Work Method Statement For Column Internal
Work Method Statement For Column Internal
ALMUZAIN
(AL MUZAIN GULF SAUDI CONTRACTING
COMPANY
Jubail Industrial City, Saudi
Work Method Statement
Note: This Work method statement is the property of ALMUZAIN and shall not be duplicated,
copied or otherwise reproduced, without prior consent of General Manager
ISSUE NO: 01 REV NO: 0 PREPARED BY: REVIEWED BY: APPROVED BY:
DOC.NO.MZN-MED-WMS-041
Page 1 of 12
Sensitivity: MZN Internal
ALMUZAIN
(AL MUZAIN GULF SAUDI CONTRACTING
COMPANY
Jubail Industrial City, Saudi
Work Method Statement
Contents
1.0 Purpose
2.0 Scope of work
3.0 References & Procedures
4.0 Safety Precautions
5.0 Health safety & Environment Measures
5.1 Preparation
5.2 Lifting Equipment
5.3 During Site Execution
5.4 Safety Inspections
6.0 Responsibilities
7.0 Quality
8.0 Tools and Equipment to be used
9.0 Site Activities
9.1 Pre-Shutdown Activities
9.1.1 Jobs at Site
9.2 Shutdown Activities
9.2.1 Column Entry
9.2.2 Activities inside the column
9.3Post-shutdown activities
10.0 Housekeeping
DOC.NO.MZN-MED-WMS-041
Page 2 of 12
Sensitivity: MZN Internal
ALMUZAIN
(AL MUZAIN GULF SAUDI CONTRACTING
COMPANY
Jubail Industrial City, Saudi
Work Method Statement
1.0 Purpose
The purpose of this work method statement is to describe in detail all required
measures taken to execute the Column jobs in SATORP.
This document is applicable to all employees and sub-contractors working for
Columns Inspection and Modification carried out in SATORP.
DOC.NO.MZN-MED-WMS-041
Page 3 of 12
Sensitivity: MZN Internal
ALMUZAIN
(AL MUZAIN GULF SAUDI CONTRACTING
COMPANY
Jubail Industrial City, Saudi
Work Method Statement
DOC.NO.MZN-MED-WMS-041
Page 4 of 12
Sensitivity: MZN Internal
ALMUZAIN
(AL MUZAIN GULF SAUDI CONTRACTING
COMPANY
Jubail Industrial City, Saudi
Work Method Statement
6.0 Responsibilities
6.1 The Site Engineer/Supervisor will be responsible to manage and direct project
construction activities and ensure efficient implementation of work in accordance with
the Project Specification and standards.
6.2 The QAQC Representative shall witness all activities and tests performed and ensure
that all works are carried out to client satisfaction.
6.3 Supervisor shall monitor the execution of the work.
6.4 Foreman shall lead the work force during the execution of the work.
7.0 Quality
7.1 All the Quality related documents / Procedures shall be submitted and get it approved
before proceeding of any work.
7.2 (If Required) Submission of weld map / location map identifying the welding works
(Obstruct Piping cutting & welding) shall be prepared by the QA/QC Engineer.
7.3 Submission of ITP (Inspection Test Plan) shall be prepared by the QA/QC Engineer.
7.4 The Quality department (QAQC representative) shall ensure that the alignment is
done to client satisfaction.
7.5 The required materials shall be checked before use.
7.6 All the calibrated inspection tools to be used.
7.7 AL-MUZAIN QC inspector & Third-party NDT technician shall co-ordinate with client
inspector. They shall be responsible to assure, monitor & control quality activities for
the Column internal replacement/repair work. (If any NDT Required)
7.8 Observe the stage wise inspection as per the approved inspection and test plan (ITP)
for the job.
7.9 Get clearance from client representative(s) at site before proceeding for the
subsequent stages.
7.10 Inspection report shall be prepared and get it signed from Client inspector.
The below mentioned tools are tentative and required tools will be mobilized as required.
8.1 Air Compressor
8.2 Forklift / Trailor / boom truck
8.3 Hydro Jetting Machine
8.4 Vacuum truck / super sucker.
8.5 Air winches
8.6 Chain Block / Lever Block – as per requirements
8.7 Grinding / buffing Machine
8.8 Slings & shackles
8.9 Tower Light, Halogen lights, electric panel board, extension board, transformer, 24volt
light, 110v power tools, power cable etc. (as column required)
8.10 Hand tools etc.
All the Equipment and tools will be inspected by SATORP before taking to job location.
DOC.NO.MZN-MED-WMS-041
Page 5 of 12
Sensitivity: MZN Internal
ALMUZAIN
(AL MUZAIN GULF SAUDI CONTRACTING
COMPANY
Jubail Industrial City, Saudi
Work Method Statement
DOC.NO.MZN-MED-WMS-041
Page 6 of 12
Sensitivity: MZN Internal
ALMUZAIN
(AL MUZAIN GULF SAUDI CONTRACTING
COMPANY
Jubail Industrial City, Saudi
Work Method Statement
DOC.NO.MZN-MED-WMS-041 ALMUZAIN
(AL MUZAIN GULF SAUDI CONTRACTING COMPANY Page 7 of 12
Jubail Industrial City, Saudi Arabia)
9.2.2.41
DOC.NO.MZN-MED-WMS-041
Page 8 of 12
Sensitivity: MZN Internal
ALMUZAIN
(AL MUZAIN GULF SAUDI CONTRACTING
COMPANY
Jubail Industrial City, Saudi
Work Method Statement
DOC.NO.MZN-MED-WMS-041
Page 9 of 12
Sensitivity: MZN Internal
ALMUZAIN
(AL MUZAIN GULF SAUDI CONTRACTING
COMPANY
Jubail Industrial City, Saudi
Work Method Statement
(BDH Valve Tray #44 - #07 and SVG Valve Tray #06-#01 and chimney
tray/collector tray/Vapour horn) for cleaning and inspection
DOC.NO.MZN-MED-WMS-041
Page 10 of
12
Sensitivity: MZN Internal
ALMUZAIN
(AL MUZAIN GULF SAUDI CONTRACTING
COMPANY
Jubail Industrial City, Saudi
Work Method Statement
DOC.NO.MZN-MED-WMS-041
Page 11 of
12
Sensitivity: MZN Internal
ALMUZAIN
(AL MUZAIN GULF SAUDI CONTRACTING
COMPANY
Jubail Industrial City, Saudi
Work Method Statement
10.0 HOUSEKEEPING
10.1 Maintain cleanliness and orderly stocking of materials & tools.
10.2 Pick up and dispose wastes & other debris prior to leaving site area.
10.3 Remove safety yellow tape or other warning devices that were used to
control access to Work area.
10.4 Store tools, equipment, and unused materials properly at the end of
the workday.