Name Duration Start Finish Predecessors

1 M&E RI & TOP SCHEDULE 284 days 21/10/21 8:00 ... 29/9/22 5:00 PM
2 Electrical Installation 221 days 25/10/21 8:00 ... 20/7/22 5:00 PM
3 SPPG Incoming Power Turn-on (ESS) 30 days 25/10/21 8:00 AM 29/11/21 5:00 PM
4 Outging Power Turn-on to Blk DBs 145 days 25/1/22 8:00 AM 20/7/22 5:00 PM
5 Block 1 (Upon L5 Archi & M&E Works Completion) 7 days 31/5/22 4:00 PM 8/6/22 4:00 PM
6 Block 2 (Upon L5 Archi & M&E Works Completion) 7 days 3/2/22 8:00 AM 10/2/22 5:00 PM
7 Block 3 (Upon L5 Archi & M&E Works Completion) 7 days 4/4/22 8:00 AM 11/4/22 5:00 PM
8 Block 4 (Upon L5 Archi & M&E Works Completion) 7 days 31/5/22 8:00 AM 7/6/22 5:00 PM
9 blk 5 37 days 31/1/22 8:00 AM 16/3/22 5:00 PM
10 Blk 4 & 12 Edec Casting 1 day 31/1/22 8:00 AM 31/1/22 5:00 PM
11 Cable tray Instalaltion 7 days 28/2/22 8:00 AM 7/3/22 5:00 PM 10FS+21 days
12 Cable works 7 days 8/3/22 8:00 AM 15/3/22 5:00 PM 11
13 Power Turn-on 1 day 16/3/22 8:00 AM 16/3/22 5:00 PM 12
14 Blk 6 - 12 145 days 25/1/22 8:00 AM 20/7/22 5:00 PM
15 Edec-4 Casting 1 day 25/1/22 8:00 AM 25/1/22 5:00 PM
16 Structure & Archi clearence 45 days 26/1/22 8:00 AM 21/3/22 5:00 PM 15
17 Cabl tray Installation 28 days 22/3/22 8:00 AM 23/4/22 5:00 PM 16
18 Blk 6 Cable works & Turn on 7 days 16/4/22 8:00 AM 23/4/22 5:00 PM 17SS+21 days
19 Blk 7 Cable works & Turn on 7 days 25/4/22 8:00 AM 4/5/22 5:00 PM 18
20 Blk 8 Cable works & Turn on 7 days 5/5/22 8:00 AM 12/5/22 5:00 PM 19
21 Blk 9 Cable works & Turn on 7 days 13/5/22 8:00 AM 21/5/22 5:00 PM 20
22 Blk 10 Cable works & Turn on 7 days 23/5/22 8:00 AM 30/5/22 5:00 PM 21
23 Blk 11 Cable works & Turn on 7 days 31/5/22 8:00 AM 7/6/22 5:00 PM 22
24 Blk 12 Cable works & Turn on (Last Blk) 7 days 8/6/22 8:00 AM 15/6/22 5:00 PM 23
25 SP Unit Testing 50 days 27/4/22 8:00 AM 27/6/22 5:00 PM 7FS+12 days
26 SP Meter Installation 42 days 17/5/22 8:00 AM 4/7/22 5:00 PM 25SS+14 days
27 SP Pre Turn-on 41 days 25/5/22 8:00 AM 12/7/22 5:00 PM 26SS+7 days
28 Obtain SP Completion Cert (For Last Blk) 7 days 13/7/22 8:00 AM 20/7/22 5:00 PM 27
29 ACMV Installation 95 days 2/4/22 8:00 AM 27/7/22 5:00 PM
30 Ductless System 65 days 2/4/22 8:00 AM 21/6/22 5:00 PM
31 Edec-6 Casting 1 day 2/4/22 8:00 AM 2/4/22 5:00 PM
32 Duct & Fan Installation 14 days 29/4/22 8:00 AM 18/5/22 5:00 PM 31FS+21 days
33 T&C 14 days 19/5/22 8:00 AM 3/6/22 5:00 PM 32
34 Jetfan RI Inspection 14 days 4/6/22 8:00 AM 20/6/22 5:00 PM 33
35 Jetfan RI Certification 1 day 21/6/22 8:00 AM 21/6/22 5:00 PM 34
36 Noise Measurement Report 45 days 4/6/22 8:00 AM 27/7/22 5:00 PM 33
37 Plumbing and Sanitary Installation 226 days 1/12/21 8:00 AM 1/9/22 5:00 PM
38 Sanitary Clearence 221 days 1/12/21 8:00 AM 26/8/22 5:00 PM
39 Ejector System Testing & Inspection 30 days 15/1/22 8:00 AM 21/2/22 5:00 PM
40 Last IC Connection to Sewer MH 30 days 1/12/21 8:00 AM 6/1/22 5:00 PM
41 Submission of Post CCTV Report for Sewer Line 30 days 7/1/22 8:00 AM 12/2/22 5:00 PM 40
42 Certificate of Completion (Form C) 29 days 1/6/22 8:00 AM 4/7/22 5:00 PM
43 Blk 1 & 4 Level 5 Unit Completion 1 day 1/6/22 8:00 AM 1/6/22 5:00 PM
44 T&C 14 days 2/6/22 8:00 AM 17/6/22 5:00 PM 43
45 Submission to PUB 14 days 18/6/22 8:00 AM 4/7/22 5:00 PM 44

RI TOP MEP SCHEDULE - page1


Name Duration Start Finish Predecessors

46 PUB Sanitary Inspection 30 days 5/7/22 8:00 AM 10/8/22 5:00 PM 42


47 Saniatry Clearence 14 days 11/8/22 8:00 AM 26/8/22 5:00 PM 46
48 Plumbing Installation 79 days 31/5/22 8:00 AM 1/9/22 5:00 PM
49 Certificate of Satisfactory Completion 22 days 31/5/22 8:00 AM 24/6/22 5:00 PM
50 Blk 1 & 4 Level 5 Unit Completion 1 day 31/5/22 8:00 AM 31/5/22 5:00 PM
51 T&C 14 days 1/6/22 8:00 AM 16/6/22 5:00 PM 50
52 Submission to PUB 7 days 17/6/22 8:00 AM 24/6/22 5:00 PM 51
53 Bulk Water Meter & Water Turn-on 21 days 5/7/22 8:00 AM 29/7/22 5:00 PM 42
54 Water Sub-meters to Units 14 days 8/8/22 8:00 AM 24/8/22 5:00 PM 53FS+7 days
55 Water Serilization Report 14 days 17/8/22 8:00 AM 1/9/22 5:00 PM 53FS+14 days
56 Fire Protection Installation 79 days 31/5/22 8:00 AM 1/9/22 5:00 PM
57 Water Supply to Fire Tanks 7 days 30/7/22 8:00 AM 6/8/22 5:00 PM 53
58 Sprinkler, Hosereel & Hydrant T&C 21 days 8/8/22 8:00 AM 1/9/22 5:00 PM 57
59 Fire Alarm System 15 days 31/5/22 8:00 AM 16/6/22 5:00 PM
60 Blk 4 Roof Completion (incl: Heat Detectors) 1 day 31/5/22 8:00 AM 31/5/22 5:00 PM
61 T&C 14 days 1/6/22 8:00 AM 16/6/22 5:00 PM 60
62 Fire Hydrant T&C 7 days 8/8/22 8:00 AM 16/8/22 5:00 PM 57
63 Lift Installation 90 days 4/4/22 8:00 AM 22/7/22 5:00 PM
64 Blk 4 Lift Installation 59 days 17/4/22 8:00 AM 28/6/22 5:00 PM
65 Blk 4 Roof Stru Completion 1 day 17/4/22 8:00 AM 18/4/22 5:00 PM
66 Lift Installation 37 days 27/4/22 8:00 AM 11/6/22 5:00 PM 65FS+7 days
67 ID Works 7 days 13/6/22 8:00 AM 20/6/22 5:00 PM 66
68 T&C 7 days 21/6/22 8:00 AM 28/6/22 5:00 PM 67
69 Clubhouse Lift Installation (Last Lift) 76 days 4/4/22 8:00 AM 5/7/22 5:00 PM
70 Clubhouse Structure Works 24 days 4/4/22 8:00 AM 4/5/22 5:00 PM 31
71 Lift Installation 31 days 13/5/22 8:00 AM 18/6/22 5:00 PM 70FS+7 days
72 ID Works 7 days 20/6/22 8:00 AM 27/6/22 5:00 PM 71
73 T&C 7 days 28/6/22 8:00 AM 5/7/22 5:00 PM 72
74 Lift Homing Test 14 days 6/7/22 8:00 AM 22/7/22 5:00 PM 69
75 M&E RI Inspection 67 days 25/6/22 8:00 AM 13/9/22 5:00 PM
76 Submission of RI(M&E) Document & Certifcates 6 days 6/7/22 8:00 AM 13/7/22 5:00 PM 72FS+7 days
77 M&E Integrated System Testing 30 days 25/6/22 8:00 AM 30/7/22 5:00 PM 61FS+7 days
78 M&E Pre-RI Inspection 12 days 1/8/22 8:00 AM 15/8/22 5:00 PM 77
79 M&E RI Inspection 12 days 16/8/22 8:00 AM 29/8/22 5:00 PM 78
80 RI Certification 1 day 13/9/22 8:00 AM 13/9/22 5:00 PM 79FS+12 days
81 MDF/SCV/MDS Handover 195 days 21/10/21 8:00 ... 15/6/22 5:00 PM
82 MDF Room Handover 24 days 21/10/21 8:00 AM 18/11/21 5:00 PM
83 MSD Area Handover 6 days 3/3/22 8:00 AM 9/3/22 5:00 PM 10FS+24 days
84 TER & Cable Support Handover 18 days 5/5/22 8:00 AM 26/5/22 5:00 PM 17FS+7 days
85 Blk 4 Riser Handover (Last Block) 6 days 9/6/22 8:00 AM 15/6/22 5:00 PM 50FS+7 days
86 Gas Installation 96 days 8/6/22 8:00 AM 29/9/22 5:00 PM
87 Submission of X-Ray Report 12 days 8/6/22 8:00 AM 21/6/22 5:00 PM 50FS+6 days
88 In-house Inspection & Pressure Test Report 12 days 22/6/22 8:00 AM 5/7/22 5:00 PM 50FS+18 days
89 Submission of Document & Certificates 12 days 6/7/22 8:00 AM 20/7/22 5:00 PM 88
90 CityGas Inspection & Final Pressure Test 36 days 4/8/22 8:00 AM 15/9/22 5:00 PM 89FS+12 days

RI TOP MEP SCHEDULE - page2


Name Duration Start Finish Predecessors

91 PowerGas Turn-on 12 days 16/9/22 8:00 AM 29/9/22 5:00 PM 90