Professional Documents
Culture Documents
Lps-01-Hti-Mst-Me-022 - Chemical Dosing System
Lps-01-Hti-Mst-Me-022 - Chemical Dosing System
Document Title Method Statement for The Installation of Chemical Dosing System Date 01-NOV-2022
Document No. LPS-01-HTI-MST-ME-022 Rev. No. 0
Method Statement
For the Installation of CHEMICAL DOSING SYSTEM
Revision History
Issued for
Review and
LPS-01-HTI-MST-ME-022 0
Approval
Review by Approved by
Purpose of QA QC Manager Project Manager
Doc. no. Rev. no. Date Prepared by
submission
1|32
CONTENTS
1. PURPOSE…………………………………………………….………………………………………………………………………………………..3
2. SCOPE of Works………………………………………………………………………………………………………………………………………..3
3. REFERENCES………………………………………………………………………………………………………………………………………………3
4. ABBREVIATIONS………………………………………………………………………………………………………………………………………..3
5. RESOURCES……………………………………………………………………………………………………………………………………………….4
5.1 Equipment………………………………………………………………………………………………………………………………………….4
5.2 Manpower………………………………………………………………………………………………………………………………………….4
5.3 Material……………………………………………………………………………………………………………………………………………..4
6. RESPONSIBILITIES……..……………………………………………………………………………………………………………………………..5
6.1 Project Manager ………………………………………………………………………………....................................................5
6.2 Site Engineer/Supervisor………………..….……………………………………………………………………………………………….5
6.3 QA/QC Engineer …………………………………………………………………………………………………………………………………5
6.4 Safety Engineer/Officer ………………………………………………………………………................................................5
7. SEQUENCE OF ACTIVITIES……………………………………………………………….……………………………………………………5-7
8. QUALITY ASSURANCE/QUALITY CONTROL…………………………..…………………………………………………………………8
9. HSE ISSUES, RISK ASSESSMENT AND HAZARD ANALYSIS………………………….................................................8
9.1 Safety Lightings………………………………………………………………………………………………………………………………….8
9.2 Task Lightings…………………………………………………………………………………………………………………………………….8
9.3 Emergency Arrangement……………………………………………………………………………………………………………………8
10. ATTACHMENTS ……………………………………………………………………………………………………………………………………8
10.1 Risk Assessment……………………………………………………………………………………………………………………………9-23
10.2 Inspection Test Plan………………………………………………………………………………………………………………………24
10.3 Checklist for Chemical Dosing System……...….……………………………………………………………………………….32
2|32
1. PURPOSE
The purpose of this method statement is to describe the sequential approach for Installation of Chemical
Dosing System in accordance with the contract requirements. This method statement shall ensure that
the installation of Dosing Unit executed safely. This method statement aims to ensure that quality
assurance and quality control activities area adopted by Contractor M/s HexaTech in systematic manner
accordance with project requirements, works are inspected by the Project Consultant and conformance is
verified and documented.
2. SCOPE of WORKS
This method of statement describe:
Installation shall be carried out in accordance to the relevant Qatar Design Consortium,
Neo-Spectrum and HBK Judgments. The system shall be applied in accordance to manufacturer's
recommendation. Installation shall be carried out by qualified applicator trained and approved
by the manufacturer.
This method statement is subject to the requirements as stated in the following regulatory & statutory
documents, applicable standards / specifications / building codes:
Project Approved Shop Drawing
Approved Project Specification
Qatar Construction Specification 2014
3. REFERENCES
4. ABBREVIATIONS
3|32
4.1 Manpower
Project Engineer
QA/QC Engineer
Safety Engineer
Foreman
Pipe fitter
Electrician
Helper
4.2 Materials
Anchors
Identification label
Threaded rod and steel/channel support
Anchor bolt, Bolt, and Nuts
Chemical dosing accessories
Dosing tank
Dosing pump and controller
5 RESOURCES
Tools and Equipment
4|32
6 RESPONSIBILITIES
Project Manager: The Manager Leads and Directs the Projects team for overall development of the project.
Also, he provides single point of contact in dealing with the Employer resolving Contractual, Commercial and
Technical issues during the progress of the project for Mechanical works.
6.1. Site Engineer/ Supervisor: It is the Site Engineer / Site Supervisor’s duty to organize the work force in a
safe manner and to ensure that safety and protective equipment are being properly utilized. He also
ensures that the method statement procedure is strictly followed and observes any hold-points noted
on the ITP and notify the Engineer for inspection. They shall be responsible for safe execution of the
complete activity including, but not limited to.
a) Confirming the installation locations from schedule of approved construction drawings.
b) Organizing tools and equipment required to the work site
c) Assigning work crew.
d) Toolbox talks
6.2. QA/QC Engineer: It is the QA/QC Engineer & Inspector having the responsibility to ensure that all
Inspections and Tests are carried out as per Project Requirements, Shop drawings, Approved Method
statement and Inspection Test Plan and that all are properly recorded. They shall be responsible for.
Ensuring that approved work methods and materials are being used and in conformance with project
specifications.
Carryout periodic work inspection & testing along with client representative.
Stage inspections and surveillance in accordance with ITP.
6.3. Safety Engineer/ Officer:
Enforce the implementation of the HSE Management System in the project and support the relevant
construction Supervisors on all HSE matters;
Ensure that relevant HSE information and training is provided to all personnel working in the assigned
area;
Collaborate with Supervisors in assessing training needs for personnel in the assigned area;
Reports HSE findings to the relevant construction personnel as well as the HSE MANAGER, and follow up
the status of implementation of the identified preventive and corrective actions; Carry out any other
assigned HSE activity.
7. SEQUENCE OF ACTIVITIES
7.1. METHOD OF WORK
Coordinated drawings and the required material is arranged by the Project engineer as per
Project specifications. T h e c h e m i c a l d o s i n g s y s t e m will be installed by t h e specialist.
Before the start of the work make sure that all the HSE measures have been taken and obtain
all the necessary PPEs. If required, get a safe work permit from the HSE department.
Preparation & Pre-Installation Work
Works shall not proceed until an approved shop drawing or detail is issued.
After the approval of shop drawings, the site will be checked by the Project engineer.
Safe Access to work areas shall be provided and shall be approved by the competent person before
the commencement of works.
Materials shall be safely moved to the work area and shall not block access/egress from the site.
Where high-risk works are involved, a safety clearance must be obtained from the safety department.
5|32
Secure all the necessary permits before commencing work as well as for any connected works to
others.
Ensure that the installation of the Chemical dosing system is done as per the manufacturer’s
recommendation.
Electrical power connections shall be done as per approved drawings.
Electrical details like the Control panel and its control connections, and drawing shall be submitted for
approval.
Turn on the Chemical dosing Controller after connecting all the accessories & equipment.
Open the inlet valve and allow water to flow through the Flow Switch assembly.
Check the pH/Conductivity reading (as applicable) on the screen of the water treatment controller.
Cross check the readings with manual testing of water pocket pH/Conductivity meter.
Calibrate the Controller if it needs to be based on the reading.
Activate all the relays of the chemical dosing controller manually and ensure they are functioning
properly.
Setpoint for the chilled water system conductivity is 2000 us/cm.
The Corrosion Inhibitor of the dosing pump will be working when the conductivity is lower than 2000
us/cm.
Timer setting for Chilled Water Biocide will be once a month. (4 weeks Biocide Timer)
Fill the dosing tank with 50 liters of potable water.
Removed the discharge end and also make sure that the suction line is below the water level.
Start the chemical dosing pump by activating the controller relay manually.
Take the float switch out and make sure the relay is getting activated in case of low level.
Keep the system Operation in auto mode.
All local and network interfacing shall be tested for proper connection.
Provision of proper handling of water treatment chemicals to be observed with caution.
The testing & commissioning are to be offered for the Consultant’s approval.
7|32
Authorizing product delivery and project hand over to Client.
8.4. Measuring and Equipment Control
Testing and Measuring Equipment shall be calibrated and certified by approved third party facilities having
a standard traceable to “Qatar National Standard” Where no National Standards is available the basis
employed for calibration shall be in accordance to the international measuring standard.
Records shall be evaluated periodically to ascertain adequacy of inspection intervals presently in use. The
system designated to ensure all measurement resources have the capability of making measurements
within limit designated as appreciate to these requirements. It shall provide in the prevention of accuracy
by prompt detection of deficiencies and timely action for their correction.
All measuring test equipment and devices having an effect having an effect on quality shall be tag, sticker
or other suitable marking, indicating calibration status. Equipment and devices used for measuring, testing
and inspection shall require an initial inspection for accuracy, or shall be proven prior to release for use on
production.
All testing equipment shall maintain control log number and recorded in calibrations status report
electronically to monitor and reschedule for future calibration immediate the expiration date.
Project Team shall maintain Calibration Status logbook which provide pre-planned calibration frequency
for all applicable test and inspection equipment.
Project Team shall to ensure that each item of inspection, measuring and test equipment is calibrated as
per manufacturer’s recommendation. Valid calibration certificate for measuring and testing equipment
shall be present and available for inspection during inspection and test.
9.1. Safety Lightings: Safety lights will be used in case of power failure ensuring good illumination for the
personnel.
9.2. Task Lightings: Adequate lightings will be provided ensuring the good illumination of the working area.
Task lighting will be connected to the nearest site distribution board which is RCD protected.
9.3. Emergency Arrangements: Site general safety procedure will be followed. In case of emergency the
safety officer will stop the works. He will put in to action the emergency arrangements as described in
the safety manual.
10. ATTACHMENTS
10.1. Attachment 1 - Risk Assessment.
10.2. Inspection Test Plan (ITP) (Appendix1)
10.3. Checklist for Chemical Dosing Unit. (Appendix2)
8|32
Attachment1
9|32
Project Name: LPS01 - 2B+G+6 RESIDENTIAL BUILDINGS
Document Title Method Statement for The Installation of Chemical Dosing System Date 01-NOV-2022
Document No. LPS-01-HTI-MST-ME-022 Rev. No. 0
RA Description: Risk Assessment for Installation of Chemical Dosing System MST Ref. No.: LPS-01-HTI-MST-ME-022 Rev. No.: 0 Date: 01/11/2022
Note: Where the Hazard Rating remains High after control measures have been identified the work must not be
RISK / IMPACT ASSESSMENT
started and the HSE department contacted for further advice.
MATRIX
Where the Hazard Rating remains High after any additional control
HAZARD RATING measures have been identified the work must not be started and the
HSE department must be contacted for further advice.
Likelihood
Severity
Rating 15 – 25 High -H 3 – Likely 3 - > 3 days 3 – Minor impact 3 3 6 9 12 15
4 - Very likely 4 –Major Injuries 4 – Moderate impact 4 4 8 12 16 20
5 - Almost certain 5 – Fatal 5 – Major impact 5 5 10 15 20 25
Severity x Likelihood = Hazard Rating
Contractor
Assessed by: Reviewed by: Approved by:
Name: Name: Name:
Construction Project HSE Manager Project Manager
Signature: Signature: Signature:
10 | 3 2
Risk Rating Residual Rating
Item Activity Hazard & Risks Existing Control Additional Controls
S L RR S L RR
01 Unplanned movement of 2 3 6 Workers on foot should 1 2 2
Delivery and unloading of the vehicles. Provide a secure area for never be on the opposite
Chemical Dosing system Overturning the chemical dosing system side of a truck from a
and accessories. forklift while it is loading
Collision with pedestrians/
Unload the chemical dosing or unloading material.
operatives
assembly and its If multiple items or loads
Collision with structures that may shift are moved,
accessories strictly as per
Collision with other manufacturers' these must be properly
vehicles recommendations. secured with straps,
Overloading and falling Use mechanical aids where bands, or other means
objects possible. before work commences.
Falling of people Maintain control of loads Provision of fall
when lifting & moving. protection on top of the
Visiting drivers should be truck.
made aware of their Health All personnel on foot must
and Safety responsibilities; be clear of the loading
i.e., attend hbk induction zone during operations
and obtain a visitor pass Drivers should visually
before entry. inspect and secure any
Qualified, Competent, and truck or trailer and the
authorized mobile area around it before
equipment operator(s). moving it to assure all
Qualified, Competent, and workers are clear.
Authorized Rigger Regular maintenance
Trained, Competent, and occurs with all mobile
Authorized banksman equipment.
Valid 3rd party certificate Trained, Competent, and
for lifting equipment Authorized Supervision
Valid driving/Operating present always to ensure
License for the Operator. Operators are safely using
(Operator/Driver must have the plant as per its design
a valid Qatari Driving and conduct.
License.
Provide exclusion
zone(s) where the
activity is occurring.
Wheel chocks should
be used in addition to
the brake, particularly if
any slope is present.
Never be downhill of a
moving load. 11 | 32
02 Preparation of the activity Hazard such as: Arrangement and provision Provide suitable &
/General requirements / Site
Appendix 1
10.2. Inspection Test Plan (ITP)
12 | 32