Professional Documents
Culture Documents
2017
IE 323
Production Planning, Design and Control
QUIZ 1 - KEY
Oscorp Industries produces web-shooters and the net requirements for this specific item is
given in table below. The production of the web-shooter takes 2 weeks. Setup cost is $90 per
production, holding cost per unit per week is $1 and Oscorp Industries currently have
20web-shooters on-hand.
Fill out the below MRP table using Silver-Meal lot sizing rule and calculate total cost.
Week 1 2 3 4 5 6 7 8 9 10
Gross Requirements 0 0 60 20 15 60 50 45 15 35
Scheduled Receipts 0 10 0 0 0 0 20 5 0 0
Net Requirements 0 0 30 20 15 60 30 40 15 35
Time-phased net requirements 30 20 15 60 30 40 15 35 0 0
Planned order release 65 0 0 90 0 55 0 35 0 0
Planned deliveries 0 0 65 0 0 90 0 55 0 35
Ending inventory 20 20 30 35 15 0 30 0 15 0 0
y = (60,0,0,90,0,55,0,35)