Problem Statement: 50% of the learners (53 out of 106) cannot not correctly perform the
learning competencies.
_______________________________________________________________
Project Objective Statement: At least 80 % ( 85 out of 106) can perform the learning
competencies correctly.
_______________________________________________________________
TVE
Purchase request
Purchase First quarter of teachers/Supply
for tools and none
request form 2016 officers/School
equipments
head
Canvassed TVE
Canvass for tools form for tools First quarter of teachers/Supply
none
and equipments and 2016 officers/School
equipments head
Disbursement
voucher Second quarter SDO/Bookkeeper 60,000 MOOE
voucher
Date of Person
Activity Output Budget Budget Source
Implementation Responsible
TVE EIM
Drafting project First quarter None
Project proposal teachers
proposal 2016
TVE EIM
Sourcing of First quarter none
teachers
funds 2016
Program of
TVE EIM
works Program of First quarter none
teachers
works 2016
Problem Statement: To prevent the illegal entry of astray animals and intruders
______________________________________________________________
Project Objective Statement: To secure the school perimeter/ Facilities from intruders
_______________________________________________________________
Date of Person
Activity Output Budget Budget Source
Implementation Responsible
Advertising the
school to alumni Multimedia School none
On going
and access Head/teachers
stakeholders
On going School
Introduce the Multimedia none
Head/teachers
project access
Solicitation
Solicit letter/Return On going School Alumni/
6,000/ Span
Slip Head/teachers Stakeholders
ANNEX 9 Project Work Plan and Budget Matrix
Project Objective Statement: To minimize erosion that might damage school property
_______________________________________________________________
Date of Person
Activity Output Budget Budget Source
Implementation Responsible
Third quarter of
Purchase Purchase TVE MC
SY 2016-2017 none
request request form teachers
TVE MC
canvass Canvass form Third quarter of none
teachers
SY 2016-2017
Date of Person
Activity Output Budget Budget Source
Implementation Responsible
First Quarter of
Program of Program of Office of
2016-2017 50,000 LGU-Pudtol
works works Engineering LGU
ANNEX 9 Project Work Plan and Budget Matrix
Problem Statement: The students are not aware of the value of nationalism and
patriotism
______________________________________________________________
Root Cause: Students don’t appreciate the value of flag ceremony, nationalism and
patriotism
_______________________________________________________________
Date of Person
Activity Output Budget Budget Source
Implementation Responsible
Last quarter of
Purchase Purchase SGO adviser/
SY 2016-2017
request request form Officers
Last quarter of
SGO adviser/
canvass Canvass form SY 2016-2017
Officers
Last quarter of
Purchase order SGO adviser/
Purchase order SY 2016-2017
form Officers
_______________________________________________________________
Problem Statement:
______________________________________________________________
Project Objective Statement: To provide students wider space for parking, co-curricular
activities
_______________________________________________________________
Root Cause: No centralized parking space for students and teachers motorcycle, space for
holding students co-curricular activities
_______________________________________________________________
Date of Person
Activity Output Budget Budget Source
Implementation Responsible
Second quarter
Purchase Purchase
of SY 2016-2017 Provincial Office
request request form
Second quarter
canvass Canvass form of SY 2016-2017 Provincial Office
Second quarter
Purchase order
Purchase order of SY 2016-2017 Provincial Office
form
Project Objective Statement: To deliver the lesson more effectively through ICT
_______________________________________________________________
Root Cause: less interest on the subject matter on the part of students and lesser burden
on the part of the teacher doing traditional method
_______________________________________________________________
Date of Person
Activity Output Budget Budget Source
Implementation Responsible
Computer
Drafting Project Last quarter of
Project proposal Laboratory
proposal SY 2016-2017
custodian
Computer
Liquidation Liquidation Last quarter of Computer Lab
Laboratory 25,000
Report paper SY 2016-2017 Fee
custodian
ANNEX 9 Project Work Plan and Budget Matrix
Project Objective Statement: To provide adequate water to all comfort rooms and washing
areas.
_______________________________________________________________
Date of Person
Activity Output Budget Budget Source
Implementation Responsible
Last quarter of
Purchase Purchase
SY 2016-2017 School head
request request form
Last quarter of
canvass Canvass form SY 2016-2017 School head
Last quarter of
Purchase order
Purchase order SY 2016-2017 School head
form
Problem Statement: Only 75% of the learners in Section B and C attain passing grade in
most of the core subjects.
______________________________________________________________
Project Objective Statement: at least 100% attain passing in all the core subjects.
_______________________________________________________________
Date of Budget
Activity Output Person Responsible Budget
Implementation Source
Drafting
Project
Project First quarter of
proposal by Subject teachers
proposal by SY 2016-2017
subject area
subject area
First quarter of
Purchase Purchase
SY 2016-2017 Subject teachers
request request form
First quarter of
Administrative
canvass Canvass form SY 2016-2017
assistant/Bookkeeper
First quarter of
Purchase order Administrative
Purchase order SY 2016-2017
form assistant/Bookkeeper
Project Objective Statement: 100% of the teachers will be able to prepare Sims, IMs, LPs,
Table of specification and rubric form of rating.
_______________________________________________________________
Date of Person
Activity Output Budget Budget Source
Implementation Responsible
School head/
Drafting Project Second quarter
Project proposal Head Teachers,
proposal of SY 2022-2023 N/A
Teachers
Purchase
Second quarter School head/
request of Purchase
of SY 2022-2023 Head Teachers, N/A
Materials request form
Teachers
needed
School head/
Liquidation Liquidation Last quarter of
Head Teachers, 15,000 MOOE
Report paper SY 2022-2023
Teachers
ANNEX 9 Project Work Plan and Budget Matrix
Problem Statement: no enough equipment for indoor games to be used when P.E. period
falls on rainy season
______________________________________________________________
Project Objective Statement: Students will have enough equipment to use and enjoy their
P. E period during rainy season while increasing their vocabulary
_______________________________________________________________
Root Cause: Rainy days inhibit the students to perform learning competencies in P.E.
Furthermore, Vocabularies of students are not much developed.
_______________________________________________________________
Date of Budget
Activity Output Person Responsible Budget
Implementation Source
Drafting
Project Secondquarter
Project Subject Teacher
proposal of SY 2016-2017
proposal
Second quarter
Purchase Purchase
of SY 2016-2017 Subject Teacher
request request form
Last quarter of
Purchase order Administrative
Purchase order SY 2016-2017
form Assistant/Bookkeeper
Project Title :
_______________________________________________________________
Problem Statement:
______________________________________________________________
Root Cause:
_______________________________________________________________
Date of Person
Activity Output Budget Budget Source
Implementation Responsible
Last quarter of
Purchase Purchase
SY 2016-2017 School head
request request form
Last quarter of
canvass Canvass form SY 2016-2017 School head
Last quarter of
Purchase order
Purchase order SY 2016-2017 School head
form