Item Description of Works Unit Quantity Rate Amount

No
A. SubStructure
1 Earth work
1.1 Site clearing and removing 2 300
m

the top 200 mm thick soil


1.2 Bulk Excavation(BE) m3 52.92
1.3 Pit Excavation for footing(PE) m3 219.934

1.4 Trench excavation for m3 32.23


foundation wall(TE)
1.5 Back fill(BF) m3 105.95
1.6 Cartaway(CA) 3 257.214
m
2 Concret Work
2.1 lean concrete 2 159.78
m
2.2 Grade beams 3 12.2
m
2.3 Footing 3 37.4
m
2.4 slab m3 12.80505
3 MASONARY WALL
3.1 Foundation wall 3 93.047566
m
3.2 Hard core-area m2 138.6
B. SUPERSTRUCTURE
1 CONCRETE WORK
Columns 12.38
Beam 21.59
Stair case 1.89
2 Masonry work
20 cm HCB 3 480.8258
m
10 cm HCB m3 61.926
3 REINFORCEMENT
dia 8 plain bar kg 1167.4699
dia 12 plain bar kg 394.88472
dia 14 plain bar kg 2534.5048
dia 16 plain bar kg 3460.3646
dia 20 plain bar kg 4024.2221
4 Finishing
terrazzo tile m2 268.14
ceramic tile 2 9.8
m
plastering m2 1207.55
Painting 2
m 1207.055
C. Sanitary
hand wash basin pcs 10
shower pcs 4
water heater pcs 4
water closet pcs 4
Water tanker litre 5000
D. Installation
Pannel pcs 3
50A breaker pcs 1
32A breaker pcs 4
25A breaker pcs 2
16A breaker pcs 8
10A breaker pcs 10
Double 36W flourescent
pcs
fixture 10
Single 36W flourescent
pcs
fixture 15
Four 18W flourescent fixture pcs
22
Wall mounted luminaire pcs 25
Double 15W Edison screw
pcs
flouresent fixture 7
Single phase socket outlet pcs
42
Heavy duty single phase
pcs
socket outlet 4
Telephone line entry
pcs
manhole 1
TTJB Telephone socket to
pcs
telephone junction box 7
TTDJB-TV socket to TV & Dish
pcs
junction box 7
Dishline intake PVC Ф25mm pcs
1
Double pole two way switch pcs
42
Single switch pcs 9
Dimmer switch pcs 19
Intermediate switch pcs 4
Deep refrigrator pcs 2
Water heater pcs 4