K017-T12-0002 - 0 Procedure For Installation of Temporary Jetty For Ro-Ro Operation
K017-T12-0002 - 0 Procedure For Installation of Temporary Jetty For Ro-Ro Operation
CONTRACTOR TO COMPLETE
PR2ME-K000-MGT-TMP-006_0
24-AUGUST-2022
Project : No Document K017-T12-0002
Batu Hijau Process Expansion
Project Date 25/05/2023
Title : Revision 00
K-017 Temporary Jetty Page 1 of 47
Title: Revision 00
Temporary Jetty Page 2 dari 47
Table of Contents
1. INTRODUCTION ............................................................................................................................................................................................ 4
1.1 General ...................................................................................................................................................................................... 4
1.2 Scope ......................................................................................................................................................................................... 4
1.3 Reference.................................................................................................................................................................................. 4
1.4 Responsibility ........................................................................................................................................................................... 4
2. BARGE AND LCT SELECTION .....................................................................................................................................................................5
2.1 Barge..........................................................................................................................................................................................5
2.2 LCT 2000 DWT ..........................................................................................................................................................................6
2.3 Cargo.......................................................................................................................................................................................... 7
3. JETTY COORDINATE & PLAN.....................................................................................................................................................................9
3.1 Jetty Coordinate......................................................................................................................................................................9
3.2 Jetty Coordinate against the Sea Plane Path ...................................................................................................................11
4. DETAIL ENGINEERING DESIGN OF TEMPORARY JETTY.........................................................................................................................12
4.1 Jetty Elevation ....................................................................................................................................................................... 13
4.2 Bollard Design ........................................................................................................................................................................ 15
4.3 Lighting Plan .......................................................................................................................................................................... 20
4.4 Roll of Operation for Heavy Cargo Simulation .................................................................................................................21
4.5 Dump Truck and Trailer In/Out Simulation .................................................................................................................... 23
4.6 Dump Truck Ground Bearing Pressure ............................................................................................................................24
4.7 Formula of Settlement Calculation ....................................................................................................................................24
4.8 Settlement Calculation ........................................................................................................................................................ 26
4.9 Calculation Result Based on Finite Elements Method With Software Plaxis As Device ......................................... 29
5. EQUIPMENTS AND MATERIALS .............................................................................................................................................................. 32
5.1 2 units of Excavator ............................................................................................................................................................. 32
5.2 1 unit of Dozer D85R ............................................................................................................................................................ 32
5.3 1 unit of Vibro Roller 10 Ton ................................................................................................................................................ 33
5.4 Geotextile Woven .................................................................................................................................................................. 33
5.5 Sand Filling Material............................................................................................................................................................. 34
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 3 dari 47
6. MANPOWER .............................................................................................................................................................................................. 35
7. MOBILIZATION AND DEMOBILIZATION .................................................................................................................................................. 35
8.1 Mobilization of Manpower ................................................................................................................................................... 35
8.2 Mobilization of Equipment ................................................................................................................................................... 36
8. CONSTRUCTION METHOD STATEMENT ................................................................................................................................................. 38
9. SCHEDULE ................................................................................................................................................................................................ 40
10. ENVIRONMENTAL IMPACT .......................................................................................................................................................................41
11. CONCLUSSION...........................................................................................................................................................................................41
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 4 dari 47
1. INTRODUCTION
1.1 General
This general procedure was prepared for PT. Amman Mineral Nusa Tenggara Roll On/Roll Off operation and also
intended to build temporary jetty for unloading 350 Tons MP Column + LP Column from 270 feet barge or LCT
2000 DWT using Multi-Axle Trailer to quay.
Other civil engineering calculation will be provided once this procedure is approved
1.2 Scope
This procedure covers PT. Amman Mineral Nusa Tenggara intended to build the temporary jetty for landing and
beaching the 270 feet barge and LCT 2000 DWT.
1.3 Reference
- UU No. 17 tahun 2008 tentang Pelayaran.
- Peraturan Pemerintah RI Nomor 27 Tahun 2012 tentang Izin Lingkungan.
- Peraturan Pemerintah RI Nomor 81 tahun 2003 tentang kenavigasian
- Peraturan Pemerintah RI Nomor 69 tahun 2001 tentang Kepelabuhanan
- Undang Undang No. 1 Tahun 1970 tentang Keselamatan
- Permanekertrans RI No. 1 Tahun 1980 tentang Keselamatan Konstruksi Sipil
- Permenaker RI No. 5 Tahun 1995 tentang Pesawat Angkat dan Angkut
- Permenaker RI No. 5 Tahun 1996 tentang K3L
1.4 Responsibility
The Project Manager is responsible for the approval of this document.
The HSE Manager is responsible for the monitoring, verification and issue of this document and of its subsequent
revisions.
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 5 dari 47
2.1 Barge
Title: Revision 00
Temporary Jetty Page 6 dari 47
Title: Revision 00
Temporary Jetty Page 7 dari 47
2.3 Cargo
Gas Turbine – LNG Power Plant
Temporary Jetty will be used for roro operation for cargo weight 350 tons and with trailer configuration 24
axlelines with axle Load is 7.9 tons and Ground Bearing Pressure is 3.5 ton/m2
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 8 dari 47
Temporary Jetty will be used for roro operation for cargo weight 350 tons and with trailer configuration 48 axlelines
with axle Load is 5.9 tons and Ground Bearing Pressure is 2.6 ton/m2
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 9 dari 47
The Jetty coordinate is from 8°53'51.58"S, 116°44'54.70"E and 8°53'52.21"S 116°44'53.86"E to 8°53'58.45"S,
116°44'59.54"E and 8°53'58.69"S, 116°44'59.22"E
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 10 dari 47
Title: Revision 00
Temporary Jetty Page 11 dari 47
Title: Revision 00
Temporary Jetty Page 12 dari 47
Title: Revision 00
Temporary Jetty Page 13 dari 47
Title: Revision 00
Temporary Jetty Page 14 dari 47
Title: Revision 00
Temporary Jetty Page 15 dari 47
Title: Revision 00
Temporary Jetty Page 16 dari 47
WIND FORCE = F Wind = SHIP BODY AREA ABOVE WATER X P wind X 1.3
= (2 x ( H-T)) x P )
= 23012.275 Kg
= 23.012275 TON
P Wind = 41 Kg/m²
CURRENT FORCE = F Current = AREA OF THE SHIP BODY IN THE WATER X P current
= (( P X L) + (2 X ( P X T ))
= 1609.25 Kg
V = Current Speed
= 0.2 m/s
P Current = ϒ x V²
2xg
= 2.089704383 Kg/m²
ϒ = Weight of Sea Water
= 1025 Kg/m²
F Current = 2208.042559 Kg
= 2.208042559 TON
SHIP MOORING FORCE (BOLLARD TENSILE FORCE) = F Wind + F Current
F bollard = 25.22031756 TON
Title: Revision 00
Temporary Jetty Page 17 dari 47
Title: Revision 00
Temporary Jetty Page 18 dari 47
WIND FORCE = F Wind = SHIP BODY AREA ABOVE WATER X P wind X 1.3
= (2 x ( H-T)) x P )
= 26362.31858 Kg
= 26.36231858 TON
P Wind = 41 Kg/m²
CURRENT FORCE = F Current = AREA OF THE SHIP BODY IN THE WATER X P current
= (( P X L) + (2 X ( P X T ))
= 2287.3395 Kg
V = Current Speed
= 0.2 m/s
P Current = ϒ x V²
2xg
= 2.089704383 Kg/m²
ϒ = massa jenis air laut
= 1025 Kg/m²
F Current = 2890.022303 Kg
= 2.890022303 TON
Title: Revision 00
Temporary Jetty Page 19 dari 47
Title: Revision 00
Temporary Jetty Page 20 dari 47
Title: Revision 00
Temporary Jetty Page 21 dari 47
Title: Revision 00
Temporary Jetty Page 22 dari 47
Title: Revision 00
Temporary Jetty Page 23 dari 47
Title: Revision 00
Temporary Jetty Page 24 dari 47
Description:
Cc : Compression Index
Cs : Swelling Index
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 25 dari 47
Description:
Influence graph
Description:
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 26 dari 47
Title: Revision 00
Temporary Jetty Page 27 dari 47
From the analysis by analytical method, the jetty is able to carry a load of 6,85 T/m2 at surface level
Variation of Tv with U
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 28 dari 47
Title: Revision 00
Temporary Jetty Page 29 dari 47
4.9 Calculation Result Based on Finite Elements Method With Software Plaxis As Device
Title: Revision 00
Temporary Jetty Page 30 dari 47
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 31 dari 47
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 32 dari 47
Title: Revision 00
Temporary Jetty Page 33 dari 47
Title: Revision 00
Temporary Jetty Page 34 dari 47
Sand filling comes from the beach and sedimentation in the area below will be dredged to a depth of 1 meter
Title: Revision 00
Temporary Jetty Page 35 dari 47
2. Gravel
Gravel will be prepared from around West Nusa Tenggara
6. MANPOWER
• 1 Person Project Manager
• 2 Person Supervisor
• 4 Person Operator
• 12 Person Labor
• Speedboat from Kayangan Port to Poto Tano Port = 20,5 km (1,5 hours)
Title: Revision 00
Temporary Jetty Page 36 dari 47
Northern Route
Southern Route
Title: Revision 00
Temporary Jetty Page 37 dari 47
• Trucking from Jamuna Jetty to Jago 10 Laydown or designated Parking Area by AMNT (1 day)
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 38 dari 47
The construction of temporary jetty will include the following two main items:
The jetty structure will be supported with jumbo sandbag on the front and side before being dumped with quarry course.
This is also to optimize quality and minimize the potential environment impacts and risk inherent in marine working like
tendering the barge to the jetty, or against the sea wave.
Typically the construction of the temporary jetty would be staged from foreshore using excavator, operators, and labor
plus supervision. Dozer will be required to leveling the ground and maybe compactor can be used.
Bollard installation will use long arm excavator and embedded to the sea bed up to 3 meter in order to get bollard
strength more than 9 Tons against tensile force. Distance of the bollard will be based on the mooring arrangement.
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 39 dari 47
Working area on the foreshore will be limited for the dump truck traffic and as necessary will be kept to be limited to the
safe working minimum to undertake the construction activities. Vehicles access to the jetty will be strictly controlled and
working areas and access track will be clearly remarked and fenced as appropriate with line and sign.
Fuel will be required for the diesel power of our supported equipment and to minimize the number of fuel deliveries, we
will use our fuel drum to support our operation.
The jetty construction contractor will be required to demonstrate that detailed working practices and construction
methods are appropriate to ensure that sufficient measures will be in place to prevent construction materials and
equipment from entering the Project area.
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 40 dari 47
9. SCHEDULE
The planning implementation schedule is 4 months with details below:
SCHEDULE
WEIGHT ( 1ST MONTH 2nd MONTH 3rd MONTH 4th MONTH
NO SCOPE OF WORK VOLUME UNIT
%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 PERMIT 1 LS 2% 0.02
2 PREPARATION 1 LS 1% 0.01
3 MOBILIZATION 1 LS 9% 0.05 0.05
4 BOWLANK MEASUREMENT AND INSTALLATION 1 LS 3% 0.02 0.02
5 JUMBO BAG FILLING 1 LS 5% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6 JUMBO BAG INSTALLATION 1 LS 34% 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
7 GEOTEXTILE INSTALLATION 1 LS 6% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8 LANDFILL 1 LS 15% 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
9 COMPACTION 1 LS 16% 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
10 INSTALATION BOULDER 1 LS 6% 0.02 0.02 0.02 0.02
TOTAL 100%
PROGRESS PER WEEK 100% 9.9 6.6 3.5 4.8 6.1 6.1 6.1 6.1 6.1 6.1 6.1 6.1 7.7 7.7 7.7 3.0
PLANING
CUMULATIVE 9.9 16.6 20.1 24.8 31.0 37.1 43.2 49.3 55.5 61.6 67.7 73.8 81.6 89.3 97.0 100.0
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 41 dari 47
11. CONCLUSION
- The settlement that will occur at quay depth of 5.5 m is 1,761 m with 5,13 years of Long Term Settlement. As this
is Temporary Jetty that usage for short period of usage then the Long Term Settlement can be not calculated.
We only use Immediate Settlement as from the analysis using the finite element method (Plaxis), Total Extreme
Immediate Settlement is 25,15 x 10-3 m = 2,515 cm
- Jetty will be passed by cargo weighing 350 tons and distributed to 24 axles. Axle Load is 7,9 tons per axle line
with Ground Bearing Pressure is 3,5 ton/m2. Based on Jetty capacity calculation, the jetty is able to carry a
load of 6,85 T/m2. So, 3,5 ton/m2 < 6,85 ton/m2 (Ok)
- There are 6 points of mooring, each point of Boulders construct using 6 Pcs of Reinforce Concrete Block with
weight @2,4 tons. Total self weight of each set of Boulders is 6 x 2,4 tons = 14,4 tons. Boulder force maximum
is 4,75 tons for LCT 2000 DWT, 4,75 tons < 14,4 tons (Ok) and 5,5 tons for Barge 270 feet, 5,5
tons < 14,4 tons (Ok)
- Installation of Temporary Jetty include processing of permit will takes 4 months and demolished of Temporary
Jetty can be done for 2 months.
- Design of Temporary Jetty is using maximum for suitable LCT and Tug Barge. LCT is 2000 DWT and Barge is
maximum 270 feet. Operation for Loading/Discharging can be done in High – Low Tide with Ro-Ro (Roll On-Roll
Off) Method.
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 42 dari 47
APPENDIX
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 43 dari 47
Existing Condition:
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 44 dari 47
Title: Revision 00
Temporary Jetty Page 45 dari 47
During construction:
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 46 dari 47
Previous project: 250 tons load through the jetty using multiaxle trailer
Project: No Document K017-T12-0002
Jago Beaching Jetty Date 25/05/2023
Title: Revision 00
Temporary Jetty Page 47 dari 47