Professional Documents
Culture Documents
Hyderabad
Assistant Professor, Dept.of Civil Engineering, Lords institute of Engineering and Technology,
5
Hyderabad, mdameerullahkhan2014@gmail.com
Abstract: Proper planning and scheduling is very important in construction projects for
reducing and controlling delays of the project. Substantial amounts of time, money, resources
are wasted each year in a construction industry due to improper planning and scheduling.
With globalization the construction projects have become vast and complex. Planning of such
projects requires huge amount of paperwork, which can be reduced with the help of project
planning software. Providing good planning, proper organization, sufficient flow of resources
to a project cannot automatically achieve desired result. A warning mechanism must be
present which can alert the organization about its possible success and failures throughout
the project. The main objectives of this study are to plan, schedule, and track a residential
project with help of primavera software, study the results generated, it is possible to suggest
which method is suitable for the selected residential project. Also, to recommend measures to
the organization for enhancing their project planning skills for similar projects in future.
status of development in urban areas. The against time, resources and performance
time available to achieve this goal is schedule during execution of the project
shrinking. Here arises the need for and identifying lagging areas requiring
effective project management. Many timely attention and action whereas project
issues are being faced by construction controlling uses data from monitor activity
industry that must be taken care of. They to bring actual performance to planned
include time and cost overruns due to performance. The objective of this study is
inadequate project formulation, poor to plan, schedule and to budget a
planning for implementation, lack of Residential project with help of primavera
proper contract planning and management software, study the results generated, it is
and lack of proper management during possible to suggest which method is
execution. It has been estimated by suitable for the selected G+4.Commecial
analysts that average cost of a project goes Building project and also to recommend
up by 30 percentage compared to the measures to the organization for enhancing
budgeted cost. Observations show that their project planning skills for similar
proper skillful management is imperative projects in future. The traditional project
for the timely completion of the project management system cannot meet the
within estimated budget and with allocated demands of today’s projects, as
resources. Projects with good planning, tremendous amount of information and
adequate organizational machinery and data on a project are always changing.
sufficient flow of resources cannot Project managers from construction
Automatically achieve the desired result. industry state that their 70-80% time is
There must be some warning mechanism, spent on communication and 70% of
which can alert the organization about its project documentation is paper based. The
possible success and failures, off and on. main objectives of this study are to plan,
Project monitoring is the process of schedule, and track a residential project
collecting, recording, and reporting with help of primavera software, study the
information concerning project results generated, it is possible to suggest
performance that project manager and which method is suitable for the selected
others wish to know. Monitoring involves residential project. Also to recommend
watching the progress of the project measures to the organization for enhancing
their project planning for similar projects accounting personnel, clients, etc. These
in future. The contract scheduling are all the reasons that strengthen the
specifications mandate the use of critical significance of project management
path method (CPM) schedules for the techniques in construction projects.
management of many of the construction
Objectives of Project Management
projects. An understanding of the
underlying mathematics that form the basis The objectives of project management are:
prerequisite to use of Oracle Primavera® budget and specified time using Primavera.
(Pietroforte and Stefani 2004; Betts and mainstream themes related with the subject.
Lansley 1993). Performance related research is looming
large in the field of construction
Within all fields of study there is a need
management discipline, yet there have
for knowledge of the ways in which an
been few traditional literature reviews only
academic discipline develops and for
partially addressing performance related
strategic overview of main dimensions
issues and which do not address aspects
representing the subject matter and
and features of performance studied in
classifications of relevant research
different contexts.
methods and tools. In many disciplines,
studies that address these concerns are Lin and Shen (2007) analyzed construction
termed meta-analysis (Betts and Lansley management journals between 1998 and
1993). 2004 with a specific focus on performance
measurement. This investigation
In each academic discipline, there are
considered patterns of published output
major journals that have high impact
from peer-reviewed articles in mainstream
scores resulting in them receiving the
construction management journals. In this
largest number of submissions and which
regard, this paper addresses the following
therefore can be selective in choosing their
three objectives; a) To assess recent
content. An established refereed academic
performance research in construction
journal is a repository of good and novel
management journals. b) To map patterns
insights gained from data-based research,
in the articles that concerned performance
scholarly enquiry, rigorous analysis of
against proposed meta-analysis framework
experience and careful logical debate
constructs
about an issue or phenomenon (Betts and
Lansley 1993). Subramani and Chinnadurai (2015)
Discusses although the long-introduced
As Betts and Lansley (1993) indicated, the
Industrialized Building System (IBS) has
analysis of large numbers of papers can
promised to solve and improve the current
reflect important patterns and biases in a
construction method and scenario in our
discipline. Also, studies of research
country, but the IBS method has not gained
patterns can be important indicators for
enough popularity. One of the reasons is
understanding researchers' preferences and
due to lack of research works done to execution. The benefits of primavera are
quantifying the benefit of IBS especially in using quantified data, allowing project
construction time saving. In lieu with such managers to justify and communicate their
scenario, this study conducted to quantify arguments when senior management is
evidence of time saving in IBS application. pushing for unrealistic project expectations.
Primavera P6 is amazing software, which Proper risk management education,
is used not just by planners, but also training, and advancements in computing
managers, engineers, schedulers, and technology combined allow project
anyone else involved in planning, managers to implement the method easily.
management, reporting of a project.
Regina Mary and Rathinakumar (2015)
Primavera P6 has benefited every industry
Study deals with the methods that reduce
from aerospace to manufacturing,
time and cost constraints and resource 16
electronics to IT, Telecom to Civil, any
management. A construction of residential
more. Primavera is an amazing project
apartment is taken for this study which is
management software tool which is not
undergoing a time and cost overrun. The
just used by project managers. Designed to
constraints are reduced by using
make managing large or complex projects
techniques interconnecting activities
a piece of cake, Primavera is the ideal tool
properly an increasing the resources,
for anyone who is involved in planning,
schedules are prepared by means of
monitoring and reporting on the progress
Primavera software. The cost constraints
of any big task, development or venture.
can also be reduced by managing labour
Prabhat Kumar Sinha et.al. (2013) Aims resources of different categories. The
in providing time and schedule actual schedule of the project is considered
management by using primavera is a as base schedule. The base schedule is
useful technique for modelling and compared with the modified schedule
analysing project management. This paper using techniques which helps to reduce
is a conceptual paper that Projects are constraints. Schedule made by the
expected to be completion in schedule and technique interconnecting activities
help to project manager to control schedule properly gives a time difference for the
while achieving performance, quality and completion of the project of about 5
cost goals by proper planning and months from the baseschedule of the
project. Schedule made by the combination the construction is 18275 sq. ft. The
of the both techniques show the result of 7 number of flats at each floor is two with
months prior completion from the base typical floor plan of an area of 3735 sq. ft.
schedule of the project. for each flat.
The scope of work was divided into the The project was started on the month of
following steps: September-2022 and will be finished on
the month of May-2023. This actual
Collection of data and Specifications
construction of the residential building
of activities.
takes a long duration of one year for the
Study area characteristics.
completion of the project. The long
Identifying the Constraints
duration of a single project will lead to a
Preparing Actual Schedule for the
considerable increase in the cost of the
Project in Primavera
project. Therefore, reducing the project
Tracking the schedule of the project by
completion timeis necessary for
using Primavera (P6)
completing the project within the budgeted
Collection of data and Specification of cost and budgeted time. This on time
activities project completion and on budget
completion of project is the two factors
The data which is required for the schedule
which state the project is a successfully
of the project was collected from site. The
completed. Reason for taking a long
total numbers of activities that are required
duration of this project is identified by
for the schedule are listed out.
means of the primavera schedule report.
Specifications required for each item or
activity is collected from site to prepare Preparing Actual Schedule for the
schedule. Project in Primavera
Study area characteristics A real time Actual schedule preparation process starts
residential building which is to be started with the collection of data like project start
has taken as a case study for the project. date, activities involved in the construction
The construction is for a residential of a G+4 building with activities
purpose having G+4 and the carpet area of sequences, duration taken for each and
every activities, resources needed for each which have finished. Cost variance was
and every activities and its amount, cost calculated by the difference between the
spent for each and every activities. The earned value cost and the actual cost.
collected data are entered in the software
Planning, Controlling, and Managing
and the relations between the activities are
Projects
given as per its sequence of activities
collected. The process of scheduling in Before implementing Primavera to
primavera for the actual progress of work schedule projects, team members and other
and the report obtained for the actual project participants should understand the
schedule from the primavera software are processes involved in project management
prepared. This actual schedule and report and the associated recommendations that
is considered as a schedule for this project. help smooth the Primavera implementation
that supports your corporate mission. If
Tracking the schedule of the project by
you were driving to a place you had never
using Primavera (P6)
seen, would you get in the car without
The schedule that was prepared was directions or a map? Probably not. More
tracked and updated from September 6th to than likely you‘d take the time to plan your
May 8th and actual costs are calculated trip, consider alternate routes, and estimate
based on the updated schedule. Record your time of arrival. Planning the drive
actual start date for those activities which before you even left would help your trip
started. Record activity % complete for on- be more successful. And, along the way,
going or completed activities to 24 should you encounter road blocks or traffic
determine how much of the work has been delays, you would have already identified
completed. This should be based on work- alternate ways to reach your destination.
in-place relative to the total amount of Project management follows the same
work planned for the activity. Enter methodology and purpose—to achieve
Remaining Duration for in progress each project‘s goals, you need to plan them
activities. Remaining duration will be the in advance. Good project management is
amount of time required to complete the no longer an option in today‘s corporate
activity as determined from the status date. world. It is a critical tool to help your
Enter actual finish date for those activities company stay on target and accomplish its
goals. Simply stated, project management the constraints of time, budget, and
is the process of achieving set goals within staffing restrictions.
It is a hierarchical structure that identifies the company wide projects and enables
organization and management of those projects and enables organization and management of
those projects by means of subdivisions or levels.
Fig.1 EPS
PROJECT
There are three Access Modes: Shared Mode: Anyone who has access January also open the
project, calculate and display with their user preferences, and report different data from the
same project at the same time. Exclusive Mode: In order to open the projects exclusively, that
means the respective users alone can edit the projects information’s, other users cannot be
editable. Read-only Mode: In read-only mode the project information is displayed for all
users but the information is not edit by any of the user. It is just for viewing purpose only. In
this project we have made a project with the following specifications:
3) The Project Start date: 6trh September 2022. 4) Access Mode: Shared Mode
CALENDARS
They are used to set in a project and its resources’ working times to accurately reflect
resource availability information. The application uses your calendar assignments for
levelling resources, scheduling, and tracking activities. Calendar will display the working and
non-working time of an organization. Calendar will also represent the working days and
working hours in a day. Besides, national holidays, specified days, and project-specific
work/non workdays can also be declared
There are three types of calendars: - Global Calendar: It contains calendars that apply to all
projects. - Project Calendar: It is a separate pool of calendars for each project. - Resource
Calendar: It can be defined and applied to each individual resource. In this project we have
used 6X8 Global Calendar and given holidays for: December 24TH , September 26TH,
September 8ND, October 13TH , November 24TH , January 26TH , February 18TH , March
8TH , April 14TH,22ND and May 1 ST.