In cases of single customers with a maximum demand in
excess of 1.5 MVA, EDD shall provide an 11,000 Volt
incoming switchboard in a ring-main arrangement to be installed in the distribution sub-station. The customer shall provide his own 11,000 Volt switchboard, incorporating one or more incoming 11,000 Volt circuit breaker(s), on which the customer shall receive the electricity supply. The customer’s equipment shall be installed in a switch room immediately adjacent to the distribution substation of EDD with an interconnecting door lockable only from the distribution substation.
Where power supply is to be provided at 11 kV, customer(s)
shall comply with the requirements stated in the Appendix 6.
407 Distribution substation(s) within a development shall be
provided with vehicular access open over 24 hours per day. The clearance available in front of the door of the substation(s) shall be at least five metres. Orientation of the substation(s) shall be done in such a way that the door of the substation faces the road. In case this regulation can not be met entirely, customer shall seek the advice of EDD before commencing the construction.
All substations shall be constructed as per the approved EDD
drawings and regulations. Any deviation from the standard dimensions/ clearance around the substation shall be with the approval of EDD.
408 Wherever distribution substation(s) are provided within the
development, building or premises, ducts in adequate number and of not less than 150 mm in diameter, inspection chamber(s) and/ or manhole(s) to the requirements of EDD shall be provided to facilitate installation of cables for the connection of electricity to the development.
409 The electrical installation in every building or premises shall
be adequately controlled by a switchgear located adjacent to