You are on page 1of 9

MINISTRY OF CONSTRUCTION

CONSTRUCTION CORPORATION NO.1 CO., LTD (CC1)


111A Pasteur – Ben Nghe Ward – District 1 – HCMC
Tel: 84.8.8222059 – 38222172 Fax: 84.8.8290500 – 38222172

NGHI SON REFINERY AND PETROCHEMICAL COMPLEX

PACKAGE: TCF A2 & TCF C


TEMPORARY FACILITIES AND GATE

METHOD STATEMENT

ITEM / STRUCTURE: ACCESS ROAD

LOCATION: GATE 1 & 3

Revision Details
Rev. Date Revision Status Checked Approved
01 04/11/2013 For Approval
02 06/11/2013 For Approval
03 08/11/2013 For Approval

1
MINISTRY OF CONSTRUCTION
CONSTRUCTION CORPORATION NO.1 CO., LTD (CC1)
111A Pasteur – Ben Nghe Ward – District 1 – HCMC
Tel: 84.8.8222059 – 38222172 Fax: 84.8.8290500 – 38222172

CONTENT

1. INTRODUCTION

2. REFERENCE DOCUMENTS

3. EQUIPMENT

4. PROCEDURE AND SEQUENCE

5. SAFETY AND ENVIRONMENT MEASURE

ATTACHMENT: ASPHALT ROAD WORK PROCEDURE

2
MINISTRY OF CONSTRUCTION
CONSTRUCTION CORPORATION NO.1 CO., LTD (CC1)
111A Pasteur – Ben Nghe Ward – District 1 – HCMC
Tel: 84.8.8222059 – 38222172 Fax: 84.8.8290500 – 38222172

1. INTRODUCTION

The purpose of this Method Statement is to describe the methodology and the related works
involved in the construction of the access road at gate 2 for the Nghi Son Refinery and
Petrochemical Complex project.

Location of Access Road for Gate 2

The asphalt access roads at gate 1 and gate 3 locations are 12m-wide x 30m-long and 15m-wide x
18m-long respectively. A system of three 20m-long D600 (H30) concrete pipes for drainage and
one 20m-long D600 (H30) for cable shall go underneath the road. The concrete pipes shall be laid
on theirs supports that lie on a 300mm thick sand bedding layer. Filling and compaction activities
shall be carried out until the design level of the bottom of the base course layers are reached. Filling
material shall be in compliance with Specification 3550-8310-SP-0009: Earthwork Specification.
Details can be referred to Drawing: D-F40-3200-0006-SD-01, D-F40-3200-0008-SD-01, D-F40-
3200-0009-SD-01.

3
MINISTRY OF CONSTRUCTION
CONSTRUCTION CORPORATION NO.1 CO., LTD (CC1)
111A Pasteur – Ben Nghe Ward – District 1 – HCMC
Tel: 84.8.8222059 – 38222172 Fax: 84.8.8290500 – 38222172

Layout of Access Road at Gate 1

Section detail of Access Road at Gate 1

4
MINISTRY OF CONSTRUCTION
CONSTRUCTION CORPORATION NO.1 CO., LTD (CC1)
111A Pasteur – Ben Nghe Ward – District 1 – HCMC
Tel: 84.8.8222059 – 38222172 Fax: 84.8.8290500 – 38222172

1
20000

20000

5000
3000
2000

3000

3000
18000

2 2

7500 7500
1

TO HA NOI

TO NGHI SON SORT

Layout of Access Road at Gate 3

Pipe type: D600, L = 4m, weight: 1.25T


Equipment: Lorry crane 10T for transporting and installation
Section detail of Access Road at Gate 3

5
MINISTRY OF CONSTRUCTION
CONSTRUCTION CORPORATION NO.1 CO., LTD (CC1)
111A Pasteur – Ben Nghe Ward – District 1 – HCMC
Tel: 84.8.8222059 – 38222172 Fax: 84.8.8290500 – 38222172

2. REFERENCE DOCUMENTS
 Civil Drawings

 3550-8310-SP-0008_Rev. D4 : Design of concrete foundations, structures, asphalt roads &


paving

 3550-8310-SP-0009_Rev. D3 : Earthwork Specification

 Vietnamese Standard TCVN-4447 1987 (Earth work: construction and inspection


procedures)

3. EQUIPMENT

The following equipment shall be mobilized for the execution of access road

+ Excavator 0.9m3(1pc) + Dump truck 20m3 (2pcs)

+ Plate compactor (2pc) + Lorry crane 10T (1pc)

+ Jumping jack compactor (2pc) + Roller compactor 16T (1pc)

+ Pumping (2pc)

+ Related special equipment for asphalt work (which shall be provided by the supplier)

+ Total station + Automatic level with tripod and staff rod

+ Hand tools + Barricade

+ Water tank

4. PROCEDURE AND SEQUENCE

4.1. Site Survey, layout, and marking

General survey and record of existing levels of the area shall be carried out by establishing proper
grid system.

Layout & marking will be marked using surveying equipment having valid calibration certificate.

4.2. Clearing and grubbing

The initial survey work indicate that the area where the work is going to be executed has already
reached the design elevation, therefore no excavation work shall be needed. However, some
clearing and grubbing work for the area is required in order to remove the grass layer at the top and

6
MINISTRY OF CONSTRUCTION
CONSTRUCTION CORPORATION NO.1 CO., LTD (CC1)
111A Pasteur – Ben Nghe Ward – District 1 – HCMC
Tel: 84.8.8222059 – 38222172 Fax: 84.8.8290500 – 38222172

a little muddy soil layer at the ground. The grubbed material then shall be disposed in an approved
area.

Clearing work shall be carried out by an excavator with the assistant of surveyor to ensure the
design elevation as well as the gradient of the pipes.

4.3. Sand bedding

The muddy soil layer shall be removed until approx. 200mm depth from existing ground and then
replaced by the 200mm bedding sand layer.

The preliminary compaction for base shall be carried out before the carrying out of the sand bedding
layer.

The 200mm-thick sand bedding layer shall be achieved by placing and uniform compaction of the
approved sand material.

The filled material shall be transported to the site and be unloaded directly from the Road 513 side
(the removal of the temporary fence for access is the scope of other contractor).

Temporary access line for easy construction shall also be constructed using filling material.

Placing of sand shall be carried out by truck with the assist of an excavator for spreading out the
material evenly over the area. Compaction then shall be carried out by roller compactor.

The compacted fill shall achieve dry density of 90% of the maximum dry density at optimum
moisture content as determined in the standard proctor laboratory tests.

During compaction, the moisture contact of fill material shall be maintained the optimum moisture
content. If required, water shall be added to the fill material in order to maintain the necessary
moisture contact.

After compaction, the surface shall be leveled using suitable equipment.

4.4. Piping Installation

Each piece of pipe and its support shall be examined prior to the installation.

Damaged segment of pipe shall be discarded.

Pipes and fittings shall be cleaned before installation

Lorry crane shall be used to unload and place the concrete pipes and supports on the sand bedding.

7
MINISTRY OF CONSTRUCTION
CONSTRUCTION CORPORATION NO.1 CO., LTD (CC1)
111A Pasteur – Ben Nghe Ward – District 1 – HCMC
Tel: 84.8.8222059 – 38222172 Fax: 84.8.8290500 – 38222172

Fixing and aligning of the pipe segments then shall be carried out under the checking of surveyor to
ensure the correct position.

4.5. Backfilling with sand

Once testing has been conducted and the acceptance is granted, backfilling then shall be carried
out. Sand filling material shall comply with the requirements stated in Earthwork specification
(3550-8310-SP-0009).

Before commencing the backfilling work, unsuitable materials which may accidently fall into the
trench during the pipe laying process shall be removed.

Filling from the bottom of trenches and to a height of 400mm above the top of the pipes shall be of
sand material, well compacted, watered if necessary. Sand fill material around the area around the
pipe shall be carefully placed and packed. The general body of filling shall be placed in layers of
200 mm and thoroughly compacted to a 95% maximum optimum dry density.

4.6. Compaction and Leveling the soil fill

Fill materials shall generally be placed in layers, and uniformly compacted. Only when inspection
and approval of the QC Engineer is granted, the work for the next layer shall be carried out. Loose
thickness of each layer shall not be greater than 250 mm in order to have the thickness after
compaction approx. 300mm.

Compaction shall be done by roller compactor .

The compacted soil fill shall also be required to achieve a dry density of 95% of the maximum dry
density at optimum moisture content as determined in the standard proctor laboratory tests; and the
required water content shall also need to be maintained during the filling and compaction.

4.7. Dewatering

The Site-ditches shall be provided in order to maintain the dry condition of the construction area. All
site-water shall be conducted into the collection pits and pumped out.

4.8. Sandbag protection

Placing of sandbag shall be carried out simultaneously with the compaction of each layer. The
purpose of sandbag protection is to ensure the filled and compacted material is well placed and
movement is minimized. The height of the sandbag protection layer shall always be higher than the

8
MINISTRY OF CONSTRUCTION
CONSTRUCTION CORPORATION NO.1 CO., LTD (CC1)
111A Pasteur – Ben Nghe Ward – District 1 – HCMC
Tel: 84.8.8222059 – 38222172 Fax: 84.8.8290500 – 38222172

level of the compacted layer.

4.9. Asphalt road

The full work procedure of asphalt road can be referred to the attachment.

5. SAFETY AND ENVIRONMENT MEASURE

 Safety training should be conducted to all personnel assigned at site prior to commencement
of the work.

 The work involves some transportation and unloading material on the side of Road 513. And
to ensure safety, the following actions shall be carried out. Barricades and sign boards shall
be provided when vehicles stop on the road side for unloading. In addition, competent signal
person shall always be assigned to assist operators.

 Competent signal person shall always be assigned to assist equipment operators to ensure the
safety of nearby personnel.

 Barricade and sign boards shall also be provided along the area boundary to avoid
unauthorized and unnecessary enter/egress.

 Personal Protective Equipment (PPE) shall be worn at all times.

 Good housekeeping shall be maintained in the work area.

 Appropriate measures to be applied for controlling air pollution shall be: i) watering when
required, ii) vehicle transporting fill material shall have cover.

 Daily checking of equipment prior to start of work and regular checking of equipment before
using shall always be carried out to ensure no contamination could occur due to oil leakage.

You might also like