You are on page 1of 1

FORMULA POLINÓMICA

OBRA :
SISTEMA ELECTRICO RURAL TAYABAMBA - HUANCASPATA V ETAPA

LÍNEAS PRIMARIAS
PRESUPUESTO BASE S/. 1,794,735.41
BASE (ENE 2021) Jul-22 Ago-22 Oct-22 Mar-23 May-23 Jul-23
SIMBOLO
Nº ELEMENTO REPRESENTATIVO INDICE SIMBOLO MONTO INCIDENCIA % PARCIAL COEF. INDICE COEF. INDICE COEF. INDICE COEF. INDICE COEF. INDICE COEF. INDICE COEF. INDICE
MONOMIO
1 POSTES DE MADERA TRATADA IMPORTADA 062 PM 94,154.25 0.052 67.21% 478.22 571.18 573.02 571.69 575.45 574.81 571.43
CRUCETAS DE MADERA 043 MN PM 11,593.25 0.006 8.28% 0.08 789.32 0.10 922.11 0.09 921.88 0.09 910.74 0.10 898.31 0.09 898.69 0.09 911.80
FERRETERIA PARA POSTES Y CRUCETAS 002 FP 34,346.28 0.019 24.52% 685.50 888.94 810.43 823.86 874.05 849.68 779.58
2 CONDUCTORES DE AAAC Y ACCESORIOS 030 DI DI 187,606.97 0.105 100.00% 0.10 550.38 0.13 674.44 0.13 669.37 0.13 688.55 0.13 662.85 0.12 652.49 0.12 640.97
3 EQUIPOS DE PROTECCIÓN 011 AE1 268,477.05 0.150 76.94% 265.88 283.11 280.13 289.07 273.89 270.14 263.08
AISLADORES Y ACCESORIOS 011 AE2 5,429.26 0.003 1.56% 265.88 283.11 280.13 289.07 273.89 270.14 263.08
RETENIDAS Y ANCLAJES 002 FE AE1 35,715.85 0.020 10.24% 0.19 685.50 0.22 888.94 0.22 810.43 0.22 823.86 0.22 874.05 0.21 849.68 0.20 779.58
CONDUCTOR DE COBRE Y ACCESORIOS 006 CU 27,844.91 0.016 7.98% 1162.29 1380.03 1339.97 1347.56 1388.98 1316.79 1268.33
MATERIAL PARA PUESTA A TIERRA 006 PT 11,479.47 0.006 3.29% 1162.29 1380.03 1339.97 1347.56 1388.98 1316.79 1268.33
4 MONTAJE ELECTROMECANICO 047 J 904,025.94 0.504 98.27% 633.53 650.44 650.44 702.10 704.78 704.78 704.78
J 0.513 0.53 0.53 0.57 0.57 0.57 0.57
TRANSPORTE 032 T 15,955.24 0.009 1.73% 490.89 526.28 526.28 533.81 539.86 539.86 547.75
5 GASTOS GENERALES Y UTILIDADES 039 GG GG 198,106.94 0.110 100.00% 0.110 473.17 0.12 526.99 0.12 530.50 0.13 535.12 0.13 551.82 0.13 556.66 0.13 557.98
1.000 1.095 1.086 1.137 1.139 1.130 1.118
K= 0.077 PMr/PMo + 0.105 DIr/DIo + 0.194 AEr/AEo+ 0.513 Jr/Jo + 0.11 GGr/GGo