You are on page 1of 2

K GOWDA & CO

KSPH NAGARBHAVI
PLINTH BEAM SCHEDULE

D BLOCK
SL NO DESCRIPTION NO OF DAYS
STARTING DATE COMPLETION DATE

1 PLINTH BEAM OF 3 UNITS 16/07/2018 25/07/2018 10DAYS

2 PLINTH BEAM OF 3 UNITS 26/07/2018 31/07/2018 6DAYS

PLINTH BEAM OF 2 UNITS


3 1/8/2018 6/8/2018 6 DAYS
& LOBBY AREA

C BLOCK
SL NO DESCRIPTION NO OF DAYS
STARTING DATE COMPLETION DATE
PLINTH BEAM OF 3 UNITS 23/07/2018 28/07/2018 6DAYS

PLINTH BEAM OF 3 UNITS 29/07/2018 3/8/2018 6DAYS

PLINTH BEAM OF 2 UNITS


4/8/2018 11/8/2018 8 DAYS
& LOBBY AREA

THANKING YOU

SCHEDULED BY

K GOWDA & CO. SRI SAI CONSTRUCTIONS


K GOWDA & CO
KSPH NAGARBHAVI
PLINTH BEAM SCHEDULE

DATE OF REVISED SCHEDULE : 28/07/2018

D BLOCK
SL NO DESCRIPTION NO OF DAYS
STARTING DATE COMPLETION DATE

1 PLINTH BEAM OF 4 UNITS 16/07/2018 25/07/2018 10DAYS

2 PLINTH BEAM OF 4 UNITS 26/07/2018 31/07/2018 6DAYS

C BLOCK
SL NO DESCRIPTION NO OF DAYS
STARTING DATE COMPLETION DATE
1 PLINTH BEAM OF 4 UNITS 1/8/2018 4/8/2018 4DAYS

2 PLINTH BEAM OF 4 UNITS 4/8/2018 7/8/2018 4DAYS

THANKING YOU

SCHEDULED BY

K GOWDA & CO. SRI SAI CONSTRUCTIONS

You might also like