Professional Documents
Culture Documents
Matematik Keputusan: Decision Mathematics
Matematik Keputusan: Decision Mathematics
Matematik Keputusan
7 7 12 27
1 2
3 4
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 46 48 50
Akt Float D E F
A
B
1
1
C Resource Levelling
A B
C 15
D 0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 46 48 50 • A project requires resources to execute the activities.
Number of people
3
E 0
2 • These resources include the labor, equipment and materials
F 0
1 required to get the work done.
• In the ideal world, resources are unlimited and available as
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 46 48 50 required.
D E F • Yet, resources are generally not unlimited and the project
team needs to “level” out the use and consumption of
A B C
resources.
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 46 48 50
Number of people
5 6
1
25-Mar-20
7 8
9 10
11 12
2
25-Mar-20
Checking Q&A
In the example, the minimum no of workers required within critical time of 25 days
was 3
➢ Lower bound for the number of workers needed
𝑠𝑢𝑚 𝑜𝑓 𝑎𝑙𝑙 𝑜𝑓 𝑡ℎ𝑒 𝑎𝑐𝑡𝑖𝑣𝑖𝑡𝑦 𝑡𝑖𝑚𝑒𝑠
Pls send your questions to
=
𝑐𝑟𝑖𝑡𝑖𝑐𝑎𝑙 𝑡𝑖𝑚𝑒 𝑜𝑓 𝑡ℎ𝑒 𝑝𝑟𝑜𝑗𝑒𝑐𝑡 our WhatsApp's group chat
8 + 6 + 8 + 7 + 11 + 10 + 5 + 3 + 4 + 4
=
25
66
=
25
= 2.64 S𝑜 𝑡ℎ𝑒 𝑙𝑜𝑤𝑒𝑟 𝑏𝑜𝑢𝑛𝑑 𝑖𝑠 3
Simply means that it is impossible to complete the project using fewer than 3
workers. BUT it doesn’t guarantee that 3 workers is sufficient»refers to
scheduling diagram
13 14