Professional Documents
Culture Documents
Industrial Economics
Dr. SYED IMRAN ALI “The study of how people & society choose to employ
scarce resources that could have alternative uses in order to
produce various commodities and to distribute them for
consumption, now or in the future”
Department of Applied Chemistry & Chemical (Taken from Economics, 12th Ed., McGraw-Hill, New York, 1985)
Technology, University of Karachi
2
1
WHY STUDY ECONOMICS? WHAT YOU WILL LEARN?
Industrial activities are aim to gain Profits Course Outcomes
This section of the course has following broad outcomes
For successful operations, Economics plays a key role
Economic analysis of chemical processes with emphasis on:
Theoretical & practical aspects are important, but the fate of a
Cost estimation (capital, production costs etc.)
process, design or project is determine by its Profitability
Time value of money
Evaluation of design changes, procurement, project
alternatives, costing etc. all based on Economic Principles Depreciation
5
Selecting among alternatives (decision making)
2
Why Cost Estimation? Cost Estimation....
3
Components of Capital Cost…. FCC Components of Capital Cost…. FCC
2. Boilers & steam infrastructure, BFW treatment plant 9. Labs, offices, canteens, changing rooms, control rooms
3. Cooling towers, pumps, piping's, cooling water treatment 10. Workshops & maintenance facilities
4. Water pipes, water demineralization, wastewater treatment 11. Emergency services, firefighting setup, medical facility
plant, site drainage system
12. Site security, fencing, gatehouses, and landscaping.
15 16
4
Components of Capital Cost…. FCC Components of Capital Cost…. FCC
OSBL….
c) Engineering Costs
NOTE:
Engineering costs are best estimated on project scope basis:
Offsite costs are in the range from 10 to 100% of ISBL 10% of (ISBL + OSBL) for large projects
19 20
We will discussed Working Capital in more detail latter
5
Components of Capital Cost…. Components of Capital Cost…. Lets Summarize…
Land costs can be obtained from real estate market ISBL OSBL Engineering & Contingency
Construction
For initial estimates, about 3% of FCC may be used
Delivered Equipment Utilities Engineering & Supervision
Equipment Installation Storage Construction
Electrical Work Service Facilities Contractor Fee
Instrumentation, Controls Waste Treatment Administrative & Overheads
Piping Yard Improvement Project Contingency
Insulation, Painting etc. etc.
etc.
We will discussed Lang Cost in more detail latter
21 22
Production cost is of two types: Variable & Fixed Variable Costs of Production….
Costs that vary with production volume. Include: e. Packaging and shipping (drums, bags, tankers, freight
charges)
a. Raw materials
Fixed Costs of Production
b. Utilities (fuel, steam, water, electricity, air, N2 & other
services brought in from elsewhere on the site) Costs that do not change with the production volume
6
Costs of Production… Costs of Production…
27 28
Gross profit = Main Product Revenue - CCOP
7
Revenues, Margins, and Profits…
ESTIMATING CAPITAL COSTS
Profits…
Profit is usually subject to taxation
Estimate is an Estimate!!!
29 30
A project is:
Estimated cost is the probable cost computed based on plans &
specifications Economically feasible if it is more profitable than
competing projects
Good estimate should be within 5-10 % of actual cost
Financially feasible if sufficient funds are available
Requires engineering knowledge, cost data, experience, Even a profitable project may be abandoned due to financial
foresight and judgment constraints
31 32
8
Estimating Capital Costs… Estimating Capital Costs…
Economic evaluation projects proceeds in several steps: Types of Capital Cost Estimates
1. Preparing a process flow diagram Depending on project stage and
availability of information, estimates
2. Calculating mass & energy flows Engineering
of various accuracies can be
3. Sizing major equipment prepared
6. Forecasting product sales price For early stages. only an approximate estimate is sufficient
Economic
7. Estimating return on investment Evaluation
33 34
Association for Advancement of Cost Engineering (AACE) Based on accuracy & purpose there are 05 types of estimates:
gives 05 major classes:
1. Order of Magnitude Estimate (OoM)
1. Order of Magnitude Estimate (CLASS 5) (ratio, predesign, ballpark, guesstimate, or class 5 estimate)
2. Study Estimate (CLASS 4) Based on costs estimates of similar processes
3. Preliminary Estimate (CLASS 3) Not much design details required, BFD sufficient
4. Definitive estimate (CLASS 2) Accuracy = ± 30–50%
5. Detailed Estimate (CLASS 1) Used for initial feasibility studies & screening purposes
9
Estimating Capital Costs… Estimating Capital Costs…
(approximate, feasibility, factored or class 4 estimate) (budget authorization, scope, definitive, control, class 3 estimate)
Based on limited cost data Based on sufficient data to permit budgeting of estimate
List of major equipment, PFD needed (accurate equipment sizes, layout, piping,
instrumentation & electrical requirements, PFD &
Accuracy typically ± 30%
preliminary PI&D)
Used to make coarse choices b/w design alternatives
probable accuracy: ± 20 %
37 38
(project control, class 2 estimate) (contractor’s, Check, tender, as-bid, Class 1 estimate)
Need completed or near complete process design, Based on complete engineering drawings of the
correct equipment cost, and detailed breakdown of process and all related off-sites and utilities,
estimated construction cost. specifications, site surveys, completed negotiations on
Final PFD & preliminary PI&D procurement
Probable accuracy: ± 5 %
39 40
10
Estimating Capital Costs… Estimating Capital Costs…
43 44
11
Estimating Capital Costs… Equipment Cost Data… Estimating Capital Costs… Equipment Cost Data…
Different types of auxiliary equipment & materials (insulation, It is thus essential to have reliable equipment cost data
ducts) should also be included
Engineer need good judgment in selection and use of cost
data
45 46
Estimating Capital Costs… Equipment Cost Data… Estimating Capital Costs… Equipment Cost Data…
Handling the Cost Data: Important Points Handling the Cost Data: Important Points…..
It is essential for the estimator to know: Most data include its date
Data source of cost data
For textbook data, deduct 2 years from publication date
Basis of data
Date Data > 10 years should be avoided
47 48
12
Estimating Capital Costs… Equipment Cost Data… Estimating Capital Costs… Equipment Cost Data…
Handling the Cost Data: Important Points….. Where to Find Equipment Cost Data??
Equipment Cost data often stated as:
PURCHASED COST: Price of equipment FOB (free on
board) at manufacturer’s plant
INSTALLED COST: Total cost incurred when an equipment is Equipment cost can be determine from:
purchased, delivered, uncrated & placed on foundation Vendor Quote:
Most accurate
Does not include piping, electrical, insulation costs
Based on specific information
A more accurate term is set-in-place cost Requires significant engineering
49 50
Estimating Capital Costs… Equipment Cost Data… Estimating Capital Costs… Equipment Cost Data…
Where can we find cost data…. Correcting Past Equipment Cost for Inflation
Past Cost of Similar Equipment & Correct for Time & Size:
COST INDEXES:
Less accurate Past costs are adjusted to time using Cost Index (C.I)
Beware of large extrapolation CIs are dimensionless numbers assigned to each year based
Beware of foreign currency on changes in value of money due to inflation or deflation
Use Cost Estimating Charts & Scale for Time: If cost at some time is known, cost at another time can be
obtained as:
Reasonably accurate
𝑪. 𝑰 𝒐𝒇 𝒀𝒆𝒂𝒓𝟐
Convenient 𝑪𝒐𝒔𝒕 𝒂𝒕 𝒀𝒆𝒂𝒓𝟐 = 𝑪𝒐𝒔𝒕 𝒂𝒕 𝒀𝒆𝒂𝒓𝟏
𝑪. 𝑰 𝒐𝒇 𝒀𝒆𝒂𝒓𝟏
51 52
13
Estimating Capital Costs… Equipment Cost Data… Estimating Capital Costs… Equipment Cost Data…
COST INDEXES…
53
Cost Indexes…
56
14
Estimating Capital Costs… Equipment Cost Data… Estimating Capital Costs… Equipment Cost Data…
Index Value
Separate indices should be used for labor and materials
Estimating Capital Costs… Equipment Cost Data… Estimating Capital Costs… Equipment Cost Data…
EXAMPLE: EXAMPLE:
15
Estimating Capital Costs… Equipment Cost Data… Estimating Capital Costs… Equipment Cost Data…
where f‘, f’’, f ‘’’ are inflation rates for three consecutive years.
Estimating Capital Costs… Equipment Cost Data… Estimating Capital Costs… Equipment Cost Data…
EXAMPLE: EXAMPLE:
Cost of a vessel in 1993 was 25,000, what is the estimated cost
on Sept 2003?
SOLUTION
16
Estimating Capital Costs… Equipment Cost Data… Order of Magnitude Estimates (OOM)
EXAMPLE: Estimation of fixed-capital investment using Simplest but least accurate
ranges of process-plant component costs. Make a study
estimate of the fixed-capital investment for a process plant if the Only initial design concept or idea needed
purchased-equipment cost is $100,000. Use the ranges of
What would be the cost of a 50,000 ton
process-plant component cost outlined in Table 4 for a process
per year acetic acid plant?
plant handling both solids and fluids with a high degree of
automatic controls and essentially outdoor operation.
No engineering done, only idea of
project exists
EXAMPLE 1 from Max S. Peters & Klaus D. Timmerhaus,
Chapter 6 There are many OOM methods
65
Estimating Capital Costs… OOM Estimates…. Estimating Capital Costs… OOM Estimates….
𝒏
1) ESTIMATING COSTS BY SCALING Can also be written as: 𝑪𝟐 𝑺𝟐
=
Very useful relationships in cost engineering 𝑪𝟏 𝑺𝟏
Where C1 , C2 are base and required costs, S1 , S2 are their
Log-log plot cost vs capacity of items with
capacities, n is the cost exponent. Rearranging gives:
same features is straight line:
𝑪𝟏 𝑪𝟏
𝒏 𝑪𝟐 = 𝑺𝒏 where = Constant = a
𝑪𝒐𝒔𝒕𝒔𝒊𝒛𝒆 𝟐 𝑪𝒂𝒑𝒂𝒄𝒊𝒕𝒚𝒔𝒊𝒛𝒆 𝟐 𝑺𝟏𝒏 𝟐 𝑺𝟏𝒏
= (Eq. 1)
𝑪𝒐𝒔𝒕𝒔𝒊𝒛𝒆 𝟏 𝑪𝒂𝒑𝒂𝒄𝒊𝒕𝒚𝒔𝒊𝒛𝒆 𝟏
Log Cost
𝑪𝟐 = 𝒂 𝑺𝟐𝒏
(COST CAPACITY
Where n is the size exponent RELATION) Taking log: 𝒍𝒐𝒈𝑪𝟐 = 𝒏𝒍𝒐𝒈𝑺𝟐 + 𝒍𝒐𝒈𝒂
Log Capacity
Cost-capacity relation is used for OOM estimate of equipment
log-log plot of capacity vs equipment cost for a given type of
cost using known cost of a similar equipment of different size
equipment
68 should be a straight line with a slope equal to n
17
Estimating Capital Costs… OOM Estimates…. Estimating Capital Costs… OOM Estimates….
Plot of Cost-Capacity Data for Heat Exchanger Cost-Capacity Relation: Important Points
Max S. Valid for equipment, plant and processes
Peters &
Estimating Capital Costs… OOM Estimates…. Estimating Capital Costs… OOM Estimates….
EXAMPLE: Recently a cast iron pressure filter with 100 ft2 was
EXAMPLE: If a 100-ton per year plant cost $32.9M, what would
purchased for clarifying an inorganic liquid stream for $15,000.
a 150-ton per year plant cost?
In a similar application, the company will need a 450 ft2 cast iron
SOLUTION: As size exponent is not known, we use 0.67 leaf pressure filter. The size exponent for this type filter is 0.6.
Estimate the purchased price of the 450 ft2 unit.
SOLUTION:
18
Estimating Capital Costs… OOM Estimates…. Estimating Capital Costs… OOM Estimates….
Estimating Capital Costs… OOM Estimates…. Estimating Capital Costs… OOM Estimates….
Solution:
19
Estimating Capital Costs… OOM Estimates….
Estimating Capital Costs… OOM Estimates…. Estimating Capital Costs… OOM Estimates….
79 80
20
Estimating Capital Costs… OOM Estimates…. Estimating Capital Costs… OOM Estimates….
SOLUTION: First Bring Costs to a Common Time: Applying the power law,
𝑪𝒂 𝑺𝒂 𝒏
For A= 70 m2, =
𝑪𝒃 𝑺𝒃
𝒏
𝑺𝒂
For A= 130 m2, 𝑪𝒂 = 𝑪𝒃
𝑺𝒃
𝟎.𝟒𝟓𝟔𝟓
𝟖𝟎
Using these two points, we can calculate value of exponent n, 𝑪𝒂 = 𝟏𝟗. 𝟎𝟖𝟗
𝟕𝟎
𝑪𝒂 = $ 𝟐𝟎. 𝟐𝟖𝟖 𝑲
81 82
Estimating Capital Costs… OOM Estimates…. Estimating Capital Costs… OOM Estimates….
Extending Cost-Capacity Relation for Chemical Plants Cost-Capacity Relation for Chemical Plants: Important Points
Capital Cost of a chemical plant can be obtained by scaling For chemical plants, n vary from < 0.2 to >1
from a known cost of an earlier plant with same technology
n is typically:
No design info except production rate
0.8-0.9 for plants with lot of mechanical work or gas
𝒏 compression (methanol, pulp & paper, solid-handling)
𝑺𝟐
𝑪𝟐 = 𝑪𝟏 ~ 0.7 for typical petrochemical processes
𝑺𝟏
0.4-0.5 for small-scale, highly instrumented processes
Where,
C2 = ISBL capital cost of plant with capacity S2 Averaged value of 0.7 is often used (‘‘Seventeenths Rule’’)
C1 = ISBL capital cost of plant with capacity S1 For many known processes, values of n are tabulated
83 84
21
Estimating Capital Costs… OOM Estimates…. Estimating Capital Costs… OOM Estimates….
Estimating Capital Costs… OOM Estimates…. Estimating Capital Costs… OOM Estimates….
𝑪𝟏 𝑪𝟏
𝑪𝟐 = 𝑺 𝒏 = Constant = a
𝑺𝟏 𝒏 𝟐 𝑺𝟏 𝒏
𝑪𝟐 = 𝒂 𝑺𝟐𝒏
These values may be used if sufficient data are unavailable Values of a and n for many processes are tabulated in literature
If sufficient data available used, find n from plot 88
22
Values of a and n Values of a and n
89 90
91 92
23
Values of a and n Values of a and n
93 94
Estimating Capital Costs… OOM Estimates…. Estimating Capital Costs… OOM Estimates….
2) STEP COUNT METHOD Where, C = ISBL capital cost in $, U.S. Gulf Coast, 2000 basis;
If cost of similar process is not available, an alternative Q = Plant capacity (metric tons/year)
approach is Bridgewater’s method S = Reactor conversion (mass of product/mass of feed)
It correlates plant cost with the number of processing steps N = Number of functional units.
NOTE:
For plants primarily processing liquids and solids:
Functional unit includes all equipment & ancillaries needed for
a significant process step (major unit operation/process such as
reaction, separation etc.)
24
Estimating Capital Costs… OOM Estimates…. Estimating Capital Costs… OOM Estimates….
This equation can be used for very approximate estimate of EXAMPLE 6.1 from,
CHEMICAL ENGINEERING DESIGN, Principles, Practice and Economics of
plant cost if fixed costs and utilities can be estimated Plant and Process Design,
By GAVIN TOWLER and RAY SINNOTT
97 98
Estimating Capital Costs… OOM Estimates…. Estimating Capital Costs… OOM Estimates….
99 100
25
Estimating Capital Costs… OOM Estimates…. Estimating Capital Costs… OOM Estimates….
Bridgewater’s method is a rough approximation and cost Turnover ratio is defined as:
correlations data of Table 6.2 is from technology vendors
which is somewhat understated. 𝑨𝒏𝒏𝒖𝒂𝒍 𝑮𝒓𝒐𝒔𝒔 𝑺𝒂𝒍𝒆𝒔
𝑻𝒖𝒓𝒏𝒐𝒗𝒆𝒓 𝑹𝒂𝒕𝒊𝒐 𝑻𝑶𝑹 =
𝑭𝒊𝒙𝒆𝒅 𝑪𝒂𝒑𝒊𝒕𝒂𝒏 𝑰𝒏𝒗𝒆𝒔𝒕𝒎𝒆𝒏𝒕
The costs are not on the same time basis
With the level of information available, it is better to say that Annual gross sales=Annual production rate x price per unit
the estimated cost is in the range $10MM to $20MM.
Basic Assumption = ALL PRODUCT MADE IS SOLD
101 102
Estimating Capital Costs… OOM Estimates…. Estimating Capital Costs… OOM Estimates….
Value of TOR:
TOR vary from 0.2 to 5.0
26
Estimating Capital Costs… OOM Estimates…. Estimating Capital Costs… OOM Estimates….
Estimating Capital Costs… OOM Estimates…. Estimating Capital Costs… OOM Estimates….
EXAMPLE: You read recently in a trade journal that FFC, a EXAMPLE: The purchased price of glass–lined vessels with
competitor of your company in the fertilizer business, plans a agitator, baffle, and thermwell is as follows:
$20MM expansion of their existing urea facilities. The article did
not mention how much this expansion would increase production.
Your supervisor asks you to estimate the increase in annual
production assuming that urea is selling for $0.05/lb.
27
Estimating Capital Costs… OOM Estimates…. Study Estimates
Order of Magnitude Methods: Concluding Remarks Accuracy 30%
Several OOM methods
Some design info needed
available
(much more than OOM
Based on assumptions, estimates!)
thus not very accurate.
At a minimum, we need,
Useful in a pre-design
Block flow diagrams
stage
Preliminary material & energy balance
A better approach is to calculate/collect some more data and
go for “Study Estimate”.
Environmental risk review
110
Estimating Capital Costs… Study Estimates…. Estimating Capital Costs… Study Estimates….
Preliminary material & energy balances Main assumption: If cost of major equipment is known, all
other costs can be estimated as its Factors
Block flow diagrams/flow sheets
Very simple approach:
Rough sizes & specifications of major equipment
1. Purchase Costs of equipment are estimated using their
Rough utilities & packaging requirements specifications
Rough sizes of buildings & structures 2. Purchase Costs are then multiplied by appropriate factors
to incorporate all other expanses
Environmental assessment & equipment
111 112
28
Estimating Capital Costs… Study Estimates…. Estimating Capital Costs… Study Estimates….
113
DIRECT COSTS
Purchase, Calibration, Installation Instrumentation
DELIVERED EQUIPMENT
Process piping, Pipe Hangers, Fittings, Valves, Insulation Piping
+ Equipment placing
Electrical Equipment, Materials, Installation Electrical
+ Piping & connections ISBL
Direct & Process Buildings, Maintenance Shops, Buildings for Services,
+ Electrical equipment & wiring Indirect Warehouses, Garages, Steel Structures, Labs, Medical, Cafeteria
Buildings
+ Instrumentation & controls Costs Utilities, Waste Treatment, Receiving, Shipping, Packaging, Storage,
Auxiliary Facilities
Lighting, Communications
FCC + Buildings
OSBL Administration, Process Design, General Engineering, Cost
INDIRECT COSTS
29
THE PROCESS AREA & AUXILIARY FACILITIES OF A CHEMICAL PLANT.
Estimating Capital Costs… Study Estimates….
Utilities
1) Lang Factors Method
Proposed by Hans J. Lang (1947)
Estimating Capital Costs… Study Estimates…. Estimating Capital Costs… Study Estimates….
Value of Lang Factors EXAMPLE: A small fluid processing plant is considered for
construction adjacent to a larger operating unit at a large plant
Lang developed factors for battery limit FCI of 03 types of plants
site. The present delivered equipment costs are as follows:
in Carbon Steel construction:
30
Estimating Capital Costs… Study Estimates…. Estimating Capital Costs… Study Estimates….
SOLUTION: Lang Method can be used for estimating:
Sum of the delivered equipment cost = $ 2,715,000 Total Direct Plant Cost
Fixed-capital Investment
for fluid processing plant, LF = 4.74
Total Capital Investment
Thus,
LFs vary with the type of plant
ISBL fixed capital investment = ($ 2,715,000)(4:74) = $12869100
Lang method should be used only in the early stages of
Adding 15% contingency: process design in the absence of detailed design info.
ISBL fixed capital investment = ($12869100 )(1.15) Most estimators use LF of 3, 4, or 5, depending on the plant
scale (larger plant = smaller LF) and type
= $14,799,000, or $14,800,000
121 122
31
Estimating Capital Costs… Study Estimates…. Estimating Capital Costs… Study Estimates….
For material other than Carbon Steel, LFs & HFs need
correction using material factor (see Brown’s Method)
Estimating Capital Costs… Study Estimates…. Estimating Capital Costs… Study Estimates….
EXAMPLE: A small fluid processing plant is considered for SOLUTION: Multiplying by Hand factor for each items:
construction adjacent to a larger operating unit at a large plant
site. The present delivered equipment costs are as follows:
935,000
*Note:
As no information given to indicate that Receivers & Accumulator
Drum were pressure vessels, so we treat them as noted. Had they
been pressure vessels, a factor of 4.0 might be used
Estimate the battery-limits fixed capital investment, assuming a
15% contingency factor. 128
32
Estimating Capital Costs… Study Estimates…. Estimating Capital Costs… Study Estimates….
In case if Receivers & Accumulator Drum were pressure vessels: 3) Brown’s Method
Brown introduced correction factors for LF & HF methods:
a) Material Factor (FM)
LF & HF were developed for carbon steel equipment
Estimating Capital Costs… Study Estimates…. Estimating Capital Costs… Study Estimates….
Fm is determined from the plot of Fm vs Material Cost Ratio EXAMPLE: The Hand factor for heat exchangers is 3.5. What
would be the adjusted Hand factor for a U-tube heat exchanger
with titanium tubes and CS shell? Assume material cost ratio is
2.6.
𝑪𝒐𝒔𝒕 𝒐𝒇 𝑨𝒍𝒍𝒐𝒚
𝑴𝒂𝒕𝒆𝒓𝒐𝒍 𝑪𝒐𝒔𝒕 𝑹𝒂𝒕𝒊𝒐 = SOLUTION: Using Fm vs Material Cost Ratio Plot for a material
𝑪𝒐𝒔𝒕 𝒐𝒇 𝑪𝑺
cost ratio of 2.6. we find Fm = 0.63
Fm
The adjusted Hand factor = 3.5 (0.63) = 2.2
33
Estimating Capital Costs… Study Estimates…. Estimating Capital Costs… Study Estimates….
b) Instrumentation Factors (Fi) c) Building Factors (Fb) (Only for Hand Factors)
Fi depends on amount of instrumentation in a process or plant HFs include almost no building costs, so the estimate must be
corrected to account for building costs
Fi Values
This is done using a building factor (Fb)
Local controls 1.15 New Plant/ New Unit at Expansion at
Type of Plant New Site Existing Site Existing Site
A typical chemical or processing plant 1.35
Solid Processing 1.68 1.25 1.15
Extensive controls, central control, computerization 1.55 Solid & Fluid 1.47 1.29 1.07
Processing
Fluid Processing 1.45 1.11 1.06
133 134
Estimating Capital Costs… Study Estimates…. Estimating Capital Costs… Study Estimates….
Place Factors
d) Location or Place Factors (Fp)
If plant is built outside US, cost is adjusted using Place Factor
34
Estimating Capital Costs… Study Estimates…. Estimating Capital Costs… Study Estimates….
Lang & Hand Methods in Final Form Creating Your Own Factors
If recent data available, it better to calculate own factors:
137 138
139 This chart gives you an idea how factor methods works! 140
35
Estimating Capital Costs… Study Estimates…. Estimating Capital Costs… Study Estimates….
Garrett’s Module Factors…. Garrett’s Module Factors….
141 142
143 144
36
Estimating Capital Costs… Study Estimates…. Estimating Capital Costs… Study Estimates….
To find Fm we first calculate the weight average alloy/CS cost
ratio for the 11 material equipment:
We now need to find the factors Fm, Fi and Fp. Total capital cost ($) = ($346.3K)(4.1)(0.63)(1.35)(1) = $1.208M
145 146
Estimating Capital Costs… Study Estimates…. Estimating Capital Costs… Study Estimates….
Now lets solve the same problem using Hand Method (modified)
The Hand Method
147 148
37
Estimating Capital Costs… Study Estimates…. Estimating Capital Costs… Study Estimates….
Finally using,
How to Use Factor Methods for Spare & Used Equipment
Fi = 1.35 (process is fully automated)
LFs & HFs are valid for full-price equipment and cannot be
Fb = 1.06 (process is upgrade to an existing plant) used for spare & used equipment which cost much less
Fp = 1.0 (process will be in the U.S)
To address this problem, calculation is done using the price of
We calculate the capital cost as: new equipment
The capital cost ($) = ($726.4K)(1.35)(1.06) (1) = $1.039M
The answer is adjusted by subtracting the extra cost of new
OBSERVATIONS: equipment
Result of Lang method is 16% higher than Hand method
(still within the accuracy range the methods)
Five major pieces of equipment (whose purchase cost is
more than $25K) account for about 88% of the capital cost!
149 150
Estimating Capital Costs… Study Estimates…. Estimating Capital Costs… Study Estimates….
EXAMPLE: As part of a plant upgrade project, you plan to use a To find Fm we use alloy/CS ratio to be 1.7 (Appendix 4)
spare 1000 ft2 U-tube heat exchanger (HE) rated at 150 psig
and built with a carbon steel shell and stainless steel tubes. The From the graph of Fm vs alloy/CS ratio, we find Fm = 0.8
plant will charge you $2000 for the exchanger. Assume the
instrumentation will be typical for a processing plant and that Fi = 1.35 (for typical controls)
your plant is in the U.S. What is the capital cost of this
Fb = 1.06 (expansion of fluid processing at an existing site)
exchanger?
38
Preliminary Estimates
Accuracy 15 to 25% Information
guide for capital
More info needed than Study
cost estimates
Estimates (see chart on next slide)
1. Factored methods
Estimating Capital Costs… Preliminary Estimates… Estimating Capital Costs… Preliminary Estimates…
39
Estimating Capital Costs… Preliminary Estimates… Estimating Capital Costs… Preliminary Estimates…
Estimating Capital Costs… Preliminary Estimates… Estimating Capital Costs… Preliminary Estimates…
40
Estimating Capital Costs… Preliminary Estimates… Estimating Capital Costs… Preliminary Estimates…
Include steam, electricity, water infrastructures needed Motors, starters, and wiring for process equipment are
included in the installed equipment costs
Factor ranges from 0 to 1.00 depending on amount of work
Electrical services within the building or structure are part of
needed for providing auxiliary facilities
the building costs
OUTSIDE LINES (Factor of IEC)
Outside feeder lines are part of the outside lines
All piping outside the building area is classified as “outside” Substations & transformer costs are under auxiliary facilities.
lines and the costs include the piping supports
Estimating Capital Costs… Preliminary Estimates… Estimating Capital Costs… Preliminary Estimates…
Total physical plant cost (TPPC) is then calculated as: ENGINEERING & CONSTRUCTION (Factor of TPPC)
TOTAL PHYSICAL PLANT COST = Installed Equipment Cost Estimated on the basis of a project’s complexity.
+ Cost of (process piping + instrumentation + building & site
If it is simple, use 20–35% of TPPC
development + auxiliary facilities + outside lines)
But if the engineering is difficult, first of its kind, or new to the
The remaining costs are calculated as factors of TPPC company, a percentage selected in the difficult range
163 164
41
Estimating Capital Costs… Preliminary Estimates… Estimating Capital Costs… Preliminary Estimates…
Contingencies are based upon process information available Small plants have a variety of problems that larger plants don’t.
If the data are reliable and similar to other known processes, The “size” factor is included to account for this.
then 10–20% of TPPC is satisfactory
Depending on the size of the plant a factor of 0 to 35% is used
If the process is speculative and subject to change, a higher
percentage should be used
165 166
Estimating Capital Costs… Preliminary Estimates… Estimating Capital Costs… Preliminary Estimates…
167
168Value ranges of these factors is given in the next table
42
Summary of Chilton Method Summary of Chilton Method
169 170
171 172
43
A small fluid processing plant is to be built at an existing plant site.
Estimating Capital Costs… Preliminary Estimates…
The delivered equipment costs are given. The equipment is to be
installed in an outdoor structure. The process is heavily SOLUTION: The total delivered equipment cost is $2,715,000.
instrumented, and auxiliary services and outside lines are
minimal. The process is well defined and is based upon a similar
unit built at another company location. Estimate the battery-limits
fixed capital investment using the Chilton method
173 174
Estimating Capital Costs… Preliminary Estimates… Estimating Capital Costs… Preliminary Estimates…
Direct-cost items incurred in the construction of a plant, in 6. Ancillary buildings, offices, laboratory buildings, workshops
addition to the cost of equipment, are: 7. Storage for raw materials & finished product
1. Equipment erection, including foundations and minor 8. Utilities (Services), provision for steam, water, air,
structural work firefighting services (if not costed separately as offsite)
2. Piping, including insulation and painting 9. Site preparation
3. Electrical power and lighting
175 176
44
Estimating Capital Costs… Preliminary Estimates… Estimating Capital Costs… Preliminary Estimates…
Contribution of items 1-9 to Total Capital Cost is calculated by The method can be used for approximate estimates of capital
multiplying Purchased Equipment Cost by factors given below cost using equipment cost data
177 178
Estimating Capital Costs… Preliminary Estimates… Estimating Capital Costs… Preliminary Estimates…
Material Factors for Correcting Equipment Cost Material cost factors of some common metals are given in
The installation factors given in Tables 6.3 and 6.4 are for Table 6.5
plants built from Carbon Steel (CS)
IMPORTANT NOTE
When more exotic materials are used, then a materials factor
Material Cost Factors fm is use to correct the equipment cost
fm should also be introduced:
and is different from Materials Factor (Fm) use to correct
If cost of CS equipment is known, corresponding cost in Factors (see Brown's Method)
another material can be determine by multiplying with Material
Cost Factors fm
179 180
45
Estimating Capital Costs… Preliminary Estimates… Estimating Capital Costs… Preliminary Estimates…
OR
181 182
Estimating Capital Costs… Preliminary Estimates… Estimating Capital Costs… Preliminary Estimates…
46
Estimating Capital Costs… Preliminary Estimates… Estimating Purchased Equipment Costs
Summary of the Factorial Method…… All Factorial Methods are based on equipment costs data
4. Calculate the OSBL, engineering, and contingency costs Reliable equipment cost are therefore very important
using the factors given in Table 6.4.
Sources of purchased equipment costs are:
5. The sum of ISBL, OSBL, engineering, and contingency
costs is the fixed capital investment. a) Vendors /suppliers /dealers
6. Estimate the working capital as a percentage of the fixed
b) Manufacturers’ catalog (available online now a days)
capital investment 10 to 20% is typical (or calculate it from
c) Recent data for similar equipment
cost of production if it is estimated)
7. Add the fixed and working capital to get the total d) Data from the open literature
47
Estimating capital investment…
𝑪𝒆 = 𝒂 + 𝒃𝑺𝒏
Values of a, b and n are tabulated in chemical engineering
books for a number of commonly used equipment
(A table from Gavin Towler’s book is given in the next slides)
189 190
191 192
48
Chemical Engineering Design, Principles, Practice and Economics of Plant and Process Example 6.2……
Design, By GAVIN TOWLER and RAY SINNOTT
Example 6.2 taken from Chemical Engineering Design, Principles, Practice &
Solution: First convert units as required by correlations. For
Economics of Plant and Process Design, By GAVIN TOWLER and RAY
costing of metal equipment, shell mass is needed which can be SINNOTT
calculated
193 using the wall thickness.: 194
The design pressure of vessels should be ~ 10 % above operating Now the shell mass for the distillation column can be calculated using:
pressure (11 bar or 1.1 x106 N/m2), (section 13.4)
The max. allowable stress for type 304 st. steel @ 500 ˚ F (260 ˚C) is
12.9 ksi (or 89N/mm2) (Table 13.2).
195 196
49
Example 6.2… Example 6.2…
Using the correlations in Table 6.6, we can obtain the purchase costs:
197 198
We now have estimated the purchased cost of the major equipment items.
The ISBL installed capital cost can be calculated using suitable methods Total cost of Dist. Col. + Internals =1,480,000+76,700 =$ 1,560,000.
and correcting for materials of construction using materials factors given
in Table 6.5. The installed cost of the horizontal pressure vessel is:
The cost of the trays can be converted to type 304 stainless steel by
multiplying with material factor from Table 6.5, giving:
So, the cost in type 304 SS is: 1.3 (176,000) = $ 229,000.
199 200
50
Example 6.2… Example 6.2…
For pumps, we must add the cost of the pump and driver before Factor Method:
determining the installed cost (only pump cost is converted to SS). Using equation 6.13 and the factors given in Table 6.4, the installed cost
For the first type of two pumps: for the exchangers, tank, and pumps will be:
For the second type of three pumps, (only 02 installed), the total
installed cost is:
The installed cost for pressure vessels and pump drivers (no materials
conversion factor needed) is:
The total installed ISBL cost of the plant is then
201 202
The cost of the trays in SS and cost of the spare pump and driver: Note:
203
51
Estimating capital investment… Estimating capital investment…
Location Factors
Most plant & equipment cost data are based on U.S. Gulf
Coast (USGC) or Northwest Europe (NWE) basis
where LFA = location factor for location ‘A’ on USGC basis 206
52
EXAMPLE PROBLEMS SCOPE & CONTINGENCY
IMPORTANT PROBLEMS Scope:
Problems 6.1 to 6.8 Chapter 6,
A document that defines a project
Gavin Towler’s Book
Frequently used by cost control & estimating personnel to
Problems 1 to 4 Chapter 3 Thane
ensure plant constructed as per requirements
Brown’s Book
A scope should include following info:
Problems 1 to 10 Chapter 6
Timmerhaus’s Book What product is being manufactured?
209 210
53
SCOPE & CONTINGENCY…
Estimating Capital Costs… Working Capital… Estimating Capital Costs… Working Capital…
WORKING CAPITAL
Total Capital Fixed Capital Working Capital Land
= + + Funds necessary to conduct a day-to-day business (pay wages
Cost Cost Cost Cost
and salaries, purchase raw materials, supplies, etc.)
54
Estimating Capital Costs… Working Capital… Estimating Capital Costs… Working Capital…
Estimating Capital Costs… Working Capital… Estimating Capital Costs… Working Capital…
EXAMPLE: A company is considering an investment in an Since the working capital is 15% of the total capital investment,
aldehyde facility. The engineering department has estimated that the subtotal above is 85%, providing no other capital items are
the battery-limits fixed capital investment to be $19MM. Land added:
𝟖𝟓
allocated for the project is $500,000 and start-up expenses to be 𝑻𝒐𝒕𝒂𝒍 𝑪𝒂𝒑𝒊𝒕𝒂𝒍 𝑰𝒏𝒗𝒆𝒔𝒕𝒎𝒆𝒏𝒕 × = 𝟐𝟎, 𝟒𝟎𝟎, 𝟎𝟎𝟎
𝟏𝟎𝟎
capitalized are expected to be $900,000. The company normally
uses 15% of the total capital investment for working capital. Total Capital Investment = 𝟐𝟒, 𝟎𝟎𝟎, 𝟎𝟎𝟎
Determine the estimated amount of working capital for this
project. 𝑾𝒐𝒓𝒌𝒊𝒏𝒈 𝑪𝒂𝒑𝒊𝒕𝒂𝒍 = 𝟐𝟒, 𝟎𝟎𝟎, 𝟎𝟎𝟎 − 𝟐𝟎, 𝟒𝟎𝟎, 𝟎𝟎𝟎 = 𝟑, 𝟔𝟎𝟎, 𝟎𝟎𝟎
SOLUTION:
or
TCI= 𝟐𝟎, 𝟒𝟎𝟎, 𝟎𝟎𝟎 + 𝟎. 𝟏𝟓 𝑻𝑪𝑰,
219 220
55
Estimating Capital Costs… Working Capital… Estimating Capital Costs… Working Capital…
221 222
Estimating Capital Costs… Working Capital… Estimating Capital Costs… Working Capital…
56
225 226
One-time expenses needed to brought the plant to operation How Much Start-Up Expanses Should be used
Period between end of construction and production of product Start-up expenses vary between 5 to 20% of FCI
in required quality and quantity is termed as Start-Up
For plants with FCI ≥ $100MM, 6% is a reasonable
In this period several expenses are incurred such as
For plants with FCI $10MM to $100MM, 8% is satisfactory
Operator and maintenance employee training
Temporary construction For plants of < $10MM, start-up expenses may be as high as
10% of FCI
Auxiliary services
227 228
57
PRODUCTION COSTS Production Costs…
All expenses required to make a product ready for shipment Classification of Production Costs
Include cost of:
Can be classify in two broad groups
Manufacturing a product
1. Fixed Costs: Do not change with production volume
Packaging and shipping
Selling and distribution 2. Variable Costs vary with production volume
Another way of classifying production cost Another way of classifying production cost…
1) Direct Expenses: Costs that are directly associated Indirect Expenses: Costs that are nearly constant with
with product manufacture (e.g., utilities, supplies, and labor) respect to production rate (e,g. depreciation, security, fire
protection, roads, yards, gardening, docks)
Direct costs are nearly directly proportional to production rate.
On a unit-cost basis, the indirect expenses tend to decrease
On per unit-cost basis, they remain constant irrespective of
with increasing production, since their cost is constant or
the amount of material produced.
varies slightly with the production rate
Raw materials and byproducts are often mentioned separate
items from direct and indirect expenses, although they tend to
vary directly with the production rate!
231 232
58
TYPE Estimation Method
PRODUCTION COST Production Costs…
Fixed Variable Direct Estimate Factor
1) Raw materials We will now discuss the production costs which are directly
2) Packaging materials estimated :
3) Manufacturing
1. Raw materials Numbers are based on
a) Operating labor PRODUCTION COST List in
b) Utilities 2. Packaging materials the previous slide
c) Employee benefits
3b) Utilities
d) Supervision
e) Laboratory 3a) Operating labor,
f) Maintenance 4) Product Delivery
g) Insurance & taxes
h) Operating supplies
i) Plant overhead
j) Depreciation
4) Product delivery
233 234
59
Production Costs… Production Costs…
For items such as cooling water, refrigeration, and steam, SOLUTION
company cost data is probably the most accurate.
Ulrich Table
Production Costs…
Ulrich Method:
If we know what equipment is in the process, Ulrich Table can
be used to estimate the crew size
60
Ulrich Table
Production Costs…
EXAMPLE: Find the crew size for a process that has the following
equipment:
241 242
Next best is to ask for quotes from trucking companies and railroads
243 244
61
Production Costs… Production Costs…
Subcategories (3c to 3j) of Production Cost Subcategories of Production Cost Estimated by Factor Method:
Estimated by Factor Method: Insurance and Taxes: use 3 to 5% of the capital investment
Employee benefits: 22 to 45% of Operating Labor Cost (For Operating Supplies: use 0.5 to 3% of the capital investment
study estimates, use your company’s percentage)
Plant Overhead: 1 to 5% of the capital investment.
Supervision: 10 to 30% of Operating Labor Cost
Depreciation: calculated using Straight-Line method
Laboratory: 10 to 20% of Operating Labor Cost
The annual straight depreciation cost (write off) is given by:
Maintenance: For new plants use 2 to 10% of Total Plant Cost
(the average is 6%)
For older plants, use 5 to 31% of the depreciated cost of plant,
(the average being 12%) Numbers are based on PRODUCTION
245 COST List 246
247 248
62
249 250
251 252
63
253 254
255 256
64
257 258
259 260
65
261 262
263 264
66
265 266
267 268
67
269 270
271 272
68
273 274
275 276
69
277 278
279 280
70
281 282
Interest rate (discount rate) for which the present value of the future
cash flows would equal to the initial cost (capital investment
OR,
Interest rate for which the NPV of all the cash flows is zero
Present Value = Cost or NPV = 0
We know that NPV is given by:
71
Discounted Cash Flow Rate of Return (DCFROR) or IRR…important Points Discounted Cash Flow Rate of Return (DCFROR) or IRR…important Points
IMPORTANT NOTES…
IMPORTANT NOTES:
IRR is a more useful method than NPV for comparing projects of
IRR also called Interest Rate of Return and Discounted Cash Flow
very different size because:
Rate of Return (DCFROR)
1) NPV of large projects is usually higher than NPV of small projects, but then the
It is a measure of the maximum interest rate that the project could investment amount is also much greater
pay and still break even by the end of the project life 2) IRR is independent of project size, and the project with the highest IRR always
IRR is a useful way of comparing different projects, independent of provides the best returns!
the amount of capital used, the life of the plant, or the actual interest When IRR is used as an investment criterion, good projects are
rates prevailing at any time. those which have IRR > the cost of capital (interest rate).
285 286
287 288
72
289 290
291 292
73
293 294
295 296
74
297 298
299 300
75
301 302
303 304
76
305 306
307 308
77
309 310
311 312
78
313 314
315 316
79
317 318
319 320
80
321 322
323 324
81
325 326
327 328
82
Do this problem only with Net Present Value
329 330
331 332
83
Do this problem only with Net Present Value
333 334
335 336
84
337 338
339 340
85
341 342
343 344
86
EXAMPLE: A plant is producing 10,000 metric tons per year There are two ways of evaluate the modification:
(10kMTA) of a product. The overall yield is 70%, on a mass basis 1) If all the increased production can be sold, (sufficient demand exist), the
(kg of product per kg raw material). The raw material costs proposal will increase earnings (increased sales)
$500/metric ton, and the product sells for $900/metric ton. A
2) Even if no demand exist for additional production, the modification will still
process modification has been devised that will increase the reduce raw materials requirement for the current production level (reduce
yield to 75%. The additional investment required is $1,250,000, RM cost)
and the additional operating costs are negligible. Is the
The second way is the safest basis for making the evaluation
modification worth making?
SOLUTION: At 10kMTA production,
345 346
Raw Material Saving = 14286 -13333 = 953 MT/y EXAMPLE: A carbon steel heat exchanger that costs $140,000
is expected to have a service life of 5 years before it requires
Amount saved = 953 x 500 = $ 476500 /y
replacement. If type 304 stainless steel is used, then the service
Therefore , life will be increased to 10 years. Which exchanger is the most
economical if the cost of capital is 12%?
SOLUTION:
and Pay Back Period (inverse of ROI) ,
From Table 6.5, we can estimate the cost of the type 304
stainless steel exchanger to be $140,000 X 1.3 = $182,000
DO YOURSELF
As both ROI and payback period are very attractive, the
proposed investment worth implementation depending on other
constraints and company policy.
87
PERPETUITIES & CAPITALIZED COSTS PERPETUITIES & CAPITALIZED COSTS
Perpetuity: Capitalized Cost…
Perpetuity is an annuity (periodic payments) that continue In these cases, a fund P is maintained which will earn enough
indefinitely interest to pay for periodic equipment replacement
If annual interest rate is 6 % the fund needed in this case can be
It is use to determine the total investment required for a piece of
calculated as:
equipment or asset under conditions which allow it to be
replaced perpetually without considering inflation or deflation. 𝑃+10000 𝑃+10000
𝑃= = , therefore P = 12650 $
1+𝑖 𝑛 1+0.6 𝑛
Capitalized Cost:
The fund of 12650 would becomes ($12650)(1+0.06)10= $22650
Let original cost of an equipment is $12,000, useful-life is 10 yrs
after 10 years.
and the scrap value is $2000
Thus, after 10 yrs, the equipment can be replaced for $10,000
To use the equipment for long time, it will be necessary to spend and $12,650 will remain in the fund.
$10,000 every 10 yrs to replace it.
This cycle could now be repeated indefinitely.
88
The Capitalized Cost is defined as the original cost of the
equipment plus the present value of the renewable perpetuity.
89
Practice Problems
A plant is proposing to install a combined heat and power system (CHP)
to supply electrical power and process steam. Power is currently taken
from a utility company, and steam is generated using onsite boilers.
The capital cost of the CHP plant is estimated to be $23 million.
Combined heat and power are expected to give net savings of $10
million per year. The plant is expected to operate for 10 years after the
completion of construction. Calculate the cumulative net present value
of the project, at a discount rate of 12%. Also, calculate the discounted
cash flow rate of return. Construction will take 2 years, and the capital
will be paid in two equal increments, at the end of the first and second
years. The savings (income) can be taken as paid at the end of each
year. Production will start on the completion of construction.
90
Recommended Books HEAT EXCHANGERS BASICS
1) PLANT DESIGN AND ECONOMICS FOR CHEMICAL ENGINEERS Log Mean Temperature Difference (LMTD):
BY Max S. Peters & Klaus D. Timmerhaus (Chapter 6) The temperature difference between hot & cold fluids varies
along the heat exchanger. LMTD is used to calculate average
2) CHEMICAL ENGINEERING DESIGN, Principles, Practice and temperature difference:
Economics of Plant and Process Design,
BY Gavin Towler & Ray Sinnott (Chapter 6)
3) The topics Time Value of Money and Measure of Profitability are from
OPTIMIZATION OF CHEMICAL PROCESSES, Here Δ𝑇2 & Δ𝑇1 are the temperature difference between the two
By T. F. Edgar, D. M. Himmelblau & L. S. Lasdon fluids at the two ends (inlet & outlet) of the heat exchanger.
(Chapter 3) NOTE: It makes no difference which end of heat exchanger is
taken as inlet or outlet as shown in figure:
362
Cold Fluid
Hot Fluid
ΔT2 = T1 - t2
ΔT2 = T2 – t1
Cold Fluid
363 364
91
HEAT EXCHANGERS BASICS….
Q = U × A × LMTD
365
92