Ri Top Mep Schedule
Ri Top Mep Schedule
1 M&E RI & TOP SCHEDULE 284 days 21/10/21 8:00 ... 29/9/22 5:00 PM
2 Electrical Installation 221 days 25/10/21 8:00 ... 20/7/22 5:00 PM
3 SPPG Incoming Power Turn-on (ESS) 30 days 25/10/21 8:00 AM 29/11/21 5:00 PM
4 Outging Power Turn-on to Blk DBs 145 days 25/1/22 8:00 AM 20/7/22 5:00 PM
5 Block 1 (Upon L5 Archi & M&E Works Completion) 7 days 31/5/22 4:00 PM 8/6/22 4:00 PM
6 Block 2 (Upon L5 Archi & M&E Works Completion) 7 days 3/2/22 8:00 AM 10/2/22 5:00 PM
7 Block 3 (Upon L5 Archi & M&E Works Completion) 7 days 4/4/22 8:00 AM 11/4/22 5:00 PM
8 Block 4 (Upon L5 Archi & M&E Works Completion) 7 days 31/5/22 8:00 AM 7/6/22 5:00 PM
9 blk 5 37 days 31/1/22 8:00 AM 16/3/22 5:00 PM
10 Blk 4 & 12 Edec Casting 1 day 31/1/22 8:00 AM 31/1/22 5:00 PM
11 Cable tray Instalaltion 7 days 28/2/22 8:00 AM 7/3/22 5:00 PM 10FS+21 days
12 Cable works 7 days 8/3/22 8:00 AM 15/3/22 5:00 PM 11
13 Power Turn-on 1 day 16/3/22 8:00 AM 16/3/22 5:00 PM 12
14 Blk 6 - 12 145 days 25/1/22 8:00 AM 20/7/22 5:00 PM
15 Edec-4 Casting 1 day 25/1/22 8:00 AM 25/1/22 5:00 PM
16 Structure & Archi clearence 45 days 26/1/22 8:00 AM 21/3/22 5:00 PM 15
17 Cabl tray Installation 28 days 22/3/22 8:00 AM 23/4/22 5:00 PM 16
18 Blk 6 Cable works & Turn on 7 days 16/4/22 8:00 AM 23/4/22 5:00 PM 17SS+21 days
19 Blk 7 Cable works & Turn on 7 days 25/4/22 8:00 AM 4/5/22 5:00 PM 18
20 Blk 8 Cable works & Turn on 7 days 5/5/22 8:00 AM 12/5/22 5:00 PM 19
21 Blk 9 Cable works & Turn on 7 days 13/5/22 8:00 AM 21/5/22 5:00 PM 20
22 Blk 10 Cable works & Turn on 7 days 23/5/22 8:00 AM 30/5/22 5:00 PM 21
23 Blk 11 Cable works & Turn on 7 days 31/5/22 8:00 AM 7/6/22 5:00 PM 22
24 Blk 12 Cable works & Turn on (Last Blk) 7 days 8/6/22 8:00 AM 15/6/22 5:00 PM 23
25 SP Unit Testing 50 days 27/4/22 8:00 AM 27/6/22 5:00 PM 7FS+12 days
26 SP Meter Installation 42 days 17/5/22 8:00 AM 4/7/22 5:00 PM 25SS+14 days
27 SP Pre Turn-on 41 days 25/5/22 8:00 AM 12/7/22 5:00 PM 26SS+7 days
28 Obtain SP Completion Cert (For Last Blk) 7 days 13/7/22 8:00 AM 20/7/22 5:00 PM 27
29 ACMV Installation 95 days 2/4/22 8:00 AM 27/7/22 5:00 PM
30 Ductless System 65 days 2/4/22 8:00 AM 21/6/22 5:00 PM
31 Edec-6 Casting 1 day 2/4/22 8:00 AM 2/4/22 5:00 PM
32 Duct & Fan Installation 14 days 29/4/22 8:00 AM 18/5/22 5:00 PM 31FS+21 days
33 T&C 14 days 19/5/22 8:00 AM 3/6/22 5:00 PM 32
34 Jetfan RI Inspection 14 days 4/6/22 8:00 AM 20/6/22 5:00 PM 33
35 Jetfan RI Certification 1 day 21/6/22 8:00 AM 21/6/22 5:00 PM 34
36 Noise Measurement Report 45 days 4/6/22 8:00 AM 27/7/22 5:00 PM 33
37 Plumbing and Sanitary Installation 226 days 1/12/21 8:00 AM 1/9/22 5:00 PM
38 Sanitary Clearence 221 days 1/12/21 8:00 AM 26/8/22 5:00 PM
39 Ejector System Testing & Inspection 30 days 15/1/22 8:00 AM 21/2/22 5:00 PM
40 Last IC Connection to Sewer MH 30 days 1/12/21 8:00 AM 6/1/22 5:00 PM
41 Submission of Post CCTV Report for Sewer Line 30 days 7/1/22 8:00 AM 12/2/22 5:00 PM 40
42 Certificate of Completion (Form C) 29 days 1/6/22 8:00 AM 4/7/22 5:00 PM
43 Blk 1 & 4 Level 5 Unit Completion 1 day 1/6/22 8:00 AM 1/6/22 5:00 PM
44 T&C 14 days 2/6/22 8:00 AM 17/6/22 5:00 PM 43
45 Submission to PUB 14 days 18/6/22 8:00 AM 4/7/22 5:00 PM 44