Job Safety Analysis Form JSA-ALG-HAL-SL-005

JSA - Job/Process Description:


PSL/Support Function Location Date Completed / Revised Core JSA ID # Approver Minimum PPE Required Supervisor Conducting Toolbox Talk, JSA, Pre-Tour
Sub PSL Core JSA Version 5 Checks to GO - Printed Name Below
(Print Name) SAID ZEGHIDI

WPS MD 515 6/5/2023 N/A GAFSI MESSAOUD FULL OF PPE

If applicable - Person In Charge / Ultimate Work Authority (Print and Sign) N/A

5 Checks to GO
1 Check 1 Review any previously identified hazards (if prepopulated below), along with all work instructions such as DOS, procedures, checklists, etc. Verify Tasks are clear and understood, Confirm Communication methods such as
1

O Review Plan Radios / Hand Signals / Signage - Verify Competency and Operator Qualifications.

HAZARD CATEGORY Describe the specific source, what could go wrong to who or what,
Steps associated with the activity and the most likely consequence. Name of Person
What Control Will Prevent Incident?(Use the highest feasible level of control)Eliminate, Responsible
Substitute, Engineer,for Implementing
Admin, PPE Control
From 10 Key Hazards
(E.g., Chemical - Employee could be splashed with acid causing a chemical burn)

Ensure machinery gaurds or drum covers as per OEM are


installed on unit
Stored Energy : Hudraulic pressure inside, winch turing can cause finger or hand
Step 1: STORED ENERGY injury Do not stand in line of Fire
Spotting & function test of unit once CHEMICAL Chemical : Hydraulic hoses, PTO engagement can cause sudden release of pressure No personnel to engage hands or fingers in any moving parts SAID ZEGHIDI
Wear min required PPE on wellsite all times
reach location MACHINERY Machinery : Moving parts in unit, spooler moving can hit, Spooling wire /
Use ropes on the choke blocks to pull/push them insie the unit
unspooling wire can cause finger injury
tires
SWA if required and in unsafe situation

Do not stand below the red zone and mark the red zone area
with barricade/Caution tape.
Use SWA in case of anyone enter the area without
authorization.
Only certified crane operator to drive the crane.
Only certified banks man to give signals to the crane.
GRAVITY Gravity : Equipment or tools falling from the crane hook can hit someone, Personnel Ensure the crane is on flat area and land underneath is hard to
Step 2: EQUIPMENT injury, Swinging load can cause personnel injury ensure outriggers does not sink in ground SAID ZEGHIDI
Rigup Crane & Red Zone safety MACHINERY Equipment Machine Tools : Injury from handtools or crane movement to the Use of proper outriggers & base plate before lifting operations
TOOLS personnel begin
Ensure lift plan is done and crane operator is aware of the
heaviest lift.
Estimate the boom angle and maximum load during the rigup /
rigdown operations and ensure it does not exceed SWL of
crane boom.
Wear min required PPE on wellsite all times

Check the well head pressure on gauge and ensure pressure in


well is max 80% of working pressure of your PCE
Ensure proper scaffolding is used on location, IF customer to
provide scaffolding but Hal employee to check and ensure its
good condition.
Stored Energy : Pressure in well head trapped can hit the employee, Personnel
SWA in case of any doubts
Step 3: STORED ENERGY injury Bleed tree cap pressure safely and ensure no valves are leaking SAID ZEGHIDI
Prepare Well head Area & Tree cap GRAVITY Gravity : Falling objects from Xmas tree, or personnel fall down from scaffolding - or passing.
Personnel injury and equipment damange also possible Use finger saver tool if need to rigup flange and brass hammer
to avoid any sparks
SWA if required and in unsafe situation
SWA if required and in unsafe situation
Make sure to use proper PPE for the task

Revision 1
06-OCT-21
Job Safety Analysis Form JSA-ALG-HAL-SL-005

Ensure the lifting gear is certified and checked on location


before rigup
Visual inspection of lifting equipment.
All slings & shackles have tags & properly maintained
Ensure safety pins installed in all shackles prior to rigup
Use tag lines and push pull sticks, NO HANDS ON LOAD
Gravity : Falling objects from elevator or upper sheave while rigged up
Step 4: GRAVITY personnel fall down while rigging up - Personnel injury Plan the lift and lift path before picking up the lift
Rigup Sheave/WPCE & PCE String ERGONOMICS Slip and trip while passing over hoses if attention not paid - personnel injury Do not lift more than 27 kg manual lifting & more than 81kg for SAID ZEGHIDI
3 person lifting. Use mechanical aid if weight of tool/PCE above
this.
Ensure the crane operator is following only banksman signal.
Do not stand under red zone.
Do not stand in line of fire
Use wheel dolly while rigging up the PCE
Wear min required PPE on wellsite all times

Check the condition of hand tools before use


Be aware of dropped objects area and red zone (changing)
GRAVITY
Use lubricator entry guide to avoid any dropped object
EQUIPMENT Gravity : Falling objects or tools while making up can cause injury, Pinch points on
Vertical makeup tools MACHINERY the plate and between tools and other equipment can cause personnel injury. incident SAID ZEGHIDI
TOOLS Only 1 dedicated employee to give clear signals to winch man
Do not move the toolstring and crane at same time
Wear min required PPE on wellsite all times

Ensure PCE is certified as per HAL Standards & all O-rings are checked.
Setup bleed line or stuffing box to have no pressure to allow air to
escap.
Do not stand in line of fire of pressure manifold and bleed port.
Check the gauge condition and needle valves are good.
Stored Energy : Leaks from well pressure or lubricator pressure can cause injury to Increase the pressure gradually in 500 psi and hold for 5 mins before
personnel. proceeding to next pressure up to maximum working pressure or crack
Step 5: Personnel standing in line of fire open the well head Upper Master valve and see if there is any pressure
Pressure testing STORED ENERGY Improper bleed off procedure increase if not then crack open the lower master valve and let the SAID ZEGHIDI
Use of expired equipment on location can cause pressure test failure and SITHP stabilize in PCE string, confirm no leaks for 10 mins, if any leaks
personnel/equipment damages close the both master valves quickly and bleed the pressure thru bleed
port
SWA in case of any leaks and bleed to retify the lead
Do not hammer to loose or tight any connection under pressure.
Ensure bleed line is properly secured and away from wind/well head
area
Wear min required PPE on wellsite all times

Revision 1
06-OCT-21
Job Safety Analysis Form JSA-ALG-HAL-SL-005

Ensure the area is clearly barricated for the entire rigup lenght &
wire path upto SL unit
Follow winch operations speeds guidelines and use AA valve all the
times while POOH. Adjust AA valve every wrap as per winch FOM
Follow hand jarring guideline in case need to hand jar as per SL
operations FOM
EQUIPMENT Use tool catcher or tool trap (one of them at least in PCE stack)
Step 6:
MACHINERY Equipment : Personnel inury if cut on surface and and NPT due to fishing operation. Ensure wellhead is marked clearly with sign “DO NOT OPERATE”
SAID ZEGHIDI
RIH/POOH (Winch Operations) Do not excessive jar at same depth & if stuck SWA and consult
TOOLS town to change the position of wire in rigup by moving truck
position.
Ensure AMS is properly calibrated before RIH and tension alarms
and shutdown are set 200 lbs above normal slickline tension
during RIH/POOH
Catch the tool string in tool catcher while POOH
Wear min required PPE on wellsite all times

Check the condition of hand tools before use


GRAVITY Be aware of dropped objects area and red zone (changing)
Use lubricator entry guide to avoid any dropped object
Step 7: EQUIPMENT Gravity : Falling objects or tools while making up can cause injury, Pinch points on
Vertical Break makeup tools MACHINERY the plate and between tools and other equipment can cause personnel injury.
incident SAID ZEGHIDI
TOOLS Only 1 dedicated employee to give clear signals to winch man
Do not move the toolstring and crane at same time
Wear min required PPE on wellsite all times

Use tag lines and push pull sticks, NO HANDS ON LOAD


Plan the lift and lift path before picking up the lift
Do not lift more than 27 kg manual lifting & more than 81kg for
3 person lifting. Use mechanical aid if weight of tool/PCE above
Gravity : Falling objects from elevator or upper sheave while rigged up this.
Step 8: GRAVITY personnel fall down while rigging up - Personnel injury Ensure the crane operator is following only banksman signal.
SAID ZEGHIDI
Rigdown Sheave & PCE String ERGONOMICS Slip and trip while passing over hoses if attention not paid - personnel injury Do not stand under red zone.
Do not stand in line of fire
Use wheel dolly while rigging down the PCE
Ensure the toolstring is secured in tool catcher while rigging
down with enough slag on slickline to not break the line
Wear min required PPE on wellsite all times

“Walk the line” to ensure proper rig up, fluid movements, valve alignment, equipment set up, etc. Check equipment is certified, calibrated, in operable condition, safety guards in place, pre-run checks are complete. Ensure
1 good housekeeping practices, red zones, line of fire and drop zones are effectively implemented. Check for simultaneous operations. Will your work affect theirs, will their work affect yours?
Check 2
Verify Readiness

Revision 1
06-OCT-21
Job Safety Analysis Form JSA-ALG-HAL-SL-005

1 Check 3 Ask team members open-ended questions regarding the plan, roles and responsibilities using the 10 Key Hazards list. Use the section below to document hazards that can't be immediately eliminated. Identify specific hazard,
“What’s Different?” control and the individual responsible for ensuring each control is implemented.

10 KEY HAZARDS - BIOLOGICAL CHEMICAL ELECTRICAL EQUIPMENT/MACHINERY/TOOLS GRAVITY MUSCULAR ERGONOMICS NOISE RADIATION STORED ENERGY THERMAL

HAZARD CATEGORY Describe the specific source, what could go wrong to who or what,
Steps associated with the activity and the most likely consequence. Name of Person
What Control Will Prevent Incident?(Use the highest feasible level of control)Eliminate, Responsible
Substitute, Engineer,for Implementing
Admin, PPE Control
From 10 Key Hazards
(E.g., Chemical - Employee could be splashed with acid causing a chemical burn)

Check the well head pressure on gauge and ensure pressure in well is max 80% of
working pressure of your PCE
REATCH INTO METAL BOX TO RIGHT OF MACHINE
GRASP CASTING AND CARRY TO WHEEL
GRAVITY Lifting equipment in bad candition Ensure proper scaffolding is used on location, IF customer to provide scaffolding but Hal SAID ZEGHIDI
employee to check and ensure its good condition.
SWA in

PSL/Support Function EQUIPMENT


Sub PSL MACHINERY Equipment : Personnel inury if cut on surface and and NPT due to fishing operation. equipment or tools lifting from the crane hook can hit somone,personnel injury SAID ZEGHIDI
TOOLS

PLEACE FINSHED CASTING IN BOX TO LEFT OF MACHINE MUSCULAR AND ERGANANIES pressure in well head trepped can hit the employeer pressure in well head trapped can hit emploiyee ,personnel injury SAID ZEGHIDI

Check 4
1 Validate Controls
Verify all controls are in place according to Core JSA or JSA and validate their effectiveness. Confirm escape routes and ask team members "where will you go or what will you do if something goes wrong?"

Signature SAID ZEGHIDI


Check 5 Are all contingencies in place? Final walk the line. 100% ready to go? Team Lead/Supervisor approval and signature required prior to starting
1 Final Check work.
After Action Review / Additional Discussion Points or Notes

N/A

JSA Participant - Print Name What's Your Role? Company Name I have read and understood the risks and controls listed above - (Signature)

HES
Zeghid said performer

HES
GHOUL MOHAMED reviewer

HES
NOUACER MOUSSA member

Revision 1