rawson
Associates, New York, NY.
252 Wong, E.T.T. and Norman, G. (1997), “Economics of materials planning systems for
construction”, Construction Management and Economics, Vol. 15, pp. 39-47.
Wu, Y.C. (2003), “Lean manufacturing: a perspective of lean suppliers”, International Journal of
Operations & Production Management, Vol. 23 No. 11, pp. 1349-76.
Wyatt, D.P. (1978), Material Management: Part I, The Chartered Institute of Building, Longman.

Further reading
CIDB (2004), Master Plan for Occupational Safety and Health in Construction Industry
2005-2010, CIDB, Kuala Lumpur.
CIDB (2004), Construction Industry Development Board Directory, CIDB, Kuala Lumpur.
Howell, G.A., Ballard, G., Abdelhamid, T. and Mitropoulos, P. (2002), “Working near the edge: a
new approach to construction safety”, paper presented at the International Group of Lean
Construction 10.
Imtiaz, G. and Ibrahim, A.R. (2005), “Lean production system in project delivery: the way
forward for Malaysian construction industry”, Proceedings of Kuala Lumpur Quantity
Surveyor Convention, Kuala Lumpur.
Lee, J. and Fong, T.Y. (2000), “Environmental management within the development approval
process in the construction industry”, paper presented at the Dialogue on Good
Environmental Practices in the Construction Industry, Bangi.

Corresponding author
Zafar U. Ahmed can be contacted at: zafaruahmed@gmail.com

To purchase reprints of this article please e-mail: reprints@emeraldinsight.com


Or visit our web site for further details: www.emeraldinsight.com/reprints

You might also like