Project Charter
Comments: Project manager will supply weekly updates on project’s current progress
as well as plans/goals for the following week. Monthly there will be a budget meeting
to ensure the project is operating within its budget. If there is anything major that
happens outside of the WBS the project manager will consult with the stakeholders
prior to making that decision.
This study source was downloaded by 100000870019183 from CourseHero.com on 09-05-2023 22:41:13 GMT -05:00
https://www.coursehero.com/file/112381704/Project-Charter-M3A1doc/
Cost Estimate
Project Name: Solar Farm
Construction Date: 15-Sep-21
Internal $/hour Internal External $/hour External Total Non-labor $ Total Cost
WBS Categories Labor $ Total Labor $ Total Labor
1. Initiating 30 $ 50 $ 1,500 $ - $ 1,500 $ 1,500
2. Planning 30 $ 50 $ 1,500 $ - $ 1,500 $ 1,500
3. Executing $ - $ - $ - $ -
3.1 Land development $ - $ - $ - $ -
3.1.1 Solar panels base
installation - $ - $ - 400 $ 50 $20,000 $ 20,000 $ 10,000 $ 30,000
3.1.2 Panels installation - $ - $ - 200 $ 50 $10,000 $ 10,000 $ 25,000 $ 35,000
3.1.3 Electrical connection - $ - $ - 200 $ 50 $10,000 $ 10,000 $ 8,000 $ 18,000
3.1.4 Transformer installation - $ - $ - 20 $ 60 $ 1,200 $ 1,200 $ 25,000 $ 26,200
3.2 Maintanence training 40 $ 50 $ 2,000 40 $ 50 $ 2,000 $ 4,000 $ - $ 4,000
3.3.Operational training 40 $ 50 $ 2,000 40 $ 50 $ 2,000 $ 4,000 $ 4,000
3.4 Stakeholder communications 40 $ 50 $ 2,000 $ - $ 2,000 $ 2,000
4. Monitoring and Controlling 500 $ 50 $25,000 $ - $ 25,000 $ 25,000
5. Closing 8 $ 50 $ 400 $ - $ 400 $ 400
Subtotal $ 147,600
Reserves $ - $ - $ - 14,760.0
Total 688 34,400 900 310 45,200 79,600 68,000 $ 162,360
Assumptions
Without knowing the current market for skilled labor or the price of materials my estimates would vary. I gave conservative numbers where I felt
there is room for some difference.