TEST & COMMISSIONING CHECKLIST

FOR
Master Clock SYSTEM
REV 00

Reference No. CHK-KSAU-MCS-00


Table of Contents

1. Objective
2. Introduction
3. MCS PRE - Testing Procedure
4. Required Documents
5. Common Equipment’s
6. Testing Procedure
6.1.General
6.2.System Components
6.3.Power Supply
6.4.General Checklist and Handing Over Certificate
1. Objective

Testing and commissioning of Master Clock System.

2. Introduction

MCS Systems is a precision clock that provides timing signals to synchronize slave clocks as
part of a clock network. The system shall be installed on primary &redundant master clock
server connected to GPS antenna. Slave clocks shall be connected to the server through the
network.
3. MCS PRE - Testing Procedure
General

 Check the Hardware for primary and backup servers (installation,


connection cables, and power cord.)

 Check the operation of the Desktop workstation.

 Check the installation and operation of the master and slave clocks.

 Check the installation and operation of GPS antenna.

 Power Failure Test & grounding.


4. Required Documents

The following documents should be available prior to testing and commissioning:

Document Description
Single Line Diagram The overall system includes networking and receivers.
Rack Layouts Mainly fixation of equipment in each rack (front view)
Wiring Diagram Details wiring diagram

5. Common Equipment

Most of the racks have the following common equipment:

Equipment Description
System Server Control the operation of MCS
Master and Slave Clocks POE analog clocks & POE digital clocks
GPS antenna GPS antenna

6. Testing Procedure

6.1 General

Item Pass Fail Remark

Make sure that the Rack is installed in it is final


location permanently.
Make sure that all System Components are
assembled in the rack as per Rack-Layout
drawings.
Make sure that 220 AC power is available in the
Rack.
Switch on the Circuit Breaker in the Rack
Notice the fault LED in devices is off.
6.2 System Components

The following steps could be done to make sure above monitoring feature are applied in the
configuration:

Item Pass Fail Remark


Ensure the client workstation stability in Hardware
terms.
Ensure the client software is running normally, can
monitor clocks IP addresses and alarms.
Check interface with NTP Server
Check the cables termination and labeling.
Check the clocks are powered on and connected to
the network.
Check the connection and signal of GPS Antenna
After disconnect one of the clocks, the faulty status
should be reported.
Make a Short Circuit on one line, the faulty status
should be reported.
Check the accuracy of time of each clock and time
synchronization.

6.3 Power Supply

The following steps are sufficient for Power Supply testing:

Item Pass Fail Remark


Normal status should have Main & Battery LED off
while Output LED is light Green.
Lift-up 220vac CB. The system should switch back to
220vac supply smoothly without affecting the
system.
6.4 General Checklist and Handing Over Certificate

NATIONAL GUARD HEALTH AFFAIRS SPECIALIZED HOSPITALS IN REGIONS Date:

Station Ref. & Name:    

EMPLOYER: MAIN CONTRACTOR:

MCS COMMISSION CERTIFICATE

         

Device Location Configured Remarks

       

       

       

       

       

       

       

     

     

     

     

     

         

  Distributor SITE ENGINEER QC INSPECTOR

Signature      

Name      

Date      