3. The responsibility of EDD would cease at the outgoing terminals
of the 11 kV switchgear in the EDD intake substation. The
customer will be responsible for installation, operation and
maintenance of all equipment beyond this point., including the
interconnecting cable between EDD intake substation and the
customer’s switchroom.
130
receiving clearance from EDD authorities preferably in
conjunction with a properly authorised EDD engineer.
14. Supply to the customer will be connected only after his written
confirmation to abide by the above terms and conditions and by
the operational procedures for HV customers.