Professional Documents
Culture Documents
1: Building Technology 5
1.1 Floor System and Roof Slab System
The roof slab is cast last, on top. Usually, the construction is flat plate, and the slabs
have uniform thickness. A flat slab is a two-way reinforced concrete slab that usually
does not have beams and girders, and the loads are transferred directly to the
supporting concrete columns.
Advantages of System:
1. Simple formwork and suitable for direct fix or sprayed ceiling
2. No beams—simplifying under-floor services
3. Minimum structural depth and reduced floor-to floor height.
Disadvantages of System:
1. Medium spans
2. May need shear heads or shear reinforcement at the columns or larger columns for shear
3. Long-term deflection may be controlling factor
4. May not be suitable for supporting brittle (masonry) partitions
Ribbed and Waffle Slabs
Ribbed and waffle slabs provide a lighter and stiffer slab than an equivalent flat slab,
reducing the extent of foundations. They provide a very good form of construction where slab
vibration is an issue, such as laboratories and hospitals.
Ribbed slabs are made up of wide band beams running between columns with narrow ribs
spanning the orthogonal direction. Normally the ribs and the beams are the same depth. A
thin topping slab completes the system.
Waffle slabs tend to be deeper than the equivalent ribbed slab. Waffle slabs have a thin
topping slab and narrow ribs spanning in both directions between column heads or band
beams. The column heads or band beams are the same depth as the ribs.
Advantages of System:
• Excellent vibration control
• Fire resistance
• Attractive soffit appearance if exposed
• Speed of construction
• Flexible
Disadvantages of System:
• Requires special or proprietary formwork
• Greater floor-to-floor height
Lift Slab Method
Lift slab construction is a method of constructing concrete buildings by casting the floor or
roof slab on top of the previous slab and then raising the slab up with hydraulic jacks, so
being cheaper and faster as it does not need forms & shores as it is needed for cast-in-place
slabs.
It normally requires fewer joints than other types of precast building systems. Typically,
columns are erected first, but not necessarily for the full height of the building. Near the base
of the columns, floor slabs are cast in succession, one atop another, with a parting com-pound
between them to prevent bond. The roof slab is cast last, on top. Usually, the construction is
flat plate, and the slabs have uniform thickness
To raise the slabs, jacks are set atop the columns and turn threaded rods that pass through the
collars and do the lifting. As each slab reaches its final position, it is wedged in place and the
collars are welded to the columns.
Limitation:
This method is not use for multi-storey building, only use for 15-16 storey building.
No large span slabs are constructed in this type of construction.
Span Stress Floor System Steel floor system also means less labor and cost. For example,
the simplest solution of a down stand solid web I-sectioned beam as opposed to a truss
means; fewer structural elements, less fabrication, fewer surfaces to be fire protected and less
time to design.
Stiffness is needed to ensure that a floor behaves correctly from a dynamic point of view,
thereby assuring user comfort. This is a complex subject, as the real issue is how the floor
responds (in terms of acceleration), and that is a function of a number of variables including
stiffness and the mass that is mobilized. The traditional approach, which is recognized as
being crude, for designing a floor to respond acceptably is to check its natural frequency and
compare that with a limiting value (which is a function of the floor mass). The required
behavior depends on the function for a given building/room. Some uses are less tolerant to
floor movements (e.g. an operating theatre). Some uses (e.g. a gymnasium within an office)
are more likely to cause problems and warrant particular attention
Slip Form Method
Slip forming, continuous poured, continuously formed, or slipform construction is a
construction method in which concrete is poured into a continuously moving form. Slip
forming is used for tall structures (such as bridges, towers, buildings, and dams), as well as
horizontal structures, such as roadways.
Slip forming enables continuous, non-interrupted, cast-in-place "flawless" (i.e. no joints)
concrete structures which have superior performance characteristics to piecewise construction
using discrete form elements.
Slip forming relies on the quick-setting properties of concrete, and requires a balance
between quick-setting capacity and workability. Concrete needs to be workable enough to be
placed into the form and consolidated (via vibration), yet quick-setting enough to emerge
from the form with strength. This strength is needed because the freshly set concrete must not
only permit the form to "slip" by the concrete without disturbing it, but also support the
pressure of the new concrete as well as resist collapse caused by the vibration of the
compaction machinery.
In vertical slip forming the concrete form may be surrounded by a platform on which workers
stand, placing steel reinforcing rods into the concrete and ensuring a smooth pour. Together,
the concrete form and working platform are raised by means of hydraulic jacks. Generally,
the slip form rises at a rate which permits the concrete to harden by the time it emerges from
the bottom of the form.
In horizontal slip forming for pavement and traffic separation walls concrete is laid down,
vibrated, worked, and settled in place while the form itself slowly moves ahead. This method
was initially devised and utilized in Interstate Highway construction initiated by the
Eisenhower administration during the 1950s.