1. First step is creating a Project in Company code 3000 in ST1 environment with project profile
Z000001. 6/V83 is successfully created by tcode CJ01
c
Sender details
Receiver debit details
falta
TEST CASE 2 ST1
B Crear activo final y ver que se realiza el traspaso de saldo de activo en curso a activo final
C Comprobar que se puede liquidar contra activo en curso una parte y otra parte contra activo final
cuando el wbs tiene dos reglas de liquidación.
1. CREATE PROJECT
6/v85
The automatic pop for asset under construction creating does not launch automatically, despite AuC has
been created.
Settlement rules automatically created when running CJ88 for allocating cost from WBS to AuC.
2. Creating final asset for later balance transfer from AuC to Final asset.
Settlement rule 21000000 settle from wbs to Auc 21000000 when executing cj88
FXA category settlement receiver 21300018 settles from wbs to Asset AuC 21300018 when executing
cj88.
Creating final fixed asset with this parameters
Transfer from AuC to Final fixed Asset by tcode ABUMN
Final asset setting up
Setting up of settlement rule from auc to final fixed asset