Professional Documents
Culture Documents
Contents
1 Introduction......................................................... 2
1.1 Purpose ........................................................ 2
1.2 Scope ........................................................... 2
1.3 Disclaimer..................................................... 2
1.4 Conflicts with Mandatory Standards ............. 2
2 References ......................................................... 2
2.1 Saudi Aramco References............................ 3
2.2 Industry Codes and Standards ..................... 3
3 Rapid Impact Compaction (RIC) Concept .......... 4
4 Rapid Impact Compaction (RIC) Process ........... 5
5 Material .............................................................. 6
6 Rapid Impact Compaction Design ...................... 7
6.1 Depth of Treatment ...................................... 7
6.2 Spacing ........................................................ 7
7 Performance Control .......................................... 8
8 Key Features of Rapid Impact Compaction ........ 9
9 Specifications Compliance ............................... 10
10 Rapid Impact Compaction Trials ...................... 10
11 Quality Control and Quality Assurance ............. 11
12 Reporting .......................................................... 13
1 Introduction
1.1 Purpose
This Best Practice establishes guidelines and recommendations of the design and
quality control activities required for Rapid Impact Compaction (RIC) ground
improvement works. This Best Practice is intended for Saudi Aramco engineers
(mostly Project Management Team and Project Inspection Team) and engineers
working on Saudi Aramco projects.
1.2 Scope
This Best Practice provides the recommended requirements for quality control
and quality assurance plans which are vital for a successful Rapid Impact
Compaction ground improvement program. The quality control process is
ensuring the work shall deliver a ground arrangement that should meet the
requirements.
The plan performance program summaries the measures for the Rapid Impact
Compaction work, quality control documents these measures as well as the
testing conducted, and quality assurance involves evaluating the work and
testing and addresses any conformance issues.
1.3 Disclaimer
Using this Best Practice to monitor the Rapid Impact Compaction ground
improvement works for Saudi Aramco does not relieve the contractor from his
responsibility to verify the accuracy of any information presented or from his
contractual liability to provide safe and sound designs that conform to
Mandatory Saudi Aramco Engineering Requirements. The use of the
information herein does not guarantee that the resulting product will satisfy the
applicable requirements of any project. Saudi Aramco assumes no
responsibility or liability for any reliance on the information presented herein or
for designs prepared in accordance with this document.
In the event of a conflict between this Best Practice and mandatory Saudi
Aramco engineering requirements such as procedures and standards, the
requirement documents shall govern.
2 References
This Best Practice is based on the latest edition of the references below, unless
otherwise noted.
Page 2 of 14
Document Responsibility: Geotechnical Standards Committee SABP-Q-014
Issue Date: 8 June 2017
Next Planned Update: TBD Rapid Impact Compaction (RIC)
Page 3 of 14
Document Responsibility: Geotechnical Standards Committee SABP-Q-014
Issue Date: 8 June 2017
Next Planned Update: TBD Rapid Impact Compaction (RIC)
The method comprises of repeated lifting and dropping of the hydraulic hammer from a
pre-determined height on the points of a grid pattern. The points are typically positioned
on a grid pattern the spacing of which is determined not only by the subsurface soil
formations but also on foundations loading and geometry.
This method is applicable for dynamic compacting granular materials with low silt and
clay content. The Rapid Impact Compaction can be utilized for the improvement of
either shallow sandy natural materials or fills of granular nature which developed
through backfilling/reclamation.
The usage of the Rapid Impact Compaction is possible provided the following:
Presence of non-cohesive (sandy) materials.
Particles finer than No. 200 sieve shall not exceed 15%.
Depth of improvement not more than 4m.
This technique has been used for achieving the following:
To increase the bearing capacity of the soil.
To minimize settlements.
To reduce the liquefaction potential.
In summary, substantial improvement to shallow depths (up to 4m) can be
accomplished by the usage of Rapid Impact Compaction often with significant cost and
time saving when compared to other soil mitigation measures. Depth of improvement
with the Rapid Impact Compaction method is less than the deep compaction methods
applicable for same soil nature (e.g. vibro compaction, dynamic compaction) but it still
greatly overcomes the one achieved through the ordinary surface roller compactors.
Page 4 of 14
Document Responsibility: Geotechnical Standards Committee SABP-Q-014
Issue Date: 8 June 2017
Next Planned Update: TBD Rapid Impact Compaction (RIC)
The Rapid Impact Compaction was originally developed during the early 1990s in the
United Kingdom for accommodating the repair of damaged airfield runways on a fast
manner. More specifically, the craters created by the bombs were filled with granular
material. The Rapid Impact Compaction was applied at the top for rapid densification of
the sub surface materials and subsequent reinstatement of the airfield.
Rapid Impact Compaction typically is carried out by numerous compaction phases and
passes depending on the project specification criteria as well as the pre- treatment soil
formations. The Rapid Impact Compaction procedures are established through trials
based on which the optimum compaction parameters are defined.
The Rapid Impact Compaction method utilizes dynamic energy which is transferred by
a hydraulic hammer dropping from a pre-determined height on to a steel patented foot
(plate) which resting on the ground. The hydraulic driving hammer is mounted on a
specially designed arm equipped within a heavy excavator. This procedure is constantly
repeated within the same compaction point by rapidly raise and drop the hammer on to
the plate. Drop hits per minute can vary having values 40 to 80. Such energy is
transported to the sub surface soils on a safe and efficient manner since the steel foot is
attached to the ground at all time.
More specifically, a dense plug of earth is developed beneath the compaction print as a
result of the initial hammer drops. This plug is further advanced by subsequent blows
resulting on the compaction of the deeper layers. When the compaction foot cannot
further penetrate the soil surface means that no further deep compaction can be
achieved.
Hammer weights are ranged between 7tn and 16tn. Heights of drop can also vary
between 0.3m to 1.2m. Foot diameters are having values of 1.5m to 2.5m. The
compaction locations are arranged in patterns with center to center distances between
2m and 3.5m.
The arrangement of compaction is to work from the outside in, and hence densification
of the deepest formations to initially take place. Then, compaction of the upper zone by
reducing the grid spacing is occurred. The deepest sub surface formations that require
treatment benefit by the first phase through the utilization of a comparatively wide grid
spacing and reduced foot diameter as well as appropriate drop numbers from the
maximum height. An intermediate grid is then utilized for taking care the treatment of the
middle sub surface layers. The intermediate grid is defined as the mid-point (with
increased foot diameter) of the first phase where improvement works being undertaken.
Finally, a third face may be undertaken for treating shallow/surface soil formations if
project design criteria are not yet satisfied.
Page 5 of 14
Document Responsibility: Geotechnical Standards Committee SABP-Q-014
Issue Date: 8 June 2017
Next Planned Update: TBD Rapid Impact Compaction (RIC)
The grid arrangement of the Rapid Impact Compaction points and the other parameters
of the treatment (e.g., energy, phases, passes, number of drops per point) depend on the
characteristics of the soils and the improvement required to support the future facilities
within the settlement tolerances. The repeated weight drops resulting on ground surface
depressions (or prints). Such depressions are then backfilled by granular material either
on-site or imported.
5 Material
The Rapid Impact Compaction method densifies the loose sub surface granular soils
rapid, consistently, and with a high accuracy. The densification degree is monitored
through the settlement of fill that it is occurred. Normally, compaction is much more
effective at the center of the developed compaction point and decreases with radial
distance. Depths which Rapid Impact Compaction is applicable reaching not more than
4m.
The efficiency of Rapid Impact Compaction can reach depths ranging from 3m to 6m
depending on the local soil conditions and project requirements. Major restraint of the
Rapid Impact Compaction method is the presence of thin cohesive layers which can act
as a barrier to the impact energy which transmitted downwards resulting on depth
limitations in relation to the required compaction.
Within the Rapid Impact Compaction technique additional granular soil materials which
can be either in-situ or imported should be supplied. These granular material should
have the following characteristics:
Hard, inert, free of clay and organic materials, and well graded
Containing not more than 15% by weight passing the No. 200 sieve
Have a maximum particle size of 100 mm
Page 6 of 14
Document Responsibility: Geotechnical Standards Committee SABP-Q-014
Issue Date: 8 June 2017
Next Planned Update: TBD Rapid Impact Compaction (RIC)
Design of the Rapid Impact Compaction method should be addressed by the following:
Grid pattern spacing
Number of phases/passes as well as number of drops per treatment point
Treatment depth
Weight of the hammer
Drop height
Energy to be applied
Plate (foot) Diameter
Above mentioned parameters may be altered depending on the trial test results.
Well graded granular material with clay content less than 1%.
6.2 Spacing
The improvement degree is mostly governed by the spacing of the Rapid Impact
Compaction works. Main objective of the Rapid Impact Compaction method is
satisfactory strength-density-incompressibility at places in between compaction
points with the least number of points (maximum spacing) to be undertaken.
The circular area of effective compaction from the point of treatment is depends
not only on soil properties but also on specific characteristics, e.g., applied
energy, hammer weight, drop height, etc.
Page 7 of 14
Document Responsibility: Geotechnical Standards Committee SABP-Q-014
Issue Date: 8 June 2017
Next Planned Update: TBD Rapid Impact Compaction (RIC)
7 Performance Control
When any of the operating criteria (such as number of drops, settlement of the foot,
influence depth) exceeds a pre-determined cut off value the whole procedure is stopped
for the particular compaction point. In case that the pre-determined values are not
reached that means that the sub surface soils at certain depths are not applicable to be
improved through the Rapid Impact Compaction method.
Soil densities are increased when the Rapid Impact Compaction is utilized. The
technical requirements are measured by the level of densification achieved against the
specified project targets.
The grading of the materials to be used for filling the depressions should be tested in
accordance to ASTM standards.
Page 8 of 14
Document Responsibility: Geotechnical Standards Committee SABP-Q-014
Issue Date: 8 June 2017
Next Planned Update: TBD Rapid Impact Compaction (RIC)
Densifies the loose sub surface granular soils rapid, consistently, and with a high
accuracy.
Applicable to granular soils having fine content less than 15% (not applicable
for soft cohesive deposits).
Depths that can be improved by the application of Rapid Impact Compaction are
up to 4 m (larger depths can be enhanced - up to 6m - provided that soils are
well graded granular material with clay content less than 1%).
This technique is cost and time effective when compared to other compaction
techniques within shallow to medium depths (0 to 6m).
The Rapid Impact Compaction approach (for given soil conditions) can be
utilized as a substitute to the traditional backfilling operations where fill lifts and
roller compaction are used resulting on cost and time schedule benefits.
This technique can be utilized for compacting reclaimed granular soils of having
thickness not more than 4-6m.
Controls vibrations to 2 inches per second within 30 feet of the drop point.
Page 9 of 14
Document Responsibility: Geotechnical Standards Committee SABP-Q-014
Issue Date: 8 June 2017
Next Planned Update: TBD Rapid Impact Compaction (RIC)
9 Specifications Compliance
Based on improved soil properties as retrieved from the post quality control tests
technical requirements of relative density, bearing capacity, settlement, and
liquefaction should be justified through calculations for each specific case/post-
test. Alternatively, goal performance lines based on properties of the treated
ground can be initially established for skipping calculations at every single post
quality control test (optional).
Rapid Impact Compaction trials should be carried out to verify the compaction
process/compaction design parameters, the suitability of the proposed equipment and
accessories, and to confirm the competence of the soil treatment scheme.
Upon trial(s) completion a trial report should be developed including the following:
Assessment of the treatment test results including both the pre and post stages.
Rapid Impact Compaction should be undertaken according to the approved trial method
statements and associated drawings.
Page 10 of 14
Document Responsibility: Geotechnical Standards Committee SABP-Q-014
Issue Date: 8 June 2017
Next Planned Update: TBD Rapid Impact Compaction (RIC)
The test results and assessment will be compiled into a report and conclusions
should be obtained regarding increasing or decreasing the trial grids.
The quality procedure on the Rapid Impact Compaction comprises of the following
steps:
Compaction Process
Before commencing any soil treatment scheme a survey of the site should be
undertaken followed by pre-treatment penetration tests as well as appropriate soil
Page 11 of 14
Document Responsibility: Geotechnical Standards Committee SABP-Q-014
Issue Date: 8 June 2017
Next Planned Update: TBD Rapid Impact Compaction (RIC)
Prior of carrying out any ground improvement in a concerned area, the following
survey/geotechnical investigations are recommended to be performed:
Survey of existing ground levels shall be, initially, carried out within the area of
concern without which no ground improvement can be initiated.
Lab tests on samples retrieved from the exploratory boreholes shall include, but
not limited to, wet sieve analysis/hydrometer, minimum/maximum density,
strength, and carbonate content tests.
For the areas where soil treatment is to be executed trials are scheduled in consideration
to the intended Rapid Impact Compaction works. Different compaction elements
should be tested to define the ideal parameters:
When the trial has confirmed that the designated practices and procedures are effective
and meet the requirements, the ground improvement by Rapid Impact Compaction is
commenced.
The subsequent matters should be checked throughout the performance of Rapid Impact
Compaction production works:
Page 12 of 14
Document Responsibility: Geotechnical Standards Committee SABP-Q-014
Issue Date: 8 June 2017
Next Planned Update: TBD Rapid Impact Compaction (RIC)
Testing Procedures
Post treatment quality control tests including penetration and Plate Load tests.
Post treatment cone penetration tests (CPT) should be undertaken within two
weeks after execution of compaction works for comfortably allowing the
dissipation of excess pore water pressure.
The raw American Standard Code for Information Interchange (ASCII) data of
the post treatment cone penetration tests (CPT) should be submitted for review
and approval.
Based on above mentioned testing and subsequent evaluation the necessity for
either undertaking supplementary post treatment tests or additional/alternative
treatment method(s) should be decided.
12 Reporting
Page 13 of 14
Document Responsibility: Geotechnical Standards Committee SABP-Q-014
Issue Date: 8 June 2017
Next Planned Update: TBD Rapid Impact Compaction (RIC)
Revision Summary
8 June 2017 New Saudi Aramco Best Practice that establishes guidelines and recommendations of the
design and quality control activities required for Rapid Impact Compaction ground
improvement works.
Page 14 of 14