REV 03 - 20052021 1 Level 1 Schedule 08-Jun-21 12:09

Activity ID Activity Name Original Start Finish Duration % Total 2017 2018 2019 2020 2021 2022 2023 2024 2025
Duration Complete Float

REV 03 - 20052021 2813 16-May-12 A 29-Jul-21 97.85% -1123

CONTRACTUAL MILESTONES 2813 16-May-12 A 29-Jul-21 97.85% -1123

PRELIMENARIES 2065 16-May-12 A 17-Jun-21 98.99% -906

GOVERNMENT APPROVALS / PERMITS 1954 02-Oct-13 A 30-Jun-21 99.69% -914

COMMON ITEMS 2658 16-May-12 A 23-May-21 99.89% -1066

SOUTH CAMPUS 2199 21-Apr-14 A 30-Jun-21 98.38% -1100

NORTH CAMPUS 2495 23-Jun-14 A 29-Jul-21 97.58% -1220

Actual Work Critical Remaining Work Page 1 of 1 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation