Professional Documents
Culture Documents
Report Mures 09.05
Report Mures 09.05
Peeling 5
Site marking same
making iron frameworks for concrete belts 4
site cleaning 2
Tree cut 2
cut and fill 5
topograph and picketing for vegetation cut 1
making iron frameworks for concrete belts 4
- -
Perimetral fence 6
Perimetral fence 2
Iron armoured frameworks for concrete 8
Interior road leveling and compaction with gravel 3
Cutt and fill and Compound 5
Perimetral fence 6
Existing Equipment on site On-site deliveries
Truck , Excavator
Truck , Excavator ,Road Roller
Excavator
Truck , Excavator ,Road Roller, Bulldozer
same -
-
tractor with blade
- container (2 pcs)
perimetral fence
excavator, buldozer, truck, front loader -
excavator, buldozer, truck, front loader
Manitou , excavator , buldozer
excavator, buldoexcavator, small truck
- -
-
Manitou perimetral fence (1 truck)
- -
Front road roller, buldo, truck gravel
Truck, Excavator, Road roller, Buldozer -
small excavator/driller, bobcat, manitou (2 pcs)
Special Events
-
-
-
-
-
-
Heavy raining, works on peeling could not be performed
Due to heavy rain, works on soil could not be performed
Soil was super wet and there were 3 big ponds on the
site; due to this no heavy works were performed
due to very wet soil, no heavy works could be perfomed
installation of an electricity pole by Electrica S.A. to bring electricity to the construction site
acces road is very bad; subcontractor said is going to
apeal the contract because they can't prfomed the work
because of the road and site conditions
the raod has problems because there is a lot of wet mud under the ballast/stones
-
works performed for the perimetral road; soil is soft and full of roots from the trees in some areas
4 containers were delivered and installed in position
cut and fill operations were made on the north side of the hill
compound soil was compacted and graded on the north side hill
steel armoured framework was put in place acording to the plans provided by Energobit
Subcontractor; all for the station building
topo measurments were made to determine the road and cable ditches
Armoured iron frameworks were made for the structure of Medium Voltage Building (foundation)
Gravel was delivered, compacted and leveled on the interior road
cut and fill and compounding operations were made north and center part of Voivodeni 1
perimetral fence was instaled on east side of Voivodeni 2 (ongoing)
Photo's