Revision/Date

Technical Document
Page 1 of 1
DAILY DIARY OF THE SITE Issued by Krone Solar CEE

WEEKLY DIARY OF THE SITE ACTIVITY NO. 4

SITE: Mures DAY/WEEK:18-21/04/2023


PRESENT WORKFORCE : WEATHER
00
Bogdan Puscas – Krone Solar TEMPERATURE MORNING(8 ):
Mircea Panescu – Sef Santier Dtek LUNCH(1400):
Marius Calabaza - Ostenwerg EVENING(1600):
Ionel Muresanu – Energobit

WORKING HOURS:
FROM 8:00 TO 17:00

EXISTING EQUIPMENT ON SITE:


MACHINE NAME NUMBER OPERATING STATUS
OF PIECES
Excavator / Voievodeni 1 Cutt and fill and Compound, north side hill
Front loader / Voievodeni 1 Cutt and fill and Compound, perimetral road,
north side hill
Bobcat / Voievodeni 1 Compound, fence
Buldozer / Voievodeni 1 Cutt and fill and Compound, north side hill
Truck / Voievodeni 1 Cutt and fill and Compound, perimetral road,
north side hill,
Tractor/Pacureni site 1 Tree cut
Excavator / Station Pacureni 1 Compound
Excavator (Small) / Station Pacureni 1 Excavating foundations

RECEIPT/DISPATCH OF MATERIALS AND EQUIPMEN:


NR.
MATERIAL UM QUANTITY TRANSPORT OBSERVATIONS
Fence Pcs 1 truck - Delivered to Voivodeni site

© Krone Solar CEE SRL All Rights Reserved This document is subject to the handling restrictions set forth on
the title page
Revision/Date
Technical Document
Page 2 of 1
DAILY DIARY OF THE SITE Issued by Krone Solar CEE

WORKS PERFORMED:
Foundations, Pacureni Station platform: Soil was excavated in order to make foundations for “Cladire MT”, “cuva
trafo”, and perimetral fence
Armoured Iron frameworks, Pacureni station: Armoured iron frameworks were made for future concrete structures
Cut and fill, Compound Voivodeni: Cut and fill and compound operations were made on the north and center sides of
the hill
Fence, Voivodeni: holes were drilled for the fence poles, and fence was instaled on the east side of Voivodeni 2
Vegetation cut, Pacureni site: Vegetation was cut on the site on the valley area

SITE PROVISIONS, VERBAL OR WRITTEN INSTRUCTIONS: -


Site Photo’s: https://e.pcloud.link/publink/show?code=kZsa7jZUDgpn4v3UufKIBjYfTfdphCWyTF7

SPECIAL EVENTS:

© Krone Solar CEE SRL All Rights Reserved This document is subject to the handling restrictions set forth on
the title page
Revision/Date
Technical Document
Page 3 of 1
DAILY DIARY OF THE SITE Issued by Krone Solar CEE

Item Observation Picture Risk +Mitigation

REPRESENTATIVE BUILDER SITE SUPERVISOR

© Krone Solar CEE SRL All Rights Reserved This document is subject to the handling restrictions set forth on
the title page
Revision/Date
Technical Document
Page 4 of 1
DAILY DIARY OF THE SITE Issued by Krone Solar CEE

EXECUTION GRAH
Substation

PV Electrical

PV Mechanical

Design

0 20 40 60 80 100 120

PROGRE Grid