Professional Documents
Culture Documents
Articleicgst
Articleicgst
net/publication/261378558
CITATIONS READS
0 10,899
2 authors:
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Faida Hassan on 27 September 2017.
71
ICGST-ACSE Journal, Volume 10, Issue 1, December 2010
remote wind farm. In the end, section 6 provides N2: number of row of turbines
conclusions and directions for future research. N: total number of turbine to be placed on the
site
2. Dimension of wind farm via software
Alwin Mathematical modelling of frequency distribution of
2.1. Sizing techniques: [3]-[4]-[5]-[6] wind: distribution WEIBULL:
2.1.1.Wind power: As it is difficult to manipulate all of data on a
frequency distribution of wind, it is more convenient
P = ( 1 ) ρ SV 3
(1) for theoretical considerations to model the
2
frequency histogram of wind speeds by a
Vmoy = ∑ Vif i (2) mathematical function that continues through
P: wind power (kw), discrete values table. We can therefore choose the
ρ the density of air (Kg/m3) model WEIBULL [3]-[4]-[5]. Indeed, for periods
V: the average wind speed in (m / s) ranging from weeks to a year, the WEIBULL function
S: the area swept by the wind turbine in ( m 2) reasonably represents the observed rates. There is a
Vmoy: the average wind speed in (m / s) probability density function in the following form:
fi: Frequency in% of the wind speed Vi in P(V ) = (K C)(V C)k −1 exp(−( V C)k ) (6)
(m/s)to class i.
With:
i: class of wind speed
P (V): probability density of the velocity V
Vi: the wind speed in (m / s) at fi frequency
K: form factor of the curve (dimensionless)
C: scale factor of the curve (meter / second)
2.1.2. Energy provided by a wind turbine: The average wind speed can be found by
integrating the probability density is therefore the
E = Th × ∑ Pi (V ) fi (V ) (3) formula (6):
With: V = ∫ V P (V ) dv (7)
E: energy produced kWh. moy
Th: time in hours Or V moy = C Γ (1 + 1 k ) (8)
Pi (V): power (KW) given by the wind speed Vi Where Γ (x) is the mathematical function Gamma,
fi (V) : frequency of wind speed Vi defined by:
2.1.3. Capacity Factor ∞
The capacity factor assesses the degree of utilization Γ( x) = ∫0
e − t t x −1 dt (9)
of the turbine, it is defined as follows: We can deduce other important parameters such as
(4)
C(%)= (100× Pmoy) Pmax the average power:
Pmoy = 0.5 ρC 3 Γ (1 + 3 k ) (10)
These two powers Pmoy and Pmax are chosen for
the wind turbine. As the capacity factor is high, it is Thus, the distribution WEIBULL can facilitate many
certainly good choice of the wind turbine. calculations that are necessary for the analysis of
Pmax: maximum power delivered by wind data.
aerogenerator 2.2.1. Determination of WEIBULL parameters [4]-[5]:
Pmoy: average power delivered by Now, we must focus our attention on the
aerogenerator parameters K and C, as they are the key to using the
2.1.4. The total number of turbines to be placed on WEIBULL distribution. These parameters define the
the site [1] Conditions to be attained: shape and scale of the curve WEIBULL.
(N1 +1) * 10H <I The form factor, K (dimensionless), expressed in the
(N2 +1) * 3D <L. form of WEIBULL curve: A high value of K implies a
N = N2 * N1 (5) narrow distribution, with winds concentrating
Key: around a value, while a low value of K leads to
I: dimension of the field perpendicular to the widely winds dispersed.
prevailing wind direction. The factor C (m/s), determines the position of the
L: size of land parallel to the prevailing wind curve. Generally, its value is high for windy sites and
direction low for quiet sites. Various methods can be applied
D: rotor diameter of the machine to determine K and C from a given wind distribution.
H: height of the tower
N1: number of turbines per row
72
ICGST-ACSE Journal, Volume 10, Issue 1, December 2010
C = 1 . 125 V moy (1 − B )
K = 1 + 0 . 483 (V moy − 2 ) 0 . 51
B = 1 − 0 . 81 (V moy − 1 ) 0 . 089
(11)
This probability density function is called Rayleigh
distribution when K = 2
2.2.2. Changes in wind direction:
We can determine the dominant wind direction. The
alignment of the turbine is intended to capture the Figure 1.b: Wind potential of Tangier’s site
maximum energy available in the wind. Thus, in so
The annual review of the frequency distribution of
far as the ground permitted, wind turbines should
the wind speed gives the following information:
be aligned perpendicular to the predominant
The average speed of the site is: 6.04m/s. The
directions of the wind. In general, the wind direction
maximum speed of the site is: 25.4m/s. Speeds
is presented as a wind rose. predominant site varies between 2.5m/s and 11 m/s.
The parameters in the paragraph above "sizing
techniques" describe the characteristics of wind in 3.2. Daily variation / calm analysis [5]-[7] :
any site.
Winds are generally characterized by:
• The average speeds (hourly, daily, monthly
and annually).
• The predominant directions.
• The frequency of each of the speeds and
directions.
• Diurnal Pattern / Duration of calms / calm
analysis.
Figure 2. Daily variation / curve calm.
• A good knowledge of these characteristics
is important in so far as they are involved On the one Hand, the analysis of wind turbulence in
in: the site through the curve of the daily model allows
o The choice of wind turbines and the us if there is a continuity of service (Permanent
evaluation of their performance; Power) at the station. On the other hand, the curve
o The implantation (Proper orientation of calm analysis of the station in the form of sticks
wind). shown in Figure 2 shows the cumulative frequency
percentage for speeds below 2.5 m/s and 4.5 m/s
and remain for some time calm. The determination
3. Presentation of results of
of the frequency of calm is needed to determine the
dimensioning [5]- [7] speed boot of aerogenerator which will be used for
3.1. Wind Potential of Tangier’s site
energy production. Also, we need the frequency of
We processed and analyzed the data of station in
calm for determining the storage capacity of
Tangier of 369 days for an assessment of the wind
batteries included in the electrification systems
potential using the menu under "Annual Review". (independent), as well to ensure continuity servicing
We found the frequency distribution of wind speed production of energy.
as follows:
3.3. Predicted annual energy produced by the wind
farm based on the appropriate choice of wind turbine
[5]- [7]
The submenu "Prediction of Electric Power" is
designed to show the user the power measured in
MWh, the average power of the wind turbine
selected and the capacity factor, which assesses the
degree of utilization of wind turbine,
73
ICGST-ACSE Journal, Volume 10, Issue 1, December 2010
74
ICGST-ACSE Journal, Volume 10, Issue 1, December 2010
Table 1. Summary of the different technologies [6]-[8 ]-[9 ] of wind According to international standard: IEC
turbines
Speed Type of Reactive Disturbance remark (International electrotechnical committee 61400-21
control generator power created in of measurement and evaluation of power quality
the network
Fixed Synchronous Can be Mechanical More used in
characteristics of grid connected wind turbines. IEC
speed controlled oscillation large units 61400-21 involves: N10 = 10 and N 120 = 120.
With by the because the
gearbox current generator is
Pst: Compatibility levels at short time for flicker
excitation connected networks Low Voltage and Medium Voltage.
to the main
frequency Plt Compatibility levels at long time for flicker
(flicker). networks Low Voltage and Medium Voltage.
To evaluate the worst flicker, we take Kf (ψ) = 1.
Asynchronous Requires a Requires a Use in the past
correction soft start in small units.
4.3.3. Presenting the results of flicker calculations at
device device. Pcc [9]-[11]
cos(φ) Flicker
generation Table 2. The results of the flicker calculations at Pcc
A speed Asynchronous Requires a -Soft start Poor Active Power Numb Post Sccmin Emission of flicker
adaptable adaptation of correction device performance. power (KVA) er of connectin (MVA)
within rotor slipping device -Possible
limits resistance cos(φ) Harmonic (KW) unity g
with by continious During
gearbox adjusting
switching
the
slipping. operations
Pst=Plt Pst Plt
Variable Asynchronous Power Flicker Solution
Speed dual power factor reduced but technically Wind Park 2779 0.0491 0.0608 0.0584
Rotor control by
With frequency harmonics interesting
we must see
but
1000 1111.11 140
Post of 3379 0.0404 0.05 0.0480
gearbox converter Problem the investment Melloussa
rotor. cost
Post of 3199 0.0427 0.0528 0.0507
Asynchronous Requires a Requires a Solution Tanger
dual rotor correction system of technically
winding device soft start interesting but
cos(φ) device we must see The flicker factors below 1, which complies with the
the cost of
investment standard, have been obtained.
Rotor Multiple Can be Little Solution 4.4. Harmonics Calculation at PCC:
without Synchronous controlled disruption technically The harmonic current order h at the PCC due to N
Variable by the on interesting but
speed current networks. greater cost wind turbine [9]:
gearbox excitation compared to 1
the DFIG. I
I h = N α hi
n (11)
4.3. The fliker emission calculation
4.3.1. In continuous operation [9] Key:
Ihi: the harmonic distortion of current order h due
Sn to a single wind turbine.
Pst = Plt = N 0 .5 .C ( Ψ ). (9)
Scc n: the report of a transformer wind turbine.
C (ψ): coefficient flicker of 10.4 (value given by the
The coefficient α according to the order of
standard 61400-21).
Sn is the rated apparent power of the wind turbine. harmonics.
Scc is the apparent power of short-circuit at point of The rates of harmonic tension due to 140 wind
turbines at bus bar MT are in table 3.
common coupling (PCC).
Table 3. The rates of harmonic tension due to 140 wind turbines
4.3.2. During operations commutation harmonic odd total
Pst =
18
S cc
[
N . N 10 ( Kf (ψ ). S n ) 3 .2 ] 0 .31
Value relative
pair
0 ,28%
harmonics harmonic
1,19% 1,22%
(10) to 22kV
Plt =
8
S cc
[
N . N 120 ( kf (ψ ) S n ) ]
3 . 2 0 . 31
75
ICGST-ACSE Journal, Volume 10, Issue 1, December 2010
Table 4. The rates of harmonics required by ONE - Reasons for the choice:
kind of harmonic Pair odd It’s reliable, economic (cable transmission is the
Rate of harmonic 0,6% 1,5% same cable HV) and already operated by ONE
(National Office of Electricity) in Morocco at the
factory IDRISS 1.
• The rate of overall harmonic is therefore 5.3. Control and monitoring of wind turbines [5]
well below the 1.6% imposed by ONE [11]. 5.3.1. Solution based on PLC (Processing logic
• The rate of harmonic issued by all the wind control)
turbines is not embarrassing for the The configuration of the wind farm permits to
network and does not exceed the norms consider only one solution if it is based controller,
(limits prescriptives). for each turbine, we will install a mini-controller.
5.3.2. Reasons for choice:
5. Concept of remote wind park Maximum automation for a minimal investment,
5.1. Purpose of the remote [12] using a stand-alone and far simplicity of installation,
The remote is a powerful tool in management and programming and manipulation [13]-[14]-[15].
control. It improves the speed of intervention of 5.3.3. Architecture of the solution to be applied in
maintenance services and increases the the park of Tangier
performance and availability of machines. It is At the foot of each turbine mini-PLC is installed.
transmitted on a physical data and messages of The CPU will be installed in the room Melloussa and
breakdowns to a room monitoring. manages all micro-controllers before contacting the
5.2. Solutions proposed for remote for the park of supervisor PC installed in Tanger.
Tangier
5.2.1. Problem Analysis Wind
park
We want to monitor the wind farm in two different
locations: the village post of Melloussa and the post PLC
of the city of Tangier as shown in the following
diagram:
900m 25KM
melloussa Tanger
Wind Room Room PC
farm CPU
Melloussa Tanger
5.2.2 Data Transmission Figure 6. Architecture of the solution to be applied in the park of
Possible solutions Tangier
Each compact station at the foot wind turbine has a CPU: Central programmable unity.
telephone line from the central Melloussa. The latter PLC: Processing logic control (PLC micro)
The micro-robot (SIMATIC S7-200) meets the
is linked to the central Tangier by a high voltage
desired functionality [9]. Already operated by the
(225kV), we adopted the following solution:
wind Park of Tetouan in Morocco, the only
RTC HV drawback its high cost.
Wind Post of Post of 5.3.4. Solution based on a microcontroller
park Mellouss Tanger The number of entry / exit and the size of the
programs at each turbine are not important, so a
- RTC (Réseau Téléphone Comuté: phone network microcontroller based solution seems very
com muter) and transmission power line on the high reasonable, because it replaces the role of the
voltage line controller with a lower price.
Forwarded by RTC and current holders on the high-voltage line: 5.3.5.Choice of network topology [13]-[14]-[15]:
- Current holder link In the star topology, all stations of wind turbines are
connected directly to a server or a hub that is the
Post of Melloussa Modem I/E
central node through which all transmissions pass.
This topology allows to easily add equipment (one
cable per device in the limit of the server capacity).
Post Tangier Modem I/E
Network management is facilitated by the fact that
the equipments are directly searchable by the server
and all transmissions spend (centralization of
I/E : injector/extractor.
software). Moreover, a failure of terminal equipment
76
ICGST-ACSE Journal, Volume 10, Issue 1, December 2010
does not affect the operation of the rest of the (FLOWTEL) with a management software (XFLOW) to
network. However, it can lead to significant lengths secure and maximize the wind farms [13]-[17]:
of cable. It is more economical than the parallel bus.
And given the network structure, this solution is very
appropriate for our application.
In the case of topology bus, if the device is the
optical type, the adding operation is more difficult
because it requires cutting the fiber to the location
of the connection and that the stations located
downstream report to the server will be blocked.
NOTE. - The connection between the PC Melloussa
and wind turbines may also be performed by a RS
485: Figure 7. Structure of the remote management solution that will be
applied to the wind farm in Tangier.
There are two types of interface circuits:
asymmetrical and differential.
6. Conclusion
5.3.6. The asymmetric-RS232 interface:
Wind energy is a major contribution towards
Currently the RS232 interface is regularly used for
energy independence of Morocco. So, the present
almost devices on the PC.
works consists in feasibility study of harnessing
This standard requires a length of 15 m and has a
wind energy for turbine installation in Tangier’s site
low immunity to noise [13]-[14]-[15].
in northern Morocco. In the first of the study, we
5.3.7. The differential interface-RS485:
evaluated:
These standards provide a universal solution for
• The wind speed potential through the
transmission over long distances. It may be taken as
treatment of climatologically data of a
the solution for our case [1].
station, using software ALWIN for
5.3.8. Reason for the choice of RS485:
dimensions of wind parks.
It allows: a transmission distance up to 1200m, • The prediction of electrical energy
and a good immunity to electromagnetic produced in the site basically on the choice
interference. of wind energy converter.
As in our case, the distance is 900m and the site has • The determination of the direction of the
electromagnetic interference, this solution is wind energy converter in the site.
adequate. Indeed, we’re studied the integration of a wind
5.3.8. Communication protocol [13]-[15]: parks power production in the electric national
The link level protocol defines the set of rules on the network that have no negative effect on the electric
meaning of data in the order in which they are grid. However, it empowers the electric national
transmitted. It prevents access conflicts. network capacity. Eventually, we’re studied and
We can distinguish two communication protocols in suggested some solutions to apply remote
our case: Sequence of reading the information, and monitoring of the wind farm to optimize our
the other of writing exploitation of the power production.
5.3.9. Data processing at Melloussa:
Once the data is transmitted by the PC, the 7. References
database available at the central unit, will be treated [1] Y. Himri et al. “Prospects of wind farm
later by using the software. Example of software development in Algeria”. Desalination 239
Alwin studied in a first part of this work, with its (2009) 130-138
system of data acquisition [16]. [2] R. Sadur et al: “A review on global wind energy
5.4. Industrial solution proposed for remote and policy”. In journal Renewable and Sustainable
monitoring the wind farm of Tangier: Energy Reviews 14 (2010) 1744-1762.
According to industry solutions that we offered for [3] CDER-Edition-1999: Wind power in Morocco:
the data transmission and control and monitoring of Deposit and Design. Pages [27-102]
wind turbines, we can adopt the following solution [4] H. Mabchour, Doctoral Thesis of the University
that encompasses the advantages of the above Hassan II, Mohammedia: Study, modelling and
solutions: testing components of a hybrid system
The industrial solution that will apply uses a PLC combining solar and wind – performance and
design methodology. (1999)Pages [65-88].
77
ICGST-ACSE Journal, Volume 10, Issue 1, December 2010
78