Professional Documents
Culture Documents
Spoiled Units
• units that do not meet production standards and are either sold for their salvage value or
discarded
• when spoiled units are discovered, they are taken out of production and no further work is
performed on them
Defective Units
• units that do not meet production standards and must be processed further in order to be
salable as good units or as irregulars
Scrap Materials
• left over from the production process that cannot be put back into production for the same
purpose, but may be usable for a different purpose or production process or which may be sold
to outsiders for a nominal amount
Waste Materials
• left over from the production process that has no further use or resale value and may require
cost for their disposal
TWO (2) METHODS OF ACCOUNTING FOR SPOILAGE
Illustration:
Job 3044 called for the making of 4,000 with these unit costs:
When the order was completed, 200 rejected units, a normal number, were sold for Php 18.00
each.
Under this method, the MOH was recorded at the original amount of Php 11 (the Php 1 allowance
for spoilage was not included). The remaining perfect units in the job will absorb the loss on the
spoilage, resulting in an increase in unit cost.
The loss on spoiled goods will be absorbed by the remaining good units.
o used if the reason for the spoilage is considered normal to the process and the number
does not exceed the limit set by the company
o With this method, all units manufactured during the period are charged with additional
cost which is added to the MOH rate.
o The unit cost originally charged will not increase anymore even if there are spoiled units
discovered later on.
o The amount debited to spoiled goods is equal to the number of units spoiled multiplied
by the estimated sales value per unit.
o The amount credited to work in process is equal to the total costs incurred/charged to
the spoiled units.
o If the number of units spoiled exceed the limit set by the company, or if the reason is
not considered normal to the process, the loss on the spoiled units is charged to a loss
account.
Illustration:
Job 3044 called for the making of 4,000 with these unit costs:
Direct materials Php 15.00
Direct labor 13.00
MOH (includes Php 1.00 spoilage allowance) 12.00
Total Php 40.00
When the order was completed, 200 rejected units, a normal number were sold for Php
18.00 each.
Under this method, the unit cost of the completed units remains at Php 40.00. Because
the increase was made at the start (Php 1.00 spoilage allowance in MOH).
All units processed during the period, even those jobs without spoiled units, will absorb
the additional Php 1.00.
Upon completion of the job, even if there were spoiled units, the unit cost will be the
same as the amount originally charged to the job.
TWO (2) METHODS OF ACCOUNTING FOR DEFECTS
• The accounting problem for defective units is the additional costs to be incurred in reprocessing
the units to convert them into perfect articles.
o Same for spoiled units, if the reason for the defect is the job itself, the additional costs
incurred will be charged to all units in the job.
Illustration:
Job 3044 called for the making of 4,000 with these unit costs:
Direct materials Php 15.00
Direct labor 13.00
MOH (includes Php 1.00 defects allowance) 12.00
Total Php 40.00
During processing 300 units were found to be defective and required the following total
additional costs: materials – Php 2,000; labor – Php 4,000; and overhead – Php 2,000.
The unit cost of the completed units increased from the original Php 39 to Php 41 (Php
164,000 / 4,000 units). All units in the job will share in the cost incurred to re-process the
defective units.
2. Charged to all production
o If the reason is normal to the process and the number of defective units do not exceed
the normal limit, then the additional costs incurred will be charged to all units being
processed during the period.
Illustration:
Job 3044 called for the making of 4,000 with these unit costs:
Direct materials Php 15.00
Direct labor 13.00
MOH (includes Php 1.00 defects allowance) 12.00
Total Php 40.00
During processing 300 units were found to be defective and required the following total
additional costs: materials – Php 2,000; labor – Php 4,000; and overhead – Php 2,000.
The cost of the finished goods will remain at the original amount charged to the job
(Php 160,000 / 4,000 units = Php 40 / unit).
ACCOUNTING FOR SCRAPS
• The cost of disposing waste materials may be allocated either to all jobs or to specific jobs.