Method Statement For Drainage System
4. The drain shall be laid on 100mm thk compacted sands to the proper
falls and joined straight true to lines and levels. The joints shall be
cement grouted.
CASCADE DRAIN
1. Excavation for cascading drain shall be carried out to the dimensions
as shown in the drawing.
1. Excavation for pipe culvert shall be carried out to the dimensions and
size as shown in the drawing complete with strutting and formwork.
2. To lay and compact hardcore for bedding and to lay 50mm thc lean
concrete.
3. To lay 150mm thc concrete bedding, the pipes shall than be laid with
ends true to lines and gradient.
4. The annular gap shall be filled with cement sand mortar (1:3) with
sufficient water added to ensure adequate workability.
3. Box culvert shall be laid as close as possible and the maximum gap in
between shall not be more than 20mm and the difference in level not
more than 5mm.
4. The gap shall be filled with cement mortar (1:3) and finished smooth.
To ensure uniform bearing, a layer of cement grout shall be spread
along the top of the walls to the invert where the lid will sit.
5. To construct 150mm thc wing wall, compact base with hardcore lay
lean concrete, concrete base with reinforcement , starter bar to wall,
formwork, install 50dia pvc pipe for weephole and place in vibrated
G30 concrete for wall.