ID Task Task Name Duration Start Finish Predecessors Resource Names Sep 2, '18 Sep 9, '18 Sep 16,

inish Predecessors Resource Names Sep 2, '18 Sep 9, '18 Sep 16, '18 Sep 23, '18 Sep 30, '18 Oct 7, '18 Oct 14, '18 Oct 21, '18
Mode S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
1 NCP GO-LIVE PLAN 150 days? September 4, 2018 March 29, 2019
2 Process and Configuration Finalization 43 days? September 4, 2018 October 31, 2018
3 Process Finalization 5 days September 4, 2018 September 8, 2018
4 Finance Process Finalization 3 days September 4, 2018 September 6, 2018 Rakesh Agarwal,Vaibhav Kulkarni Rakesh Agarwal,Vaibhav Kulkarni
5 Distribution Process Finalization 3 days September 4, 2018 September 6, 2018 Kapil Paratkar,Sivasai Kapil Paratkar,Sivasai
6 Manufacturing Process Finalization 2 days September 4, 2018 September 5, 2018 Jayanta Kopulwar Jayanta Kopulwar
7 Transportation Process Enhancement Finalization
2 days September 7, 2018 September 8, 2018 5 Kapil Paratkar,Sivasai Kapil Paratkar,Sivasai
8 Technical Requirement Finalization 6 days September 6, 2018 September 12, 2018
9 Finance Custom Requirement Finalization2 days September 7, 2018 September 8, 2018 4 Rakesh Agarwal,Vaibhav Kulkarni Rakesh Agarwal,Vaibhav Kulkarni
10 Distribution Custom Requirement Finalization
2 days September 10, 2018 September 11, 2018 7 Kapil Paratkar,Sivasai Kapil Paratkar,Sivasai
11 Manufacturing Technical Requirement2Finalization
days September 6, 2018 September 7, 2018 6 Jayanta Kopulwar Jayanta Kopulwar
12 Custom Transportation Enhanement for 3 days
NCP September 10, 2018 September 12, 2018 7 Sujit Sujit
13 Menu Finalization 16 days? September 6, 2018 September 26, 2018
14 Finance Menu Finalization 1 day? September 7, 2018 September 7, 2018 4 Rakesh Agarwal,Vaibhav Kulkarni Rakesh Agarwal,Vaibhav Kulkarni
15 Distribution Menu Finalization 1 day? September 7, 2018 September 7, 2018 5 Kapil Paratkar,Sivasai Kapil Paratkar,Sivasai
16 Manufacturing Menu Finalization 1 day? September 6, 2018 September 6, 2018 6 Jayanta Kopulwar Jayanta Kopulwar
17 Environment Refresh 2 days? September 7, 2018 September 8, 2018
18 DV environment refresh from PY 1 day? September 7, 2018 September 7, 2018 4 Jyotirmoy,Sujit Jyotirmoy,Sujit
19 PY Environment Refresh from PD 1 day? September 8, 2018 September 8, 2018 15 Jyotirmoy,Sujit Jyotirmoy,Sujit
20 Cutover Data Migration Template Finalization
2 days? September 7, 2018 September 8, 2018
21 Finance Data Migration Finalization 1 day? September 8, 2018 September 8, 2018 14 Rakesh Agarwal,Vaibhav Kulkarni Rakesh Agarwal,Vaibhav Kulkarni
22 Distribution Data Migration Finalization
1 day? September 8, 2018 September 8, 2018 15 Kapil Paratkar,Sivasai Kapil Paratkar,Sivasai
23 Manufacturing Data Migration Finalization
1 day? September 7, 2018 September 7, 2018 16 Jayanta Kopulwar Jayanta Kopulwar
24 User Manual and Test Scripts Completion5 days September 8, 2018 September 13, 2018
25 Finance 4 days September 10, 2018 September 13, 2018 21 Rakesh Agarwal,Vaibhav Kulkarni Rakesh Agarwal,Vaibhav Kulkarni
26 Distribution 4 days September 10, 2018 September 13, 2018 22 Kapil Paratkar,Sivasai Kapil Paratkar,Sivasai
27 Manufacturing 4 days September 8, 2018 September 12, 2018 23 Jayanta Kopulwar Jayanta Kopulwar
28 Migration Preparation 2 days? September 13, 2018 September 14, 2018
29 Finance 1 day? September 14, 2018 September 14, 2018 25 Rakesh Agarwal,Vaibhav Kulkarni Rakesh Agarwal,Vaibhav Kulkarni
30 Distribution 1 day? September 14, 2018 September 14, 2018 26 Kapil Paratkar,Sivasai Kapil Paratkar,Sivasai
31 Manufacturing 1 day? September 13, 2018 September 13, 2018 27 Jayanta Kopulwar Jayanta Kopulwar
32 Technical Development & Testing Completion
13 days September 10, 2018 September 26, 2018
33 Finance 10 days September 10, 2018 September 21, 2018 9 Rakesh Agarwal,Technical Team Rakesh Agarwal,Technical Team
34 Distribution 10 days September 12, 2018 September 25, 2018 10 Kapil Paratkar,Sivasai,Technical Team Kapil Paratkar,Sivasai,Technical Team
35 Manufacturing 10 days September 13, 2018 September 26, 2018 12 Jayanta Kopulwar,Technical Team Jayanta Kopulwar,Technical Team
36 System Configuration Post Refresh 6 days September 17, 2018 September 24, 2018
37 System Configuration 4 days September 17, 2018 September 20, 2018
38 Finance Configuration 4 days September 17, 2018 September 20, 2018 29 Rakesh Agarwal,Technical Team,Vaibhav Kulkarni Rakesh Agarwal,Technical Team,Vaibhav Kulkarni
39 Distribution Configuration 4 days September 17, 2018 September 20, 2018 29 Kapil Paratkar,Sivasai,Technical Team Kapil Paratkar,Sivasai,Technical Team
40 Manufacturing Configuration 4 days September 17, 2018 September 20, 2018 29 Jayanta Kopulwar,Technical Team,Ravindra Danve Jayanta Kopulwar,Technical Team,Ravindra Danve
41 Master Data Upload 2 days September 21, 2018 September 24, 2018
42 Finance Master Data Upload 2 days September 21, 2018 September 24, 2018 40 Rakesh Agarwal,Technical Team,Vaibhav Kulkarni Rakesh Agarwal,Technical Team,Vaibhav Kulkarni
43 Distribution Master Data Upload 2 days September 21, 2018 September 24, 2018 40 Kapil Paratkar,Sivasai,Technical Team Kapil Paratkar,Sivasai,Technical Team
44 Manufacturing Master Data Upload 2 days September 21, 2018 September 24, 2018 40 Jayanta Kopulwar,Technical Team,Ravindra Danve Jayanta Kopulwar,Technical Team,Ravindra Danve
45 User Testing and Environment readiness27 Finalization
days September 25, 2018 October 31, 2018
46 User Process Testing and Confirmation15 days September 25, 2018 October 15, 2018
47 Finance 15 days September 25, 2018 October 15, 2018 44 Rakesh Agarwal,Technical Team Rakesh Agarwal,Technical Team
48 Distribution 15 days September 25, 2018 October 15, 2018 44 Kapil Paratkar,Sivasai,Technical Team Kapil Paratkar,Sivasai,Technical Team
49 Manufacturing 15 days September 25, 2018 October 15, 2018 44 Jayanta Kopulwar,Technical Team Jayanta Kopulwar,Technical Team
50 User Acceptance Testing and Fine Tune 12ofdays
System Configuration
October 16, 2018 October 31, 2018
51 Finance 12 days October 16, 2018 October 31, 2018 49 Rakesh Agarwal,Technical Team
52 Distribution 12 days October 16, 2018 October 31, 2018 49 Kapil Paratkar,Sivasai,Technical Team
53 Manufacturing 12 days October 16, 2018 October 31, 2018 49 Jayanta Kopulwar,Technical Team
54 User Acceptance Sign-Off 20 days November 1, 2018 November 28, 2018
55 Finance 10 days November 1, 2018 November 14, 2018 53 Rakesh Agarwal,Technical Team
56 Distribution 10 days November 1, 2018 November 14, 2018 53 Kapil Paratkar,Sivasai,Technical Team
57 Manufacturing 10 days November 1, 2018 November 14, 2018 53 Jayanta Kopulwar,Technical Team
58 Integrated Process Sign-Off 10 days November 15, 2018 November 28, 2018 57 Jayanta Kopulwar,Kapil Paratkar,Rakesh Agarwal,Sivasai
59 User Traning and Final Sign-Off based on Migrated
67 days Data November 29, 2018 March 1, 2019
60 Final User Testing and End User Training 60 days November 29, 2018 February 20, 2019 58
61 Transition Process 7 days February 21, 2019 March 1, 2019
62 Finance Transition 7 days February 21, 2019 March 1, 2019 60 Rakesh Agarwal,Technical Team
63 Distribution Transition 7 days February 21, 2019 March 1, 2019 60 Kapil Paratkar,Sivasai,Technical Team
64 Manufacturing Transition 7 days February 21, 2019 March 1, 2019 60 Jayanta Kopulwar,Technical Team
65 Go-Live & Support 20 days March 1, 2019 March 29, 2019
66 Go-Live 0 days March 1, 2019 March 1, 2019 64 Jayanta Kopulwar,Jyotirmoy,Kapil Paratkar,Rakesh Agarwal,Sivasai,Sujit,Technical Team
67 Support 20 days March 4, 2019 March 29, 2019 66 Jayanta Kopulwar,Jyotirmoy,Kapil Paratkar,Rakesh Agarwal,Sivasai,Technical Team

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Plan for Go_live
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: September 4, 2018
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 1
Oct 28, '18 Nov 4, '18 Nov 11, '18 Nov 18, '18 Nov 25, '18 Dec 2, '18 Dec 9, '18 Dec 16, '18 Dec 23, '18 Dec 30, '18 Jan 6, '19 Jan 13, '19 Jan 20, '19
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

Technical Team

Rakesh Agarwal,Technical Team


Kapil Paratkar,Sivasai,Technical Team
Jayanta Kopulwar,Technical Team

Rakesh Agarwal,Technical Team


Kapil Paratkar,Sivasai,Technical Team
Jayanta Kopulwar,Technical Team
Jayanta Kopulwar,Kapil Paratkar,Rakesh Agarwal,Sivasai

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Plan for Go_live
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: September 4, 2018
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 2
Jan 27, '19 Feb 3, '19 Feb 10, '19 Feb 17, '19 Feb 24, '19 Mar 3, '19 Mar 10, '19 Mar 17, '19 Mar 24, '19 Mar 31, '19 Apr 7, '19 Apr 14, '19 Apr 21, '19 Apr 28, '19
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Rakesh Agarwal,Technical Team


Kapil Paratkar,Sivasai,Technical Team
Jayanta Kopulwar,Technical Team

3/1
Jayanta Kopulwar,Jyotirmoy,Kapil Paratkar,Rakesh Agarwal,Sivasai,Technical Team

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Plan for Go_live
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: September 4, 2018
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 3
12 Custom Transportation Enhanement for NCP
Based on FInal Process related changes