You are on page 1of 1

NAC Diesel Power Plant

Km. 10, Brgy. Quezon, Surigao Cit

Effluent On-Site Test Date : May 06, 2023

SAMP[LING Time pH Average Standard Temperature Remarks/


SITE Taken 1 2 3 pH pH Degrees °C Action
O/W SEP #1
O/W SEP #2
O/W SEP #3
O/W SEP #4
O/W SEP #5
O/W SEP #6
TRIB CNL 1
TRIB CNL 2
TRIB CNL 3
RCP ER
RCP EHR

Legend:

O/W SEP #1 = Oil and Water Separator #1


O/W SEP #2 = Oil and Water Separator #2
O/W SEP #3 = Oil and Water Separator #3
O/W SEP #4 = Oil and Water Separator #4
O/W SEP #5 = Oil and Water Separator #5
O/W SEP #6 = Oil and Water Separator #6
TRIB CNL #1 = Tributary Canal #1
TRIB CNL #2 = Tributary Canal #2
TRIB CNL #3 = Tributary Canal #3
RCP E ROAD = Reinforced Concrete Entrance Road
RCP E HR = Reinforced Concrete Entrance Highway Road

Prepared by:

Cesar C. Gabaca
Safety/Environmental Officer and PCO

Conformed by:

Martiniano M. Montemor
Resident Plant Manager