Professional Documents
Culture Documents
© GHD 2023
This document is and shall remain the property of GHD. The document may only be used for the purpose for
which it was commissioned and in accordance with the Terms of Engagement for the commission. Unauthorised
use of this document in any form whatsoever is prohibited.
1. Introduction 1
1.1. Assessments and upgrades over time 2
2. About the risk assessment 4
2.1. Results of the risk assessment 4
2.2. How the consequence of failures are assessed 4
3. Managing the possibility of dam failure 7
3.1. Assessing risk reduction measures 7
3.1.1. Short term options 7
3.1.2. Long term options 9
3.2. What happens next? 9
Table index
Table 2.1 Failure modes and their probabilities 6
Figure index
Figure 1.1 Chichester Dam assessment and upgrade timeline 2
Figure 1.2 Chichester Dam 3
Figure 2.1 Failure Modes in relation to the Safety Threshold 5
The eleven failure modes are shown on the above graph, a more detailed version of which is listed as Figure 8.1 in
the full Assessment Report. In each case the potential loss of life has been approximated. The blue line represents
the aggregated or combined risks across all of the failure modes. As the blue line is above the diagonal Safety
Threshold this brings about the requirement for action to reduce the probability of failure, the potential for loss of
life, or both.
These modes are described in more detail below in Table 2.1, and more detail is provided in the main report in
Section 6 – Analyses of failure modes.
Approximate
Failure
annual
Mode Failure Mode ID Simplified Description
probability
Number
of failure
1 LD-Rf-Sl-1 The historical landslide area is reactivated after extended heavy rainfall. 1 in 10,000
The landslide damages the northern portion of the dam and leads to
complete breach.
2 LA-Hy-Sl(Fdn)-2 Very rare flood occurs, causing sliding of the dam on a rock defect 1 in 600
beneath the dam in the northern abutment.
3 LA-Hy-Sl(Cn)-3 Very rare flood occurs. Northern portion of the dam structure fails leading 1 in 10,000
to a breach.
4 LA-Eq-Sl(Fdn)-4 Extreme earthquake occurs, which leads to damage of anchors and 1 in 40,000
drainage and subsequent failure of the dam due to sliding of the northern
portion of the dam.
5 SP-Hy-Sl(Fdn)-5 Extreme flood event occurs, causing sliding of the dam on a rock defect 1 in 5,000
in the foundation beneath the spillway.
6 SP-Hy-Sl(Cn)-6 Extreme flood occurs. Part of the dam structure around the spillway fails 1 in 5,000
leading to a breach.
7 SP-Hy-Sl(Apr)-7 Extreme flood event occurs, causing extensive downstream erosion and 1 in 5,000
undercutting of the dam leading to failure on a rock defect in the
foundation beneath the spillway.
8 SP-Eq-Sl(Fdn)-8 Extreme earthquake occurs, which leads to damage of anchors and 1 in 40,000
drainage and subsequent failure of the dam due to sliding of the spillway
portion of the dam.
9 RA-Hy-Sl(Fdn)-9 Very rare flood occurs, causing sliding of the dam on a rock defect 1 in 500
beneath the dam in the southern abutment.
10 RA-Hy-Sl(Cn)-10 Very rare flood occurs. Southern portion of the dam structure fails leading 1 in 7,000
to a breach.
11 RA-Eq-Sl(Fdn)-11 Extreme earthquake occurs, which leads to damage of anchors and 1 in 40,000
drainage and subsequent failure of the dam due to sliding of the southern
portion of the dam.
Instrumentation
The dam is fitted with a range of instrumentation, and monitoring is carried out daily.
The frequency at which these instrumentations are monitored is in accordance with Australian Guidelines. In
addition to these, it is recommended that some additional instruments be considered to improve monitoring.
Piezometers – installation of further piezometers within the dam, especially at the left abutment and spillway. The
pore pressure beneath the dam is a key factor in assessing the stability.
Landslide instrumentation – installing instrumentation for the landslide to monitor movement and changes in
porewater pressure.
Maintenance
The following maintenance is recommended to be undertaken in the short term:
– Continue to flush drains on the right abutment.
– Continue to flush drains in the spillway apron.
Post-tensioned anchoring
Installing new post tensioning anchors along the dam would increase the dam’s resistance against sliding.
As part of the anchor option, there may opportunities to install new drainage on the left side of the dam where
there is minimal drainage. The new drainage would also improve the stability in this location.
Decommissioning of dam
In addition to the above options, some consideration could be given to the decommissioning of the existing dam to
remove risks of failure. This would only be considered after other options have been exhausted.
Hunter Water’s Lower Hunter Water Security Plan outlines a range of future water supply options, including a
connection with the Glennies-Lostock Dam system in the Upper Hunter, and desalination in the Lower Hunter. The
Lower Hunter Water Security Plan is available here.
Landslide treatment
Any treatment to the historical left abutment landslide area should only be completed once further investigations
are completed and the properties and shape of the area better understood. Treatment of the area may include
drainage to reduce groundwater pressures.