You are on page 1of 61

EXECUTIVE 

SUMMARY 
 
SUPPLEMENTARY ENVIRONMENTAL IMPACT ASSESSMENT STUDY: COLOMBO PORT CITY 
DEVELOPMENT PROJECT 

Introduction 

This  Supplementary  Environmental  Impact  Assessment  (SEIA)  study  is  carried  out  for  the 
expansion of the reclamation area of the Colombo Port City project from an area of 200 ha, which 
was  approved  by  the  Project  Approving  Agency,  the  Department  of  Coast  Conservation  and 
Coastal Resources Management, subsequent to an Environmental Impact Assessment (EIA) study 
that was subject to public comments via a notice placed in newspapers on 11th June 2011, to an 
altered design comprising an area of 269 ha, together with the impacts of extraction of sand from 
the  identified  borrow  areas  and  quarry  material  required  for  the  entire  landfill  and  protective 
works.  The  above‐mentioned  EIA  for  200ha  did  not  cover  environmental  impacts  of  sand 
extraction  as  a  separate  and  inconclusive  Initial  Environmental  Impact  Assessment  (IEE)  process 
was adopted by the Sri Lanka Ports Authority in this respect, and this lacuna is being addressed via 
this SEIA study.  
 
Notwithstanding the EIA of 2011 for 200 ha being approved after the public review process, this 
SEIA study covers the entire reclamation footprint and the extraction of quarry material and sand 
required for the entire project.  
 
The Project Proponent to this SEIA, the Ministry of Megapolis & Western Development, appointed 
the Central Engineering Consultancy Bureau (CECB) as Lead Consultant to execute this SEIA study. 
This SEIA is guided by the following important principles: 
(a) Terms of Reference for the SEIA issued by the Department of Coast Conservation and Coastal 
Resources  Management  (CCD)  to  the  Ministry  of  Urban  Development,  Water  Supply  & 
Drainage  on  30th  August  2015  titled:  “Terms  of  Reference  For  the  Supplementary 
Environmental  Impact  Assessment  Report  of  the  Reclamation,  Dredging,  Construction  of 
Protection  Structures  such  as  Breakwaters  and  Revetments  and  Extraction  of  Sand  and 
Quarry  Material  required  for  reclamation  and  protection  works  for  proposed  Colombo  Port 
City Development Project”  
(b) The Terms of the Agreement entered into between the Ministry of Ports and Shipping, acting 
on behalf of the Government of Sri Lanka (GOSL), and CHEC Port City Colombo (Pvt) Ltd (the 
Project  Company),  signed  on  16th  September  2014  and  extended  on  17th  September  2015 
(hereafter referred to as the “GOSL Agreement”) and the Concession Agreement attached to 
the  said  GOSL  Agreement  as  a  binding  annexure  (hereafter  referred  to  as  the  “Project 
Agreement”),  stipulates  inter  alia  that  the  Sri  Lanka  Ports  Authority  (SLPA)/GOSL  is 
responsible for securing the required environmental permits and approvals. 
(c) The Decision of the Cabinet of Ministers on 17th June 2015 that authorized the UDA to step 
into the role of SLPA and, pending the required legal formalities being finalized, the Ministry 
of  Urban  Development,  Water  Supply  and  Drainage  would  to  take  responsibility  for 
implementing matters connected to this SEIA as the Project Proponent. With the UDA being 
assigned  under  the  Ministry  of  Megapolis  &  Western  Development,  this  Ministry  has  now 
taken over such responsibilities.  
(d) In terms of the Project Agreement, the Colombo Port City will be developed in two distinct 
phases, with required environmental approvals obtained in two phases as well as follows:  

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015       ES ‐ Page 1 

 Phase 1 EIA: For Reclamation, sand extraction and construction of coastal structures to 
protect the landfill and landscaping aesthetics for the proposed Colombo Port City. This 
SEIA  is  a  continuation  of  work  connected  to  Phase  1  and  being  carried  out  as  a 
supplementary  to  the  approved  EIA  for  200  ha.  Reclamation  works  will  re‐commence 
upon this SEIA receiving required approvals. 
 Phase  2  EIA: Construction of the buildings and infrastructure of the Port City.  This  EIA 
study  will  be  based  on  the  concept  master  plan  and  infrastructure  requirements 
submitted  to  the  UDA  (and  described  in  this  SEIA  in  Chapter  2).  The  construction  of 
permanent  structures/built  environment  on  the  landfill  will  take  place  only  upon 
receiving necessary approvals for the Phase 2 EIA study.  
 
Origins of Colombo Port City 
 
Expansion  of  the  Colombo  Central  Business  District  (CBD)  by  reclaiming  the  sea  was  originally 
proposed  under  the  Government‐initiated  Western  Region  Megapolis  Regional  Structure  Plan 
dated  July  2004,  prepared  by  the  Singapore  based  urban  planning  consultants,  CESMA 
International Pte. Ltd. According to the “Colombo Core Area Plan” of the Plan (referred to as the 
CESMA Plan), the Colombo CBD was to be expanded to release lands for real estate development 
by: 
(a) Reclaiming 145 ha of land from the sea to the South of the proposed Colombo South Port 
breakwater by 2010 (i.e. the current location of Colombo Port City) 
(b) Relocating  port  related  activities  at  the  existing  Jaye  Container  Terminals  (JCT)  to  the 
Colombo South Port, releasing around 76 ha of land for real estate development 
(c) Creating  221  ha  (145ha+  76ha)  of  new  waterfront  lands  adjacent  to  the  Colombo  Port, 
which  includes  a  marketable  land  extent  of  139.5  ha,  to  meet  the  real  estate  needs  of 
Colombo CBD up to 2030 
  
In  comparison,  the  Colombo  Port  City  project  proposes  to  create  a  total  land  area  of  269  ha 
including a marketable land area of 173 ha. Therefore, the marketable land envisaged under Port 
City  is  24%  higher  than  the  139.5  ha  land  extent  envisaged  under  the  CESMA  Plan,  within  the 
same geographic area. Moreover, the CESMA Plan envisaged the South Port reclamation and JCT 
area developments to commence in 2010 and meet the city’s land requirements for 20 years till 
2030.  The  Colombo  Port  City  development  plan  is  intended  to  span  a  25‐year  period  ending  in 
2040.  Accordingly,  under  both  plans,  the  average  land  extent  to  be  released  for  development 
works out to around 7 ha per annum.  
 
An  important  aspect  that  should  be  noted  when  comparing  the  CESMA  Plan  and  the  Colombo 
Port  City  Project  is  that,  under  the  latter,  the  entirety  of  the  proposed  new  land  area  is  to  be 
created by reclamation without any interference with and/or relocation of existing infrastructure, 
whereas under the CESMA Plan part of the new land was to be created by relocation of existing 
facilities at the Jaye Container Terminals 
 
Therefore, creating a landfill for real estate development adjacent to the Port of Colombo under 
the Colombo Port City Project is not a new concept. It is an initiative that falls within the broad 
parameters  of  the  master  plans  developed  by  CESMA  approximately  11  years  ago,  which  are 
currently being updated.  
 
If a large‐scale reclamation project was to be undertaken with  minimum impact to  the coast to 
capitalize on the advantage of the site being an area where sand would naturally accumulate, the 
only location technically and financially feasible is within the shadow of the southern arm of the 
breakwater  of  the  newly  built  Colombo  South  Port  Project.  The  new  South  Port  breakwater, 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015       ES ‐ Page 2 

funded by the ADB, was the most challenging Coastal/Port Engineering project undertaken in Sri 
Lanka. Apart from the breakwater extending 1.5 km perpendicular to the beach, thus acting as a 
protective barrier to Port City, dredging for the South Port involved an area of about 820 ha and 
the  reclaimed  area  covered  about  340  ha.  This  SEIA  report  will  demonstrate  that  Colombo  Port 
City developments covered under this SEIA has far less environmental impacts than the Colombo 
South Port. 
 
Colombo  Port  City  –  A  Collaboration  between  the  Project  Company  and  Government  of  Sri 
Lanka 
 
The  CPC  project  was  initially  conceived  as  a  public  sector/Government  funded  project  to  be 
undertaken by The Sri Lanka Port Authority (SLPA). Consequently, the SLPA commissioned at its 
own cost an “Initial Technical Feasibility Study” in April 2010 for the reclamation of land South of 
the new breakwater. Around June 2010, an EIA study was commissioned by SLPA also at its own 
cost  through  the  University  of  Moratuwa  (UoM)  for  a  reclamation  area  of  200  ha.  In  October 
2010,  the  UDA  completed  a  master  plan  study  based  on  the  above  mentioned  Initial  Technical 
Feasibility Study and submitted a Project Proposal to the SLPA for consideration.  
In  April  2011,  based  on  an  unsolicited  concept  proposal  submitted  by  China  Communications  & 
Construction Company (CCCC), the parent of the Project Company, the Government of Sri Lanka 
(GOSL) decided to not to commit public funds to construct the Port City Project and proceeded to 
negotiate  with  CCCC  to  implement  the  project  entirely  as  a  foreign  direct  investment,  with  no 
financial guarantees by the Government on the investment.  
After  a  2  ½  year  period  of  negotiation  with  a  Standing  Cabinet  Appointed  Review  Committee 
(SCARC)  and  a  TEC  represented  by  16  Government  organizations,  on  16th  September  2014  an 
Agreement  (referred  to  hereafter  as  the  “Project  Agreement”)  was  entered  into  between  the 
Project  Company  and  the  Secretary  to  the  Ministry  of  Highways,  Ports  and  Shipping  (acting  for 
and  on  behalf  of  the  GOSL).  The  Agreement  was  signed  and  the  project’s  construction  works 
ceremonially  inaugurated  on  the  same  day  in  the  presence  of  the  President  of  the  Peoples’ 
Republic of China and the President of the Democratic Socialist Republic of Sri Lanka, during the 
Chinese President’s State visit to Sri Lanka.  
During the period leading to the signing of the Project Agreement and in terms of the Agreement 
itself,  the  responsibility  for  carrying  out  the  required  environmental  studies  and  obtaining  the 
required  permits  and  consents  in  relation  to  the  reclamation  and  sand  extraction  has  been  the 
responsibility of the SLPA, and, in terms of Clause 3 of the above‐mentioned GOSL Agreement and 
the  Project  Agreement  annexed  thereto,  all  rights,  obligations  and  liabilities  of  the  SLPA  are 
deemed as rights, obligations and liabilities of the GOSL.  
The Project Agreement states that of the total marketable land area at Port City (i.e. land to be 
sold  or  leased  under  applicable  laws  in  Sri  Lanka  to  third  party  investors  for  development  after 
allowing for public parks, roads and beaches) shall be no less than 170 ha. Of this, no less than 62 
ha  will  be  allocated  to  the  GOSL/SLPA  (to  be  replaced  by  UDA)  and  no  less  than  108  ha  will  be 
allocated  to  the  Project  Company.  It  should  be  noted  that  the  allocation  of  marketable  land 
between  the  Project  Company  and  GOSL  would  be  carried  out  on  an  equitable  basis  where  the 
Project  Company  will  first  select  a  marketable  land  extent  of  less  than  10  ha  and  then  the 
Government  will  select  a  similar  extent.  This  process  of  alternative  selections  will  be  repeated 
until  such  time  one  of  the  Parties  has  reached  the  maximum  amount  of  marketable  land  to  be 
allocated to that Party. Therefore, the marketable lands allocated between the Government and 
Project Company will be in non‐contiguous blocks. Note that the public areas such as roads, parks, 
beaches will be under the GOSL/UDA/CMC 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015       ES ‐ Page 3 

In consideration of receiving its share of the commercially developable land (63 ha with a current 
market value of Rs 225  billion), the SLPA/GOSL would be responsible for ensuring the supply of 
utilities (water, power, sewerage) to the boundary of the reclamation site at a suitable connection 
point and with sufficient capacity as and when needed and improve the transport infrastructure 
leading  to  the  site.  This  is  a  common  arrangement  in  priority  investment  projects  where  the 
developer  meets  the  cost  of  all  common  infrastructures  within  the  site  and  the  Government 
agencies  concerned  provide  infrastructure  connections  to  the  periphery  (e.g.  industrial  parks, 
housing projects have been implemented in Sri Lanka on this basis) 
 
Objective of the SEIA Report – The two‐Stage EIA Process
 
Several  important  issues  were  raised  in  the  Initial  Technical  Feasibility  Study  of  2010  and  the  EIA 
study of 2011 for the 200 ha reclamation. They were: 
(a) The proposed Port City has to be developed in two stages. The first stage will be the landfill, 
the  offshore  breakwater  and  the  coast  protection  for  the  protection  of  the  landfill.  The 
Second Stage will be the planned development of Port City with all infrastructure and support 
services 
(b) If  there  is  a  modification  to  the  overall  design,  then  environmental  consultants  would  be 
commissioned to present an addendum to the EIA to confirm that the changes and resultant 
environmental  impacts  will  not  make  a  significant  change  to  the  findings  of  the  initial  EIA 
completed for 200ha. If changes to the design are significant then a fresh EIA will be carried 
out.  
(c) A detailed EIA will have to be carried out for the infrastructure development plan of the Port 
City and the proposed developments on the reclaimed land.  
 
The  objective  of  this  Supplementary  EIA  is  a  consequence  of  (b)  above:  that  is,  to  capture  the 
design changes since the completion of the EIA of 2011 and to subject to public scrutiny the aspects 
covered  in  the  Addendum  to  the  EIA  of  2013  and  subsequent  changes.  It  is  noted  that  the 
Addendum to the EIA of 2011 was not open to public comments in 2013. 
 
Varying  approaches  can  be  undertaken  for  environmental  studies.  It  is  the  prerogative  of  the 
Government policy makers led by the Project Approving Agency (PAA) to decide on the scope of the 
environmental  studies.  Accordingly,  the  respective  Government  appointed  review  committees 
evaluating the Port City project recommended to the Cabinet of Ministers to adhere to a 2 stage 
EIA  process  for  Port  City,  and  accordingly  provision  was  made  for  such  a  course  of  action  in  the 
Project Agreement signed between  the  GOSL and the Project  Company.  Therefore, as  mentioned 
earlier,  Colombo  Port  City  will  be  developed  in  two  distinct  phases,  with  required  environmental 
approvals obtained via two related EIA studies.  
 
This SEIA is therefore to be read as a Supplementary to the approved EIA of 2011. The Phase 2 EIA 
for  the  construction  of  the  buildings  and  infrastructure  of  the  Port  City,  including  traffic  impact 
assessment will commence in parallel or immediately after completing this SEIA study. 
 
 
Environmental Approvals leading to the current SEIA 
 
The  Department  of  Coast  Conservation  &  Coastal  Resources  Management  (CCD),  as  the  Project 
Approving  Agency  (PAA),  made  the  EIA  report  of  April  2011  for  200ha  available  for  public 
comments as required under Section 16 Sub section 2(b) of the Coast Conservation Act No 57 of 
1981. In this respect, the CCD placed advertisements in major newspapers on 21st June 2011 in all 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015       ES ‐ Page 4 

three  languages  informing  the  availability  of  the  report  for  review  at  11  locations  including  the 
CEA, UDA, CMC, GSMB etc. Public comments received were responded to as necessary.  
 
In view of the investment proposal submitted by CCCC, in 2012  proposing a reclamation area of 
233 ha, an Addendum report to the 2010 EIA was prepared by UoM and submitted via the SLPA to 
the CCD in September 2013. The main objective of the Addendum report to the EIA was to inform 
the PAA of a “deviation which has taken place to expand the project from 200 ha to 233 ha…”. 
This was accepted and on 23rd October 2014, the CCD issued a “Permit for a Development Activity 
under Part III – Section 14 of the Coast Conservation & Coastal Resource Management Act No 57 
of  1981,  for  reclamation,  dredging  and  construction  of  breakwaters,  revetments”.  This  permit 
contained 42 conditions of which condition No 40 states ”A Separate approval should be obtained 
from the CEA for extracting sand from the offshore to be reclaimed the proposed near shore area 
and submitted to this department prior to the commencement of the construction.” 
 
In parallel to the above process, the SLPA commissioned NARA to carry out two IEE studies for 2 
sand  borrow  areas  for  which  the  GSMB  issued  exploration  licenses  to  SLPA  for  purposes  of 
securing sand for the reclamation works to be carried out under the Port City Project. The CEA as 
the  PAA  for  this  study  provided  the  Terms  of  Reference  for  the  IEE.  Obtaining  the  required 
consents for the fishermen’s compensation program was a pre‐requisite for the CEA to grant the 
necessary  permits  to  dredge  sand.  Despite  almost  a  year  of  attempting  to  obtain  the  required 
consents, the SLPA encountered several roadblocks in fulfilling this task.  In the circumstances, the 
SLPA  could  not  obtain  the  required  sand  extraction  permits  from  the  CEA  for  the  identified 
borrow  areas  as  stipulated  in  the  development  permit  of  the  CCD  and  in  terms  of  the  Project 
Agreement, which assigned this responsibility to the GOSL/SLPA. 
 
The  Project  Company  commenced  sand  extraction  and  reclamation  works  on  16th  September 
2014 consequent to the GOSL’s wish to inaugurate the project at the time of the State visit by the 
President of China and in terms of Clause 4.1 of the Project Agreement, which states that “on and 
from the date of this Agreement, the Project Company shall design and carry out the reclamation 
works  in  accordance  with  the  Concession  Agreement”.  In  addition,  the  Project  Company  was 
granted  written  permission  by  the  SLPA  to  dredge  the  Colombo  Harbour  navigation  channel 
pending (as understood by the Project Company) the finalization of the two IEE studies by NARA 
for identified sand borrow areas.   
 
Under  the  above  circumstances,  where  in  terms  of  Article  12.1  of  the  Project  Agreement  the 
obligation  to  obtain  the  necessary/applicable  licenses  and  permits  is  a  responsibility  of  the 
SLPA/GOSL,  the  Project  Company  has  taken  the  position  that  sand  extraction  and  reclamation 
works commenced on 16th September 2014 on the basis of provisions contained in the Agreement 
itself and on the basis of written clearances provided by the SLPA. 
 
Subsequently,  the  new  Government  elected  on  8th  January  2015  appointed  an  Evaluation 
Committee  to  review  the  Port  City  project  on  30th  January  2015.  On  the  basis  of  certain 
conclusions reached by this Committee (without any consultation with the Project Company), on 
4th March 2015, the Cabinet of Ministers made a decision to suspend the construction works of 
the Port City Project. This decision was communicated to the Project Company by the Secretary 
Ministry of Ports, Shipping & Aviation on 6th March 2015.  
 
The  said  suspension  is  operative  to  date.  During  the  period  of  suspension,  the  Government  has 
made the following decisions, in consultation with the Project Company where necessary: 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015       ES ‐ Page 5 

(a) The GOSL Agreement of 16th September 2014 would be amended to inter alia permit the 
UDA to step into the role of the SLPA and the end date of the said GOSL Agreement would 
be extended by 6 months to inter alia facilitate the said transition 
(b) The  necessary  amendments  to  the  Project  Agreement  shall  be  effected  via  a  tri‐partite 
agreement  between  the  GOSL  represented  by  the  Ministry  in  charge  of  the  UDA  (the 
Ministry of Megapolis and Western Development), the UDA and the Project Company.  
(c) A  Supplementary  Environmental  Impact  Assessment  (SEIA)  shall  be  carried  out  for 
expansion of the reclamation area from 200 ha to  an altered design of 269  ha together 
with  the  impacts  of  extraction  of  sand  from  the  identified  borrow  areas  and  quarry 
material required for the altered design.  
 
This SEIA is a consequence of the aforesaid decisions taken by the Government. 
 
Objective and Justification of the Project 
 
The location of Port City takes advantage of twin attractions of proximity to the Colombo CBD and 
oceanfront  living  in  a  carefully  master‐planned  area.  This  is  a  tried  and  tested  formula  by  city 
centres  that  aspire  to  position  themselves  as  destinations  for  tourism,  living,  working,  shopping 
and  entertainment.  Also,  the  Colombo  CBD  has  limited  oceanfront  lands  available  for 
development,  especially  in  view  of  the  land  area  facing  Galle  Face,  formerly  occupied  by  the 
Defence forces, now being allocated to Shangri‐La and ITC Hotels.  
 
Presently, Colombo is not a “Destination”, but primarily a transit point for tourists. The average 
stay  by  tourists  is  roughly  1.6  nights  for  Colombo,  which  is  too  low  by  international  norms.  (In 
comparison, average stay at a beach location of a typical tourist to Sri Lanka is around 5.5 nights). 
The lack of vibrancy of Colombo in terms of shopping and entertainment is a significant deterrent 
to attracting South and East Asian tourists to Sri Lanka. Sri Lanka’s tourist arrivals being impacted 
by  cyclicality  (with  higher  arrivals  being  recorded  during  the  traditional  winter  season)  can  be 
largely attributed to Colombo not being a sought after tourist destination.   
 
Investment Details & Strategic Objectives of Colombo Port City 
 
The objectives of Colombo Port City as formulated by the Project Company are as follows:  
 To foster integrated oceanfront living within the CBD to provide high quality of life through 
world‐class  office,  residential  and  recreational  spaces  that  will  attract  tourists, 
professionals, entrepreneurs, managers and retirees. 
 Position Colombo as the most liveable city in South Asia  
 To  create  a  regional  business  hub,  a  city  with  a  distinct  brand  with  high  quality  public 
spaces  and  infrastructure  facilities,  attractive  to  local  and  international  developers  and 
investors 
 To  create  a  tourism  hub  with  a  unique  character  that  reflects  the  distinctive  local  culture 
and the existing urban fabric  
 To  design  and  build  a  sustainable  urban  city  space  that  adapts  to  local  climate,  creates  a 
comfortable micro‐climate and make efficient use of energy resources 
 
Colombo  cannot  become  a  destination  that  appeals  to  the  international  business  travellers  or 
tourists  with  ad‐hoc  and  fragmented  developments  and  without  distinct  positioning.  Therefore, 
Colombo  Port  City  provides  an  opportunity  for  the  old  and  historic  part  of  Colombo’s  central 
business district to seamlessly interface with a modern planned metropolis like no other in South 
Asia. 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015       ES ‐ Page 6 

 
The investor in Port City, CCCC, is a Fortune 500 (No 187) and public listed company in Hong Kong 
and among the world’s largest construction and real estate companies with assets of over $100 
billion. It is also the world’s largest dredging company having undertaken iconic land reclamation 
projects in China and the main dredging contractor for the world’s 2 largest reclamation projects – 
the  new  airport  projects  at  Hong  Kong  and  Macau.  The  total  foreign  direct  investment  in  the 
reclamation  stage  of  the  Port  City  envisaged  at  around  $1400  million.  CCCC  has  plans  to 
undertake  further  investments  in  a  real  estate  project  in  Port  City  upon  the  completion  of  the 
phase 1 investment in reclamation and the phase 2 EIA.  
The Project Company has also hired world‐renowned international consultants working together 
with local specialists to advise on various aspects connected to the development: For e.g: Atkins 
of UK: Master plan review; Aecom of USA: Utility design, road design and landscaping; Sweco of 
Sweden:  Overall  master  planning;  Jones  Lang  LaSalle  (JLL)  and  CB  Richard  Ellis  (CBRE)  of  UK: 
financial and marketing pre‐feasibility and CDR International of The Netherlands: technical review 
of designs of the contractor.  
The investment required for the breakwater and other protective structures (both submerged and 
above‐water)  of  the  Port  City  Project  is  around  $225  million.  Therefore,  in  order  to  recover  the 
cost  of  the  breakwater  and  the  allocation  of  63  ha  of  marketable  land  together  with  96  ha  of 
common  area  land  to  the  Government  (a  total  of  159  ha  or  59%  out  of  269  ha),  the  Port  City 
project, if made smaller, would not be financially viable to the investor. Stated another way, the 
Project  Company  will  retain  only  41%  of  the  reclaimed  land  extent  for  marketing  to  developers 
(110 ha of non‐contiguous land).  
It  is  noted  that  Port  City  will  have  around  45  ha  of  public  parks  (9  times  the  size  of  Galle  Face 
Green) anchored by a 22 ha Central Park and a well‐protected beach and so called lagoon (water 
area  between  breakwater  and  beach)  suitable  for  swimming  and  water  recreational  activities  – 
currently not available to residents in Colombo CBD. The reclaimed land area is also a function of 
the length of the Colombo South Port breakwater  and takes advantage of  the full length  of the 
shadow of the breakwater. 
 
Future Developments 
Permissible developments within the 269 reclaimed land area will be In keeping with Sri Lanka’s 
planning  and  building  regulations.  Developments  proposed  under  the  concept  master  plan  for 
Port  City  submitted  to  the  UDA  for  preliminary  planning  clearance  include  commercial 
establishments, residential, health and educational institutes, small businesses and services, arts 
and  entertainment,  community  developments,  marina  and  convention  facilities.  No  industrial 
activities will be allowed within Port City.  
 
Colombo  Port  City  will  be  implemented  over  a  25‐year  period.  There  is  no  future  addition  or 
expansion envisaged beyond the 269 ha area after the reclamation works covered under this SEIA 
study is completed.  
 
The  Hon.  Attorney  General  has  opined  that  the  UDA  cannot  be  a  signatory  to  the  Project 
Agreement replacing the SLPA as it lacks the legal capacity under the UDA Act. Upon creation of 
new land by reclamation of the sea, the entire Port City land will be gazetted under the Sri Lanka 
Lands  Ordinance,  a  subject  matter  falling  under  the  purview  of  His  Excellency  the  President  in 
terms of the said Ordinance. The UDA could therefore declare the land reclaimed by the Port City 
Project  as  an  “Urban  Development  Area”  only  after  the  reclamation  process  is  over  and  a 
declaration is made under the Lands Ordinance.  
 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015       ES ‐ Page 7 

Accordingly,  the  sovereign  rights  of  the  Government  of  Sri  Lanka  including  the  right  of  eminent 
domain, is applicable within the reclaimed land.  
 

Outline of Studies Carried Out 

A  comprehensive  review  of  the  modelling  work  and  preliminary  designs  carried  out  for  the 
Feasibility  Study  of  Port  City  were  undertaken  during  the  preparation  of  this  SEIA.  This  includes 
separate comprehensive 2D and 3D physical model test studies and numerical modelling studies, 
which  includes  interpretation  of  coastal  evolution  and  siltation  due  to  proposed  development, 
sediment  transport  modelling  considering  dredging  and  reclaiming  and  interpretation  of 
contaminant concentration at the Beira Lake outfall with the proposed mitigation measures.  

In addition, ground investigations have been carried out over a period of more than two years to 
better  understand  the  technical  requirements  that  would  need  to  be  taken  into  account  in  the 
implementation of the project. In summary, the following engineering studies have been carried 
out  and  reports  compiled  during  the  feasibility  and  environmental  study  phase  of  this  project 
using the services of local and international experts/organizations: 
 Wave climate modelling – LHI Coast & Water (LHI) 
 Hydrodynamic modelling (LHI) 
 Wave disturbance modelling (LHI) 
 Sediment transport modelling (LHI) 
 Sediment dispersal modelling (LHI) 
 Shore profile survey (LHI) 
 2‐D  Stability  physical  model  Test  on  Offshore  Breakwater  and  Revetment  for  Marina  – 
Tianjin Research Institute of Water Transport Engineering (TRIWTE) 
 3‐D  Physical  Model  study  Test  ‐  South  Part  and  North  Part  –  Nanjing  Hydraulic  Research 
Institute (NHRI) 
 Analysis (numerical modelling) of Coastal Evolution and Siltation – TRIWTE 
 Numerical modelling of Water Exchange – TRIWTE and LHI 
 Ground Investigations – Forth Harbour Design Institute 
 Water quality sampling and analysis (NARA) 
 Assessment of inland quarry material availability, permits, transportation routes, impacts 
etc. (GSMB Technical Services) 
 Model and ecological studies at reclamation area (University of Moratuwa) 
 Impacts on Beria Lake outfall and storm water drain outlets impacts due to the proposed 
development, including 3D numerical model (CDR International, Netherlands)  
 
Other important study reports this SEIA builds on include: 
 Colombo Port Efficiency & Expansion Project, Environmental Impact Assessment of 2005 
carried out by Scott Wilson.  
 EIA  Study  for  Proposed  Colombo  Port  City  (2011)  and  Addendum  thereto  (2013)  by  the 
University of Moratuwa, 

 
Summary of Important Findings on Coastal Erosion  
 
The  South  Port  Project  breakwater  extends  2km  in  length  perpendicular  to  the  coast.  This  can 
potentially create erosion north of Colombo. However, monitoring over the last 4 years or so has 
confirmed  erosion  has  not  taken  place.  This  is  mainly  because  of  sediment  supply  from  Kelani 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015       ES ‐ Page 8 

River,  discharged  north  of  the  Colombo  Port.  The  construction  of  Colombo  South  Port  had 
increased the wave shadow, extending it northwards. As a consequence wave conditions in this 
area had become calmer, and the shoreline between the Colombo South Port and the Kelani River 
have remained stable after construction of the Colombo South Port 
 
The  Kelani  River  is  believed  to  contribute  some  100,000  to  200,000  m3/year  to  the  sediment 
budget  of  the  area.  Historically  this  is  believed  to  have  been  much  higher,  perhaps  400,000 
m3/year,  but  has  declined  due  to  sand  mining  and  development  upstream.  As  a  consequence 
there has been ongoing erosion of the coast to the north of the Kelani. Therefore, since Port City 
is in the shadow of the Colombo South Port breakwater, it has no impact on coastal erosion north 
of Colombo Port. 
 
The coastal stretch south of Colombo is stable with very little seasonal changes. The net longshore 
sediment transport along the west coast of Sri Lanka is predominantly directed towards the north 
as a result of the wave climate (South‐West monsoon sea waves and swell). Transport rates have 
been dominated by swell waves, with sea waves contributing little net transport. Most of the net 
transport  occurs  during  the  southwest  monsoon  season.  However  during  the  NE  monsoon  the 
sediment transport (as a result of waves from North West) is usually directed towards south for a 
limited period. Therefore, Port City has no impact on erosion South of the Colombo Port  
 
Moreover, when consider the shoreline change with this sediment transport rate for last 10 years, 
there is no significant accretion or erosion in the coastal stretch north or south of Colombo Port. 
The changes of shoreline of selected locations over the last 10 years corroborate this fact.    
 
When  dredging  is  taking  place  for  sand,  material  must  be  taken  away  from  the  active  dynamic 
zone,  where  waves  do  not  have  an  influence  on  the  seabed.  In  the  case  of  Port  City,  dredging 
areas have been identified on this basis. It must be emphasised however that the change of wave 
climate  due  to  natural  reasons  may  lead  to  movement  of  sand  which  can  take  place  anywhere 
around  the  island.  Accordingly,  studies  carried  out  and  extensively  described  in  this  SEIA  report 
and annexes clearly establish that Port City will not cause coastal erosion.  
 
Four  years  of  monitoring  of  the  Colombo  South  Port  Project  has  illustrated  that  the  turbidity 
represented  by  total  suspended  sediment  near  the  Kelani  River  outfall  has  been  always  greater 
than the mobile points around the dredging and reclamation sites (3 mobile station). This means 
that the natural environment has a greater impact on the ecosystem than arising from dredging 
and reclamation.  Sediment laden plume of the Kelani River can have an impact on ecosystem. It is 
noted that the sediment‐laden plume from the Kelani River covers the South Port region during 
heavy monsoon rainy weather. 
 
 
Material Required to Construct Port City 
 
To complete the Port City Project, a total of 2.83 mn cu m of quarry material and 65 mn cu m of 
dredged sea sand will be required. All the quarries identified for the supply of quarry material are 
either IML‐A or IML‐B grade quarries. Hence, such licensed quarries are bound to comply with the 
environmental regulations during the operations. Port City will obtain quarry material only from 
independent IML‐A licensed quarry suppliers who will individually obtain required local authority, 
environmental and transport permits.  
 
Sand is to be extracted from 2 areas designated by GSMB with exploration licenses EL/177 dated 
21st  June  2011  (Site  1)  and  Exploration  License  No:  EL/281  dated  8th  November  2013  (Site  2) 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015       ES ‐ Page 9 

issued to the SLPA. Under this SEIA, environmental impacts have been ascertained for these sites, 
which  comprise  a  combined  area  of  100  sq.  km  (46  sq.  km  for  Site  1  and  54  for  Site  2)  and  a 
dredge‐able/available sand quantity estimated at 112 mn cu. m (44 mn cu m for Site 1 and 68 mn 
cu m for Site 2) or almost double the sand requirement for completion of Port City.  
 
Supply of Quarry Material 
 
A  total  of  11  different  quarry  sites  with  required  approvals,  located  in  Kaduwela,  Hanwella, 
Padukka,  Delgoda  and  Divulapitiya  area,  have  been  surveyed  for  obtaining  quarry  material  for 
construction  of  necessary  structures  to  protect  the  reclamation.  According  to  GSMB  Technical 
Services  estimates,  the  required  quantity  of  Port  City  works  out  to  around  43%  of  the  quarry 
material available at these sites. Furthermore, the 11 quarry sites represent around 7‐9% of the 
total registered quarries in the Colombo and Gampaha districts. Consequently, the impact of this 
project on the national quarry material requirement would be negligible and therefore no price 
impact  to  the  construction  industry  according  to  the  GSMB  Technical  Services.  It  was  revealed 
during the GSMB study that most of the IML‐A category quarries are not operating due to lack of 
demand.  
 
Around  300  six  wheeler  trucks  and  38  ten  wheelers  are  to  be  used  for  transportation  from  the 
quarry sites to the project site. Transportation shall be done through two sessions, avoiding peak 
hours, and via six different routes to minimize traffic congestion.  
 
The trucks shall be covered to avoid any spilling of transported material or release of dust to the 
environment.  Dust  generation  during  the  transportation  via  unpaved  internal  roads  shall  be 
controlled  by  sprinkling  water  along  the  roads  at  regular  intervals.  Sprinkling  water  to  wash 
quarry materials loaded in trucks before unloading them at the stockpiling site shall minimize dust 
generation during the unloading. The movements of the wet returning trucks may cause Spitting 
mud along the road surfaces outside the project site. Washing the tires of the trucks, before they 
are moving out of the project site shall control this impact.  
 
There  is  facility  for  parking  for  about  75  trucks  around  the  port  gate  without  disturbing  moving 
vehicles along the road. As the gate will open at 7am, trucks will enter the stockpiling site through 
the road inside the port, which also mitigates road congestion.  
 
During  the  6‐month  period  of  construction  of  Port  City  from  September  16th  2014  to  March  6th 
2015,  prior  to  entering  into  supply  arrangements  with  quarry  owners,  the  Project  Company’s 
contractor ensured that the supplier had a valid Mining License and quantity supplied was within 
allowable  limits.  Moreover,  each  quarry  site  was  subject  to  inspection.  The  same  practice  will 
continue upon the recommencement of construction of the Port City Project.   
 
 
Dredging Methodology 
 
NARA,  who  was  commissioned  by  the  Project  Proponent  to  carry  out  the  marine  ecological 
studies  and  socio  economic  impacts,  and  LHI,  who  carried  out  studies  on  shoreline/coastal 
impacts,  have  recommended  guidelines  for  dredging  that  are  designed  to  minimize  impacts  on 
the coastal area, ecology and income from fisheries. The important applicable guidelines for sand 
extraction stipulated in this SEIA based on recommendations by NARA and LHI are as follows: 
1. Use  modern  dredging  methods.  It  is  stated  in  the  SEIA  report  that  4  modern  Trailing 
Suction Hopper Dredgers will be used in the dredging. 
2. Dredging  to  occur  3km  beyond  the  shoreline  and  at  water  depths  of  15m  or  more.  The 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015       ES ‐ Page 10 

dredging at 15 m depths will ensure that there will be no impact on coastal erosion based 
on nearshore activity and the 3km distances will minimize impacts on fishing routes and 
fishing activities. Moreover the 3 km minimum distance will ensure no impact on “ma dal” 
fishing.   
3. Obtain  no  greater  than  30%  of  total  sand  requirement  (30%  of  65  mn  cu  m)  from  SLPA 
Site 1 and the rest from Site 2. This is due to Site 1 having sensitive fish spawning areas 
4. Dredging depth to be limited to 2m from the surface of sediment on Site 1 and from site 2 
dredging  may  occur  at  greater  depths  provided  0.5  m  of  sediment  is  preserved  after 
extraction 
5. As much as possible, dredging has to be avoided in areas having fish spawning and unique 
habitat. 
6. Dredging to commence from Site 2 initially 
7. Allow fishermen to engage in fishing within the allocated dredging sites by giving proper 
notice in advance and after dredging work is done to re‐commence fishing. (This will be in 
accordance with COLREG regulations issued by the International Maritime Organization) 
8. Implement  an  income  support  and  benefits  program  to  fishermen  (outlined  in  detail  in 
Chapter 5 of this SEIA report and summarized below) 
 
Independent of this SEIA, as a mitigation measure, the Project Proponent, Ministry of Megapolis & 
Western  Area  Development,  has  directed  the  SLLRDC  to  enter  into  an  arrangement  with  the 
Project Company to supply sand from the adjacent 100 sq km borrow area assigned to SLLRDC for 
which environmental approvals have already obtained from the CEA for dredging sand in limited 
quantities to meet the requirements of the construction industry. This borrow area is estimated 
to have a dredge‐able sand quantity of 264 mn cu m, though subject to exploration studies being 
carried  out.  It  has  been  recommended  as  a  mitigation  measure  in  this  SEIA  that  once  SLLRDC 
obtains required environmental clearances to dredge its site, dredging activities in Site 1 would be 
reduced  even  further  from  levels  mentioned  above  or  curtailed  altogether.  On  19th  November 
2015, SLLRDC has secured concurrence from the CEA to dredge 4 mn cu m of sand based on the 
approved EIA of November 2007. SLLRDC intends to make this quantity available for purposes of 
Port City reclamation, pending carrying out further exploration to secure clearances from the CEA 
for extraction of up to 70 mn cu m for use by Port City and SLLRDC’s own use in the future. 
 
Assuming the sand available in the SLLRDC borrow pit is added as planned, the sand requirement 
for Port City is only 17% of the dredge‐able sand available within the 3 designated borrow areas. 
Considering an average dredging depth of 2 meters, the area to be dredged will be around 30‐40 
sq. km out of a total area of around 100 sq km allocated for SLPA sites 1 and 2 (or around 30‐40% 
of  area).  Assuming  that  the  borrow  area  allocated  to  SLLRDC  is  added,  thereby  increasing  the 
dredging area to 200 sq kms, the dredging area will reduce to only 15‐25% of the total allocated 
area.  Accordingly,  the  mitigation  measures  suggested  during  sand  extraction  such  as  avoiding 
fishing grounds and routes are feasible. 
 
 
Summary of Environmental Impacts & Mitigation  
 
To a substantial extent, environmental considerations have been incorporated into the planning of 
the  layout  and  the  feasibility  design  process  from  its  inception.  This  has  allowed  the  early 
identification  of  any  environmental  issues,  which  may  impose  constrains  on  the  design.  This 
approach  of  “Mitigation  by  Design”  has  reduced  the  need  for  a  range  of  specific  mitigation 
measures. The key findings from this SEIA study, potential impacts and solutions to mitigate these 
impacts are summarized below: 
 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015       ES ‐ Page 11 

1. There will be no reduction in fishing grounds in the reclamation area since this is not an 
ideal habitat for fish breeding due to already silted conditions. 
2. There will be some beneficial effects of using granite boulders and concrete elements for 
protection  works,  as  these  will  serve  as  suitable  habitats  for  fauna  and  flora.    Further, 
these will provide shelter for benthic animals that inhabit reefs such as lobsters and some 
fish.  In addition these boulders will serve as habitats for coral organisms as observed in 
the newly constructed breakwaters of the Hambantota port. Therefore, the populations of 
such animal may increase. 
3. Dredging will occur at or beyond the minimum stipulated depth of 15m to a maximum of 
30m. Such dredging depth is greater than the depth of closure and therefore no impact on 
the shoreline/coastal erosion. 
4. A comparison was made of the workability of a Cutter Suction Dredger (CSD) and a Trailing 
Suction Hopper Dredger (TSHD) working offshore during the monsoon and inter‐monsoon 
periods.  Based  on  the  environmental  and  production  considerations,  TSHD  was 
considered  to  be  the  most  environmentally  friendly  equipment  for  the  reclamation.  The 
proposed methodology of the use of TSHDs limits the impact of turbidity.  
5. As  and  when  necessary,  silt  curtain  will  be  installed  to  prevent  silt  migration.  The  silt 
curtain will be formed by polyester‐ fibre textile sheets to be hanged from buoys and be 
weighted  down  by  steel  chains.  An  opening  will  be  provided  to  allow  for  navigation  of 
TSHDs and other construction vessels in and out of the reclamation site.  
6. Sand dredging is expected to cause some temporary impacts by removing benthic fauna 
and  increasing  turbidity  as  a  result  of  an  increase  in  suspended  particles  in  the  water 
column.  The  proposed  dredging  area  experiences  turbidity  conditions  and  existing 
organisms  are  likely  adapted  to  high  turbidity  levels.  However,  the  above‐mentioned 
restriction of the dredge depth is expected to mitigate impacts.  
7. The  dominant  fish  resources  in  the  area  are  pelagic,  transient  species  that  are  likely  to 
avoid  unsuitable  environmental  conditions  and  return  once  normal  conditions  are 
established in the long term. The area selected for dredging has previously been dredged 
and as such is not a completely undisturbed habitat. As such it presents the best possible 
option compared to alternate sites that may be in a less disturbed state. 
8. Several  modelling  studies  were  carried  out  to  represent  Southwest  monsoon,  Northeast 
monsoon  and  non‐monsoon  periods.  During  this  period,  the  number  of  simulations 
performed was 21, which covers a period of 252 days. That is, each simulation was over 12 
days representing 50 dredging cycles, carried out 21 times (21 days x 12days = 252 days). 
Under this modeling frequency, all possible environmental conditions (monsoonal effects, 
tidal  effects,  wind/wave  pattern),  dredging  process  &  different  stages  of  dredging, 
relevant  dredge  sediment  data  were  taken  into  consideration.  A  significant  change  of 
sediment  transport  pattern  has  not  been  observed  in  the  vicinity  of  the  Port  City 
development. Clear sediment transport patterns are present in the surf zone and shallow 
areas.    Areas  where  the  depth  exceeds  16–18m  do  not  show  the  existence  of  any 
sediment  transport,  especially  under  sea  wave  conditions.  It  was  observed  from  the 
results  that  the  concentration  of  suspended  sediments  level  is  less  than  1.5x106  g/m3 
(1.5  mg/l)  for  almost  all  cases.  Although  spreading  is  occurring  up  to  certain  extent, 
concentration  of  the  suspended  sediment  is  less  than  2  mg/l,  which  is  insignificant. 
Therefore,  dispersion  of  fine  sediment  due  to  dredging  operations  should  not  have  any 
impact on the surrounding environment.   
9. The satellite remote sensing images of the project area obtained in 2002 and 2013 were 
digitally  enhanced  and  compared.  Although  there  have  been  minor  fluctuations  of  the 
shoreline,  there  has  not  been  any  significant  change  of  the  shoreline  during  these  11 
years,  even  after  construction  of  the  Colombo  South  Port.  The  construction  of  the 
Colombo South Port does not seem to have any significant impact on the evolution of the 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015       ES ‐ Page 12 

shoreline,  which  had  remained  stable.  It  should  be  noted  that  the  development  of  the 
Port City could, from the perspective of hydrodynamics, be considered as an extension of 
Colombo South Port. As such, the development of the Port City is not expected to cause 
any significant change of the shoreline 
10. A  numerical  model  was  built  specifically  for  assessing  the  impact  of  Port  City  on  the 
discharge from the Beira Lake outfall. This assumed the elimination of current sewerage 
discharge  into  the  Lake  will  not  be  finalized  by  the  Government  prior  to  completion  of 
reclamation  work  of  Port  City.  The  final  engineering  design  adpoted  at  the  Beira  lake 
outfall  will  not  block  the  outlet  but  will  streamline  the  continuity  of  the  discharge  and 
bring water further to the sea, improving dispersion and preventing any obstruction to the 
Beira outlet. The apporach proposed in this SEIA has the additional advantage as it allows 
for the formation of a beach close to Galle Face Green without obstructing the outlet.  
11. Existing storm water drain outlets around the site have been identified and solutions have 
been proposed to avoid any negative impacts for these drains.   
12. Siltation intensity within  the Port City is studied using  the numerical  model,  considering 
both  the  Southwest  Monsoon  and  the  Northeast  Monsoon.  It  is  concluded  that  the 
average computed siltation intensity within the lagoon of the Port City will be around 30 
mm  per  year,  and  normal  maintenance  dredging  should  be  sufficient  at  the  operation 
stage 
13. The  Colombo  South  Port  is  an  enclosed  water  area  connected  to  open  water  by  the 
navigation  channel.  Since  there  will  not  be  any  change  to  the  siltation  intensity  at  the 
navigation channel, it is not anticipated that there will be any change in siltation intensity 
within the Harbour.  
14. The mouth of the Kelani River is located about 4.5 km north of the Colombo South Port, 
and it is within the computation domain of the numerical model carried out for this study. 
From the change in the siltation intensity computed from the model, the construction of 
Port City will not have any impact on the siltation rate at the Kelani River mouth. 
15. The  construction  of  Port  City  on  the  southern  side  of  the  Colombo  South  Port  will  not 
cause  any  changes  the  hydrodynamics  and  sediment  transport  of  the  Colombo  Harbour, 
the Kelani river outfall and the northern coastal area. The impact is considered as low.  
16. Since  the  Port  City  is  to  be  constructed  on  the  southern  side  and  in  the  shadow  of  the 
main  east‐west  breakwater  of  the  Colombo  South  Port,  it  will  in  no  way  affect  coastal 
erosion north of the Harbour. The  coastline north of the Port  City is already shielded by 
the  breakwater  of  the  Colombo  South  Port,  which  has  prevented  any  transportation  of 
sediment between the south and the north. As such, the construction of the Port City will 
not change the pattern of littoral drift at the shoreline to the north. 
17. The coastal stretch south of Colombo is stable with very little seasonal changes. The net 
longshore sediment transport along the west coast of Sri Lanka is predominantly directed 
towards the north as a result of the wave climate (SW monsoon sea waves and swell). The 
comparison of the seabed profile between 2008 and 2012 indicates that the seabed close 
to the shoreline is stable over the four‐year period. According to the results of the survey, 
there is  no obvious deposition  close to the shore after the  construction of the Colombo 
South  Port.  It  indicates  that  the  influence  of  the  breakwater  on  longshore  sediment 
transportation is not very obvious. Therefore, the reclamation work and the construction 
of  the  breakwater  of  Port  City  are  likely  to  result  in  similar  insignificant  bathymetric 
change to the South of Colombo Port and the impact is negligible compared to the already 
constructed the South Port. 
18. Measurements  of  suspended  sediments  of  the  study  area  shows  the  TSS  range  of  2‐
25mg/l for different locations and different periods. Although spreading is occurring up to 
certain  extent,  concentration  of  the  suspended  sediment  is  less  than  2mg/l  which  is 
almost  equal  to  ambient  concentration.  Therefore  dispersion  of  fine  sediment  due  to 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015       ES ‐ Page 13 

dredging operations doesn’t show any impact to the surrounding environment 
19. The  navigation  channel  of  the  Colombo  South  Port  is  located  to  the  north‐west  of  the 
port.  Since  navigation  of  vessels  mainly  depend  on  the  wave  conditions  and  bed  level 
changes of the surrounding area, hydrodynamic and sediment transport modelling carried 
out in navigation channel showed no significant current increase or impact on the siltation 
intensity and therefore no significant impact on vessel navigation.  
20. The  reclaimed  land  has  no  impact  on  regulation  and  control  of  matters  related  to  civil 
aviation and aviation in general, in terms of the Civil Aviation Authority Act No. 14 of 2010 

The Port City Project is a collaborative venture between the GOSL/Ministry of Megapolis and the 
Project  Company  and  both  parties  would  work  together  to  ensure  required  social  and 
environmental obligations would be met. The latter is also important in considering that Port City 
will be positioned as an eco‐friendly environment for living and recreation.  
 
It  is  intended  that  the  Project  Company  and  the  GOSL/Ministry  of  Megapolis  &  Western 
Development/UDA  will  enter  into  an  understanding  on  mitigation  measures  and  resource 
requirements for implementing such measures. This takes into account that certain commitments 
for  mitigation  are  the  responsibility  of  the  GOSL  (such  as  the  income  support  and  benefits 
program for the fishing community).  
 
With  regard  to  improvements  in  social  infrastructure  in  the  vicinity  of  the  project,  the  Project 
Company has already committed to this aspect by providing over 45 ha (around 1/6th of the total 
reclaimed  area)  for  parks  and  other  recreational  spaces  within  Port  City  for  use  by  the  general 
public. The Project Company is committed to maintain the project site and undertake necessary 
mitigation  measures  in  keeping  with  the  approved  EIA,  this  SEIA  and  the  Ministry  of  Megapolis 
will adhere to and ensure the conditions in the development permit to be issued by the CCD to 
the Ministry upon approval of this SEIA will be adhered by the Ministry/UDA/SLPA and the Project 
Company.  
 
Income Support & Benefits Programme for fishermen 
 
This  SEIA  concludes  that  sand  dredging  is  expected  cause  local  and  temporary  impacts  on  the 
biological environment due to the removal of benthic fauna and increasing turbidity as a result of 
an  increase  in  suspended  particles  in  water  columns.  Hence  it  is  proposed  that  the  income 
support  and  benefits  programme  will  be  worked  out  in  detail  by  the  relevant  Ministries  and 
organizations / departments involved, with the inputs of community based organizations (CBOs) 
such  as  the  fishermen’s  societies,  churches,  etc.  As  mentioned  in  this  SEIA  study,  under  the 
Project Agreement entered into between the GOSL and the Project Company, formulation of such 
a programme and the disbursement of funds is the responsibility of the GOSL and not the Project 
Company.  
 
Accordingly, it is proposed that a sum of Rs. 500 million be allocated to the Ministry of Fisheries 
and Aquatic Resources Development via the Ministry of Megapolis and Western Development to 
meet the requirements of the proposed fisher community income support and benefits program, 
with supplementary funds allocated as needed, based on the evaluation of the effectiveness and 
actual impact of dredging on fishery and aquaculture after a one year period. The Rs 500 million 
will be deposited in a designated account in instalments for funds to be disbursed no less than on 
a  monthly  basis.  The  Department  of  Fisheries  and  Aquatic  Resources  will  finalize  the  overall 
budgets  and  guidelines  for  the  income  support  and  community  benefits  program  prior  to 
commencement of dredging and inform the fisher community and civic society at large. 
 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015       ES ‐ Page 14 

The Ministry  of Fisheries and  Aquatic Resources Development  together with the Department of 


Fisheries and Aquatic Resources will accordingly be responsible for formulating and implementing 
an acceptable community income support and benefits program for the affected fishermen. The 
key objective of the income support and community benefits programme will be to uplift of the 
social economic conditions of the fishing communities in areas such as: 
(a) Community development programmes 
(b) Research & development 
(c) Projects to uplift the social standards of the relevant fishing communities 
(d) Programs  to  enhance  the  marine  ecology  and  fish  breeding  grounds  and  other  related 
programmes  
(e) Income support to fishermen where direct impacts can be established 
(f) Capacity development of Fisheries Inspectors to improve fisheries monitoring 
(g) Establishment of a fisheries museum in Negombo 
The impact of the dredging and the implementation of the benefits program should be effectively 
and adequately monitored by the Ministry of Fisheries with continuous feedback provided to the 
Project Proponent in order to fine‐tune the program.  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015       ES ‐ Page 15 

 
 

CHAPTER 1  
INTRODUCTION 
 
1.1  Background of the Project 
1.1.1 The Western Region Megapolis Regional Structure Plan of 2004 
Expansion of the Colombo Central Business District (CBD) by reclaiming the sea was originally proposed 
under  the  Western  Region  Megapolis  Regional  Structure  Plan  of  July  2004,  designated  for 
implementation by the Western Region Megapolis Task Force and the Board of Investment of Sri Lanka 
(BOI). The Principal Technical Consultant to the Western Region Megapolis Master Planning Project was 
CESMA International of Singapore, currently known as Surbana Jurong Pte Ltd (Surbana), appointed by 
the Government of Sri Lanka in 2003. Surbana is a Singapore Government‐linked firm of urban planning 
consultants established around 50 years ago for master planning the urban landscape of Singapore. To 
date Surbana has completed urban planning studies in over 50 countries. 
According  to  the  Regional  Structure  Plan  of  2004  (hereafter  referred  to  as  the  CESMA  Plan),  the 
expansion of the Colombo CBD had several components: 
(a) To  create  new  land  banks  for  development  and  revitalization  of  the  water‐edges  to  form  the 
water front city image 
(b) To  relocate  existing  Jaye  Container  Terminals  (JCT)  within  the  proposed  Colombo  South  Harbour 
and release land for waterfront real estate developments to reinforce the new CBD fabric.  
(c) Figure 1.1: Proposed Port Expansion 
                                
                                    Jaye Container Terminal  North Port 

 
Source: Regio nal Structure Plan of the Western Region Megapolis (2004) Volume 1, page 61 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015  Chapter 1 ‐ Page 1 

 
 
 

(d) Subsequent  to  the  construction  of  the  ADB‐funded  new  Colombo  South  Harbour  breakwater 
(now completed), reclaim from the sea around 145 ha of land as an extension of the CBD by 2010. 
This is the same location as the current Colombo Port City as shown in Figure 1.1 
(e) Reclamation for the North Port by 2030 for port expansion and to provide lands for port related 
facilities  
Accordingly, the reclamation of land bordering the Colombo South Harbour breakwater was envisaged 
11 years ago under the Western Region Megapolis Regional Structure Plan. 
The  implementation  of  the  CESMA  Plan  was  abandoned  in  2005  primarily  due  to  a  change  of 
Government and the conflict situation that prevailed in the country. The Plan will however be reviewed 
and  updated  in  2015‐16,  again  with  technical  assistance  from  Surbana,  assisting  the  newly  created 
Ministry of Megapolis and Western Development. 
 
1.1.2    The Colombo Port City Project: The Administrative Process  
It is only with the advent of peace in Sri Lanka in 2009 and the commencement of construction of the 
ADB funded Colombo South Port with its 5.4 km long breakwater that reclamation of land south of the 
breakwater became technically and financially feasible.  
The  administrative  process  followed  by  the  former  Government  in  conceiving  and  developing  what  is 
now  known  as  Colombo  Port  City  (CPC)  is  summarized  below.  (Section  1.1.4  summarizes  the 
environmental approval process) 
(a) The  CPC  project  was  initially  conceived  as  a  public  sector/Government  funded  project  to  be 
undertaken by The Sri Lanka Port Authority (SLPA). 
(b) Consequently,  the  SLPA  commissioned  at  its  own  cost  an  “Initial  Technical  Feasibility  Study”  in 
April  2010  for  the  reclamation  of  land  South  of  the  new  breakwater  retaining  the  services  of 
coastal engineers (local and foreign) and urban planners.  
(c) Concurrently,  around  June  2010,  an  Environment  Impact  Assessment  (EIA)  study  was 
commissioned  by  SLPA  at  its  own  cost  for  a  reclamation  area  of  200  ha.  The  University  of 
Moratuwa  (UoM)  was  appointed  as  lead  consultant  and  the  Coast  Conservation  &  Coastal 
Resources Management Department (CCD) functioned as the Project Approving Agency (PAA) 
(d) In  October  2010,  the  UDA  prepared  a  concept  master  plan  for  the  area  to  be  reclaimed  and 
submitted a Project Proposal to the SLPA for consideration.  
(e) On  29th  April  2011,  China  Communications  &  Construction  Company  (CCCC)  submitted  an  initial 
concept proposal for Colombo Port City to SLPA for an envisaged reclamation area of 200 ha, with 
the entire financial investment for the project committed by CCCC as a Foreign Direct Investment 
(FDI), without any Government guarantees on the investment.  
(f) With the Government deciding to not to commit public funds to construct the Port City Project, a 
Standing  Cabinet  Appointed  Review  Committee  (SCARC)  was  appointed  to  review  the  above 
concept proposal submitted by CCCC. 
(g) In August 2011, SCARC, which comprised Secretaries of several Ministries, agreed to proceed with 
the  project  as  an  unsolicited  proposal  and  recommended  that  the  Secretary,  Ministry  of  Ports, 
Highways  &  Shipping  sign  a  non‐committal  MOU  between  the  SLPA  and  CCCC  and  to  obtain  a 
detailed proposal from the investor. SCARC also recommended appointing a Technical Evaluation 
Committee  (TEC)  comprising  members  from  SLPA,  CCD,  Urban  Development  Authority  (UDA), 
Board of Investment (BOI), and Central Bank. 
(h) Further  to  a  recommendation  by  SCARC,  the  MoU  between  SLPA  and  CCCC  was  signed  in 
November 2011.  

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015  Chapter 1 ‐ Page 2 

 
 
 

(i) In  October  2012,  CCCC  submitted  the  detailed  project  proposal  for  a  233  ha  reclamation  and 
preliminary  designs  to  the  SLPA.  The  Ministry  of  Ports  forwarded  this  to  SCARC  for  review  and 
negotiation by the TEC. 
(j) The TEC then submitted “Technical Evaluation Report 1” and “Technical Evaluation Report 2” to 
SCARC in March 2013 and July 2013 respectively. In August 2013, having reviewed the Technical 
Evaluation  reports,  SCARC  recommended  that  approval  of  the  Cabinet  of  Ministers  be  obtained 
for important commercial terms of the project.  
(k) Following  a  Cabinet  decision  dated  13th  January  2014,  the  Port  City  Project  was  identified  as  a 
Strategic Development Project under the Strategic Development Projects Act no 14 of 2008. 
(l) On  4th  September  2014,  the  Cabinet  of  Ministers  decided  inter  alia  to  implement  the  Colombo 
Port  City  Project  and,  subject  to  approval  by  the  Hon.  Attorney  General  (AG),  authorized  the 
Secretary to the Ministry of Highways, Ports and Shipping to enter into an Agreement on behalf of 
the Government of Sri Lanka with CHEC Port City Colombo (Pvt) Ltd, the BOI approved company 
set  up  to  implement  the  project  (the  Project  Company).  It  was  further  decided  to  authorize  the 
SLPA  to  carry  out  the  required  obligations  under  the  agreement  between  GOSL  and  the  Project 
Company. 
(m) On 16th September 2014 an Agreement was entered into between the Project Company and the 
Secretary to the Ministry of Highways, Ports and Shipping (acting for and on behalf of the GOSL). 
The Agreement was signed and the project’s construction works ceremonially inaugurated in the 
presence of the President of the Peoples’ Republic of China and the President of the Democratic 
Socialist Republic of Sri Lanka, during the Chinese President’s State visit to Sri Lanka. 
 
1.1.3  Key Terms of the Agreement between GOSL/SLPA and Project Company 
An  Agreement  was  entered  into  between  the  Ministry  of  Ports and  Shipping,  acting  on  behalf  of  the 
Government of Sri Lanka (GOSL), and CHEC Port City Colombo (Pvt) Ltd (the Project Company), signed 
on  16th  September  2014  and  extended  on  17th  September  2015  (hereafter  referred  to  as  the  “GOSL 
Agreement”)  and  the  Concession  Agreement  attached  to  the  said  GOSL  Agreement  as  a  binding 
annexure  (hereafter  referred  to  as  the  “Project  Agreement”).  The  key  terms  of  the  GOSL 
Agreement/Project  Agreement  entered  into  between  the  GOSL  and  the  Project  Company,  a  fully 
owned subsidiary of CCCC, can be summarized as follows:  
(a) In terms of Clause 3 of the GOSL Agreement, all rights, obligations and liabilities of the SLPA are 
deemed as rights, obligations and liabilities of the GOSL.  
(b) The GOSL Agreement binds GOSL, thereby making the GOSL responsible, to obtain the applicable 
permits  for  the  reclamation  works  including  environmental  permits  and  consents.  Accordingly, 
article 12.1 of the Project Agreement specifically provides that the SLPA (GOSL) shall obtain inter 
alia  the  following  applicable  permits  and  consents  necessary  for  the  design,  construction  and 
completion of the reclamation works ensuring that there is no delay or disruption to the execution 
of the reclamation works: 
 The environmental clearances pursuant to an Environmental Impact Assessment (EIA); 
 Sand Mining Licenses for sand borrow zone; 
 Approval from the Department of Costal Conservation and Costal Resources Management 
 Permits for quarry operations 
 Approvals  from  the  Department  of  Archaeology,  Marine  Environment  Protection  Authority 
(MEPA) etc 
Accordingly,  under  the  Project  Agreement  signed  on  16th  September  2014  and  later  extended 
via  an  Extension  Agreement  signed  on  17th  September  2014,  the  obligation  to  obtain  the 
necessary environmental approvals/permits is with the GOSL/SLPA 
 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015  Chapter 1 ‐ Page 3 

 
 
 

(c) The  Colombo  Port  City  will  be  developed  in  two  distinct  phases,  with  required  environmental 
approvals obtained via two EIA studies. Namely:  
 Phase 1 EIA: For Reclamation of no less than 233 ha, sand extraction and construction of 
coastal structures to protect the landfill for the proposed Port City 
 Phase  2  EIA:  Construction  of  the  buildings  and  infrastructure  of  the  Port  City,  including 
traffic impact assessment  
(d) The SLPA/GOSL would be  responsible for the supply of utilities  (water, power, sewerage) to the 
Boundary of the reclamation site at a suitable connection point and with sufficient capacity 
(e) The Project Agreement anticipated that the total area of marketable land (i.e. land to be sold or 
leased  to  third  party  investors  for  development  in  keeping  with  prevailing  laws  of  the  country) 
after allowing for public parks, roads and beaches shall be no less than 170 Hectares. Of this, the 
Project  Company  shall  be  allocated  no  less  than  108  Hectares  of  marketable  land  and  the  SLPA 
allocated no less than 62 Hectares. 
(f) The  allocation  of  marketable  lands  (no  less  than  170  ha)  between  the  Project  Company  and 
Government will be carried out on an equitable basis where the Project Company will first select a 
marketable land extent of less than 10 ha and then the Government will select a similar extent. 
This  process  of  alternative  selections  will  be  repeated  until  such  time  one  of  the  Parties  has 
reached  the  maximum  amount  of  marketable  land  to  be  allocated  to  that  Party.  Therefore,  the 
marketable  lands  allocated  between  the  Government  and  Project  Company  will  be  in  non‐
contiguous blocks. 
 
1.1.4  The EIA Process for Reclamation  
From the time the Colombo Port City project was to be implemented as a public investment in 2010 and 
after  the  submission  of  the  investment  proposal  by  CCCC  in  April  2011,  and  in  terms  of  the  above‐
mentioned GOSL/Project Agreement, the responsibility for securing environmental and related permits 
connected to the proposed project has been with the SLPA.  
Accordingly, the SLPA at its own cost carried out environmental studies for reclamation (with CCD as the 
PAA)  and  sand  extraction  (with  the  Central  Environmental  Authority  as  the  PAA)  in  parallel.  The  Lead 
Consultant  for  the  environmental  studies  on  the  reclamation  was  the  UoM.  For  sand  extraction,  the 
National Aquatic & Research Agency (NARA) functioned as the Lead Consultant.  
The  process  followed  by  the  SLPA  for  the  environmental  studies  connected  to  reclamation  is  outlined 
below:  
(a) The  CCD  as  the  PAA  appointed  a  Scoping  Committee  comprising  16  Government  agencies  to 
develop the Terms of Reference (ToR) for the EIA study in June 2010. They included the Colombo 
Municipal  Council  (CMC),  District  Secretariat,  Sri  Lanka  Navy,  Divisional  Secretariat,  Ministry  of 
Defence,  Ministry  of  Economic  Development,  Department  of  Fisheries,  Urban  Development 
Authority  (UDA),  Sri  Lanka  Tourism  Development  Authority,  CEA,  Road  Development  Authority 
(RDA), MEPA, Department of Archaeology, Geological Survey and Mines Bureau (GSMB) and Sri 
Lanka Land Reclamation and Development Corporation (SLLRDC).  
(b) In July 2010 the UoM commenced the EIA study and submitted the report, covering a reclamation 
area of 200ha, to the SLPA in April 2011. This was forwarded by SLPA to the CCD. 
(c) As required under Section 16 Sub section 2(b) of the Coast Conservation Act No 57 of 1981, the 
EIA report was made available to the Public. The CCD placed advertisements in major newspapers 
on 21st June 2011 in all three languages to inform the public of the availability of the report for 
review at 11 locations including the CEA, UDA, CMC, GSMB and Ministry of Fisheries.  

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015  Chapter 1 ‐ Page 4 

 
 
 

(d) On 20th Sept 2011, the CCD wrote to SLPA forwarding the comments received from the public for 
clarification.  Acting  on  behalf  of  the  SLPA,  the  UoM  clarified  in  writing  the  relevant  public 
inquiries, which were forwarded to the CCD by SLPA  
(e) By way of letter dated 7th December 2011, the CCD wrote to the SLPA stating that the TEC had 
granted preliminary approval to the EIA. 
(f) In view of the investment proposal submitted by CCCC in 2012 (after completion of the  EIA for 
200 ha) was for a reclamation area of 233 ha, an Addendum report to the EIA was prepared by 
UoM  and  submitted  via  the  SLPA  to  the  CCD  in  September  2013.  The  main  objective  of  the 
Addendum to the EIA was to inform the PAA of a “deviation which has taken place to expand the 
project (from 200 ha to 233 ha), primarily to accommodate the land component to be given to 
the  Government,  an  internal  canal  system  and  to  enhance  relevant  facilities  and  services  and 
improve integration with the South Port and City of Colombo”  
(g) The SLPA sought approval of the CCD to the Addendum to the EIA and, by way of letter dated 27th 
November  2013,  the  CCD  wrote  to  the  SLPA  communicating  no  objection  to  the  modifications 
proposed  to  the  EIA  by  the  said  Addendum.  A  key  condition  imposed  in  this  letter  was  that  an 
Environmental Management Plan (EMP) is submitted for approval by the CCD. 
(h) On  23rd  October  2014,  the  CCD  issued  a  “Permit  for  a  Development  Activity  under  Part  III  – 
Section  14  of  the  Coast  Conservation  &  Coastal  Resource  Management  Act  No  57  of  1981,  for 
reclamation,  dredging  and  construction  of  breakwaters,  revetments”.  This  permit  contained  42 
conditions  of  which  condition  No  40  states  ”A  Separate  approval  should  be  obtained  from  the 
CEA  for  extracting  sand  from  the  offshore  to  be  reclaimed  the  proposed  near  shore  area  and 
submitted to this department prior to the commencement of the construction.” 
(i) The  Environment  Management  Plan  (EMP)  was  submitted  by  the  SLPA  to  the  CCD  and  on  2nd 
December 2014, the CCD wrote to the SLPA stating that the EMP is approved. SLPA the wrote to 
the Project Company regarding the approval for the EMP. 
 
1.1.5  Sand Extraction & Basis for Commencement of Reclamation Works  
As stated above the SLPA obtained required approvals for the EIA study for reclamation of 200 ha and 
the subsequent Addendum thereto. This section examines the adequacy of consents obtained by the 
SLPA  for  commencement  of  sand  extraction  by  the  Project  Company,  particularly  with  regard  to 
obtaining required approvals from the CEA in keeping with Clause 40 of the Development Permit issued 
by the CCD. 
Sand extraction in open sea beyond the 2km coastal zone requires environmental clearances from the 
CEA as PAA, unless the CEA delegates such authority to another Government body in keeping with the 
provisions  of  the  National  Environmental  Act.  The  process  followed  during  the  2011‐2014  period  in 
connection with environmental approvals for sand extraction is summarized below: 
(a) In June 2011 the Director General of GSMB, under provisions of the Mines & Minerals Act No 33 
of 1992, issued to the SLPA an Exploration License No EL/177 for a sand borrow area of 46 sq. km 
(b) The  CEA  informed  the  SLPA  in  writing  that  an  Initial  Environmental  Examination  (IEE)  should  be 
carried out for sand extraction for the above borrow area. Thereafter, the CEA issued the ToR for 
the IEE to SLPA on 9th September 2011  
(c) The SLPA then commissioned NARA as the lead consultant to prepare the IEE report  
(d) In  September  2012  NARA  submitted  the  draft  IEE  report  to  the  SLPA  stating  that  the  identified 
area of 46 sq km contains a dredge‐able sand quantity of 44 million cu. m. 
(e) However, this quantum of sand was deemed insufficient to meet an estimated requirement of 65 
‐75 million cu. m. of sand to complete reclamation. Furthermore it was suggested that identifying 
additional borrow areas would mitigate the impact on fishing. 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015  Chapter 1 ‐ Page 5 

 
 
 

(f) The  SLPA  therefore  obtained  another  exploration  license  No:  EL/281  dated  8th  November  2013 
from the GSMB, covering an area of 54 sq. km.  
(g) The SLPA then commissioned NARA to carry out a second IEE study for the second borrow site and 
completed the draft IEE report in December 2014. Geophysical investigations carried out for the 
second  IEE  study  established  that  a  total  sand  deposit  of  68.3  mn  cu.  m.  was  available  for 
dredging. Accordingly, in studies covering both borrow areas, a dredge‐able sand quantum of 112 
mn cu.m, or around double the quantity of sand required by Port City for reclamation works, was 
identified.  
 
Obtaining  the  required  consents  for  the  fishermen’s  compensation  program  was  a  pre‐requisite  for 
the CEA to grant the necessary permits to dredge sand. Despite almost a year of attempting to obtain 
the  required  consents,  the  SLPA  encountered  several  roadblocks  in  fulfilling  this  task.  In  the 
circumstances, the SLPA could not obtain the required sand extraction permits from the CEA for the 
identified  borrow  areas  as  stipulated  in  the  development  permit  of  the  CCD  and  in  terms  of  the 
Project Agreement, which assigned this responsibility to the GOSL/SLPA. 
On the basis of the above, the SLPA did not have the required sand extraction permits from the CEA for 
the identified borrow areas. 
The Project Company commenced sand extraction and reclamation works on 16th September 2014 on 
the basis of the following: 
 Consequent  to the GOSL’s wish to inaugurate the project at the time of the  State visit by the 
President of China, the reclamation works commenced from the date of the said GOSL/Project 
Agreement, where and in terms of Clause 4.1 of the Project Agreement, it is stated that “on and 
from  the  date  of  this  Agreement,  the  Project  Company  shall  design  and  carry  out  the 
reclamation works in accordance with the Concession Agreement”.  
 In  addition,  the  Project  Company  was  granted  written  permission  by  the  SLPA  to  dredge  the 
Colombo  Harbour  navigation  channel,  pending  (as  understood  by  the  Project  Company)  the 
finalization of the two IEE studies by NARA for sand borrow areas.  
Under  the  above  circumstances,  where  in  terms  of  Article  12.1  of  the  Project  Agreement  the 
obligation  to  obtain  the  necessary/applicable  licenses  and  permits  is  a  responsibility  of  the 
SLPA/GOSL, the Project Company has taken the position that sand extraction and reclamation works 
commenced on 16th September 2014 on the basis of provisions contained in the Agreement itself and 
on the basis of written clearances provided by the SLPA. 
 
1.1.6   Other Permits secured  
Leading up to the commencement of construction and soon thereafter, in keeping with the provisions 
of  the  Project  Agreement,  the  SLPA  obtained  permits  mentioned  below  and  informed  the  Project 
Company in writing:  
(a) Letter  of  Approval  from  the  Department  of  Archaeology  dated  18th  July  2012  following  the 
Archaeological  Impact  Assessment  of  the  Colombo  Port  City  Project  done  by  the  Underwater 
Archaeology  Unit  of  the  Department  of  Archaeology  from  November  2011  to  February  2012 
pursuant to a request made by the SLPA by letter dated 22nd June 2010. 
(b) Industrial Mining License for Sea Sand No. IML/A/HO/8328 dated 16th September 2014 issued by 
the GSMB 
(c) Security Clearance and approval for commencement of the Colombo Port City Project dated 25th 
September 2014, granted by the Ministry of Defence & Urban Development. 
(d) Approval  for  the  Oil  Spill  Contingency  Plan  submitted  by  the  Project  Company  by  the  Marine 
Environmental Protection Authority dated 18th December 2014, issued under the Marine Pollution 
Prevention Act No. 35 of 2008 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015  Chapter 1 ‐ Page 6 

 
 
 

(e) Approval dated 2nd December 2014 granted by the CCD for the Environmental Management Plan 
(EMP) submitted by the Project Company via the SLPA  
 
1.1.7   The Suspension of Construction and Way Forward 
Subsequently, the new Government elected on 8th January 2015 appointed an Evaluation Committee 
to review the Port City project on 30th January 2015. On the basis of certain conclusions reached by this 
Committee  (without  any  consultation  with  the  Project  Company),  on  4th  March  2015,  the  Cabinet  of 
Ministers made a decision to suspend the construction works of the Port City Project. This decision was 
communicated to the Project Company by the Secretary Ministry of Ports, Shipping & Aviation on 6th 
March  2015.  During  the  period  of  suspension,  the  Government  has  made  the  following  decisions,  in 
consultation with the Project Company where necessary: 
(a) The GOSL Agreement of 16th September 2014 would be amended to inter alia permit the UDA 
to  step  into  the  role  of  the  SLPA  and  the  end  date  of  the  said  GOSL  Agreement  would  be 
extended by 6 months to inter alia facilitate the said transition 
(b) The  necessary  amendments  to  the  Project  Agreement  shall  be  effected  via  a  tri‐partite 
agreement between the GOSL represented by the Ministry in charge of the UDA (the Ministry of 
Megapolis and Western Development), the UDA and the Project Company.  
(c) A Supplementary Environmental Impact Assessment (SEIA) shall be carried out for expansion of 
the reclamation area from 200 ha to an altered design of 269 ha together with the impacts of 
extraction of sand from the identified borrow areas and quarry material required for the altered 
design.  
 
This SEIA is a consequence of the aforesaid decisions taken by the Government 
 
The evolution of the Project Area from the time of the original EIA to the current SEIA is summarized in 
Table 1.1 below 
Table 1.1   Project Area & Reclaimed Area Evolution 
EIA*  Addendum**  SEIA** 
Major Elements of Project (in Hectares)  2011  2013  2015 
Reclaimed land area    200    233.5    269 
 Beach area  Not specified  Not specified    19.79 
Canal area   None       23.7    15.24 
Water area between landfill & breakwater       161.8      113  
Seabed area occupied by protective structures          67.3     29.58  
Total Project Area   351.0    486.3    446.61  
Note: *   Based on designs commissioned by SLPA            
** Based on designs of the investor, CCCC  
 
1.2 Objective and Justification of the Project 
1.2.1   Objectives in Relation to Western Region Megapolis Structure Plan (CESMA Plan) 
 
The CESMA Plan of 2004 identifies a “Colombo Core Area Plan”, which has the following development 
objectives: 
(a) Colombo  to  be  the  economic  engine  of  the  country  and  contribute  to  improving  Sri  Lanka’s 
international competitiveness to realize its projected economic growth rate of 10% 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015  Chapter 1 ‐ Page 7 

 
 
 

(b) To develop and revitalize the city of Colombo as the financial and business hub of the South Asian 
region 
(c) To  attract  foreign  and  local  investors  to  share  the  responsibilities  for  accelerating  growth  and 
provide the resources needed to regain lost economic initiative 
(d) To attract tourists by making Sri Lanka their preferred destination 
(e) To increase infrastructure capacities while conserving the fragile environment 
(f) To make prime lands available for development 
 
It  is  noted  that  over  70%  of  lands  identified  for  development  within  the  Colombo  Central  Business 
District  under  the  CESMA  Plan  of  2004  were  water‐front  properties,  which  in  capital  cities  typically 
command a premium and considered more desirable to live and work. 
 
1.2.2   The Strategic Objectives of Colombo Port City 
 
The objectives of the Colombo Port City are broadly in harmony with the policy objectives enunciated 
in the CESMA Plan. The Port City project would reclaim 269 ha of waterfront land that will comprise 
around  173  ha  of  land  that  will  be  marketed  to  local  and  international  developers  to  undertake 
developments according to a phased master plan. The objectives of Colombo Port City as formulated 
by the Project Company are as follows:  
 Taking advantage of the natural accumulation of sand caused by the protection afforded by the 
South  Harbour  breakwater,  to  significantly  expand  the  Colombo  CBD  to  meet  the  demand  for 
such land over a 20‐25 year period 
 To foster integrated oceanfront living within the CBD to provide high quality of life through world‐
class  office,  residential  and  recreational  spaces  that  will  attract  tourists,  professionals, 
entrepreneurs, managers and retirees. 
 Position Colombo as the most liveable city in South Asia  
 To create a regional business hub, a city with a distinct brand with high quality public spaces and 
infrastructure facilities, attractive to local and international developers and investors 
 To create a tourism hub with a unique character that reflects the distinctive local culture and the 
existing urban fabric  
 To  design  and  build  a  sustainable  urban  city  space  that  adapts  to  local  climate,  creates  a 
comfortable micro‐climate and make efficient use of energy resources 
 
Therefore, the location of Port City takes advantage of twin attractions of proximity to the Colombo 
CBD and oceanfront living. This is a tried and tested formula by city centres that aspire to position 
themselves as destinations for tourism, living, working, shopping and entertainment.  
Also,  the  Colombo  CBD  has  limited  oceanfront  lands  available  for  development,  especially  in  view  of 
the  land  area  facing  Galle  Face,  formerly  occupied  by  the  Defence  forces,  now  being  allocated  to 
Shangri‐La and ITC Hotels.  
Presently, Colombo is not a “Destination”, but primarily a transit point for tourists. The average stay by 
tourists  is  roughly  1.6  nights  for  Colombo,  which  is  too  low  by  international  norms.  (In  comparison, 
average stay at a beach location of a typical tourist to Sri Lanka is 5.5 nights). The lack of vibrancy of 
Colombo  in  terms  of  multiple  shopping  and  entertainment  choices  is  a  significant  deterrent  to 
attracting  South  and  East  Asian  tourists  to  Sri  Lanka.  Sri  Lanka’s  tourist  arrivals  being  impacted  by 
cyclicality (with higher arrivals being recorded during the traditional winter season) can be primarily 
attributed to Colombo not being a sought after tourist destination.   
Colombo cannot become a destination that appeals to the international business travellers or tourists 
with ad‐hoc developments and without distinct positioning. Therefore, Colombo Port City provides an 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015  Chapter 1 ‐ Page 8 

 
 
 

opportunity  for  the  old  and  historic  part  of  Colombo’s  central  business  district  to  interface  with  a 
modern planned metropolis like no other in developing Southeast Asia. 
 
1.2.3   Permissible Developments within Colombo Port City 
 
Permissible  Developments  within  the  269  reclaimed  land  area  will  be  In  keeping  with  Sri  Lanka’s 
planning and building regulations and on the basis of the reclaimed land being gazetted  under the Sri 
Lanka  Lands  Ordinance  and  subsequently  as  an  Area  of  Authority  under  the  UDA  Act.  Samples  of 
permissible  developments  under  the  master  plan  for  Port  City  already  submitted  to  the  UDA  for 
preliminary planning clearance are given below. These are subject to the country’s investment laws and 
any other applicable statutes: 
 Commercial: Banks, offices and retail, hotels and restaurants, diplomatic embassies 
 Residential: Dwelling houses/units, apartment buildings, serviced apartments 
 Institutions: Healthcare, educational and R& D institutions  
 Small  businesses  and  services  and  allied  activities:  Open  air  trading  areas,  beauty  salons, 
bakeries,  laundries,  printing,  computer  repair,  small  scale  art  and  handcraft  workshops,  car  and 
bicycle  repair  and  service,  plumbing  and  carpentry  workshops  and  other  local  small  scale 
businesses and services such as cafes, kiosks, pavilions, newspaper stands, food trucks and book 
shops  
 Entertainment:  Indoor  amusement  and  entertainment  establishments,  outdoor  recreational 
spaces 
 Community: Art galleries, socio‐cultural establishments/community centres 
 Other:  Marina  and  related  facilities,  tourism  business,  convention  and  event  facilities,  cultural 
events and festivals 
 
No Industrial activities will be allowed within Port City. 
The Project Company has also hired world‐renowned international consultants working together with 
local  specialists  to  advise  on  various  aspects  connected  to  the  development:  For  e.g:  Atkins  of  UK: 
Master  plan  review;  Aecom  of  USA:  Utility  design,  road  design  and  landscaping;  Sweco  of  Sweden: 
Overall  master  planning;  Jones  Land  LaSalle  (JLL)  and  CB  Richard  Ellis  (CBRE)  of  UK:  financial  and 
marketing pre‐feasibility and CDR of Holland for technical review of designs by the EPC contractor.  
 
1.2.4   Forces that Produce Financial Centres: Some Theory 
 
A  key  objective  of  the  CESMA  Plan  and  the  Colombo  Port  City  project  is  to  position  Colombo  as  a 
regional  financial  centre.  There  is  sufficient  empirical  evidence,  when  examining  the  evolution  of 
Central  Business  Districts  of  regional  financial  centres  such  as  Hong  Kong,  Shanghai,  Singapore  and 
Dubai  and  even  New  York  and  Frankfurt  that  finance  has  become  more  concentrated  in  designated 
areas  of  the  CBDs  than  any  other  area  of  commerce.  (Example:  Wall  Street  in  New  York,  Dubai 
International Financial Centre). 
Significant  savings  and  synergies  are  possible  when  financial  centres  evolve  within  centralized  areas. 
Historically,  such  centres  attracted  regional  headquarters  of  banks  and  with  them,  other  financial 
institutions,  financial  intermediaries  and  corporate  headquarters.  Being  adjacent  to  a  regional  hub 
port, as is the case in Colombo, becomes an added advantage in attracting finance and commerce to a 
CBD. 
This  provides  a  clue  as  to  why  financial  centres  evolved  within  CBDs  of  cities:  economies  of  scale. 
Centralization of financial services is typically a result of several needs: 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015  Chapter 1 ‐ Page 9 

 
 
 

 The  need  to  facilitate  the  process  of  information  gathering:  Finance  depends  on  obtaining 
timely and accurate information and the process of information‐gathering increases the pressure 
for  clustering.  Therefore,  market  participants  tend  to  gather  close  to  one  another  and  to  their 
principal  sources  of  information:  e.g.  corporate  headquarters,  financial  regulators,  government 
etc. 
 The need to centralize participants engaged in complex financial transactions: Finance exists to 
serve  the  needs  of  industry  and  services.  Corporate  headquarters  are  usually  located  in  and 
around  financial  centres,  even  though  production  facilities  would  be  located  elsewhere.  Also, 
when complex corporate finance deals such as mergers and acquisitions need to be structured, 
participants  to  the  deal  including  corporate  executives,  institutional  investors,  accountants, 
lawyers and regulators should ideally be available in one location. For example, the Central area 
of Hong Kong the saying goes is a place where a financier can walk several blocks and raise $ 10 
billion. 
 The need to minimize costs in searching for counterparties with whom to trade: For investors 
and  issuers  alike,  the  crucial  function  of  a  financial  market  is  price  discovery  (the  process  that 
finds  the  right  price  to  optimize  supply  and  demand).  These  functions  work  best  when  many 
buyers  and  sellers  are  congregated  in  a  financial  centre.  Therefore,  financial  market 
intermediaries and participants such as banks, stock brokers, fund managers and insurers have a 
strong incentive to cluster in financial centres. 
 The need to recruit and train highly skilled financial professionals: Like most service industries, 
finance is a people‐oriented business. However, specialist skills required in financial services tend 
to concentrate in a central financial district of the CBD and hence the industry tends to expand 
around it. 
 
It  can  be  argued  that  the  advent  of  the  Internet  and  connectivity  has  reduced  the  propensity  for 
financial centres to cluster around a central business district. However, the above forces taken together 
with a congenial living environment (such as an oceanfront area with parks and cultural activities) and 
the  availability  of  good  regulations,  connectivity,  infrastructure  and  strategic  proximity  to  a  large 
economy  such  as  India  would  contribute  towards  financial  and  related  services  being  concentrated 
around a CBD.  
It  is  precisely  this  environment  required  to  establish  Colombo  as  a  regional  financial  centre  that 
Colombo Port City is attempting to create.  
 
1.3 Objective of the SEIA Report 
1.3.1   The 2‐Stage EIA Process 
 
Several important issues were raised in the Initial Technical Feasibility Study of 2010 and the EIA study of 
2011 for the 200 ha reclamation. They were: 
(a) The  proposed  Port  City  has  to  be  developed  in  2  stages.  The  first  stage  will  be  the  landfill,  the 
offshore breakwater and the coast protection for the protection of the landfill. The Second Stage 
will be the planned development of Port City with all infrastructure and support services 
(b) If  the  Project  Company  developing  Port  City  development  modifies  the  overall  design,  then 
environmental consultants would be commissioned to present an addendum to the EIA to confirm 
that  the  changes  and  resultant  environmental  impacts  will  not  make  a  significant  change  to  the 
findings of the initial EIA completed for 200ha. If changes to the design are significant then a fresh 
EIA will be carried out.  
(c) A detailed EIA will have to be carried out for the infrastructure development plan of the Port City 
and the proposed developments on the reclaimed land.  
 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015  Chapter 1 ‐ Page 10 

 
 
 

The  objective  of  this  Supplementary  EIA  is  a  consequence  of  (b)  above:  that  is,  to  capture  the  design 
changes since the completion of the EIA of 2011 and to subject to public scrutiny the aspects covered in 
the Addendum to the EIA of 2013 and subsequent changes. It is noted that the Addendum to the EIA of 
2011 was not open to public comments. 
Varying approaches can be undertakes for environmental studies. It is the prerogative of the Government 
policy  makers  led  by  the  Project  Approving  Agency  (PAA)  to  decide  on  the  scope  of  the  environmental 
studies.  Accordingly,  the  respective  Government  appointed  review  committees  evaluating  the  Port  City 
project recommended to the Cabinet of Ministers to adhere to a 2 stage EIA process for Port City, and 
accordingly provision was made for such a course of action in the Project Agreement signed between the 
GOSL  and  the  Project  Company.  Therefore,  as  mentioned  earlier  in  this  SEIA  report,  Colombo  Port  City 
will be developed in two distinct phases, with required environmental approvals obtained via two related 
EIA studies.  
This SEIA is therefore to be read as a Supplementary to the approved EIA of 2011. Notwithstanding, this 
SEIA  study  covers  the  entire  reclamation  footprint  and  the  extraction  of  quarry  material  and  sand 
required  to  complete  the  entire  project.  The  Phase  2  EIA  for  the  construction  of  the  buildings  and 
infrastructure  of  the  Port  City,  including  traffic  impact  assessment  will  commence  in  parallel  or 
immediately after completing this SEIA study. 
 
1.3.2   Precedence of 2‐stage EIA Process 
 
Project  Approving  Agencies  in  the  past  have  carried  out  2‐stage  EIA  processes.  In  the  case  of  the 
Muthurajawela  landfill  that  commenced  around  1994,  a  total  of  162  ha  of  near‐shore  lands  were 
reclaimed from a very sensitive marsh area by dredging for sand from the sea. (The filled area is roughly 
70% of the size of Port City).  
The EIA carried out for the Muthurajawela project  was only for the hydraulic landfill and  did not cover 
infrastructure  aspects  and  the  constructions  on  the  filled  land.  However,  the  study  covered  the 
environmental impacts of the sand borrow area. The industries/buildings that were built on the landfill 
carried out separate environmental studies prior to  construction  (e.g. Shell  Terminal) and  the land was 
marketed at commercial rates by SLLR&DC. 
Also internationally, a 2‐stage EIA is a recognised approach. In the Netherlands, where EIA processes are 
very strictly followed, a 2‐stage approach was followed for the recent expansion of the Port of Rotterdam 
by 2000 hectares (the so‐called “Maasvlakte II” project). The first EIA was for the “realisation phase” of 
the  land  reclamation,  covering  coastal  impact,  dredging  practices,  etc.  The  second  EIA  was  for  the 
“development phase” analysing the impact of the new activities within the port for the environment and 
surrounding areas. 
 
1.4 Extent and scope of the study 
The  ToR  issued  by  the  Department  of  Coast  Conservation  and  Coastal  Resources  Management  (CCD), 
the Project Approving Agency (PAA), defines the scope of this SEIA study. The ToR is given in Annex I. 
The study area for the assessment is defined in the ToR as follows: 
(a) Project site/s: Reclamation Area and Borrow Sites 
(b) For  coastal  erosion  aspects:    Reclamation  area  and  10  km  on  either  side  (Northern  area  and 
Southern Area) of the coastal belt. 
(c) For all other studies: 1km from the project sites (reclamation area and borrow sites). 
(d) Any area  beyond  the project site/sites, where there is  potential for environmental impacts:  The 
SEIA study team shall determine the limits of the influenced area. 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015  Chapter 1 ‐ Page 11 

 
 
 

The ToR outlines the report structure and the issues to be addressed during the study. The study covers 
the existing environmental parameters of the Project area (present situation) and impacts, both short‐
term  and  long‐term  in  nature.  The  analysis  proposes  effective  mitigation  measures  and  monitoring 
programmes. 
 
1.5 Methodologies and technologies adopted in SEIA report preparation 
A number of methods have been adopted to assess the environmental impacts of the Colombo Port City 
Project. These methods supplement the studies carried out for the Project Feasibility Studies, the EIA for 
200 ha and this SEIA study. The assessment methodologies have been used to evaluate impacts arising 
from  the  development  at  the  study  area,  the  surrounding  areas  and  the  sand  borrow  areas.  These 
methodologies are described in the paragraphs below. 
1.5.1   Desk Studies 
The  approach  in  the  preparation  of  this  SEIA  report  was  to  draw  on  and  build  upon  the  Project 
Feasibility  Studies,  specific  technical  studies  carried  out  for  the  Port  City  Project,  and  information 
available from the EIAs and EMPs of Colombo South Port. Relevant documents have been reviewed and 
additional studies carried out to validate and where necessary, supplement the existing information to 
take  into  account  the  development  of  the  design  under  this  SEIA  study.  In  addition,  previous  study 
reports have been used extensively to confirm the baseline situation and guide the SEIA process.  
1.5.2   Feasibility Design Investigations and their relevance to the EIA Process 
To the maximum possible extent, environmental considerations have governed the planning and layout 
of  Port  City  and  incorporated  into  the  design  process  from  its  inception.  This  has  allowed  the  early 
identification of any environmental issues, which may impose constrains on the design. This approach of 
“Mitigation by Design” has reduced the need for a range of specific mitigation measures. 
Numerical  modelling  studies  and  physical  model  test  studies  have  led  to  the  development  of  a 
hydraulically efficient layout with respect to overall impacts on the coastal regime. Hydrodynamic and 
wave disturbance modelling studies have been carried out to investigate the impact of the overall layout 
on the coastal regime and to ensure satisfactory levels of wave disturbance are maintained at the water 
area within Port City. 
1.5.3   Wave and Hydrodynamics 
A comprehensive review of the modelling work carried out during Port City’s feasibility study stage, and 
preliminary  design  stage  were  undertaken  for  this  SEIA.  In  addition,  separate  studies  have  also  been 
carried out and relevant reports prepared for this SEIA. These reports include: 
(a) Final report on Hydrographical Survey 
(b) 2‐D Stability Physical Model Test on the offshore breakwater and revetment for marina 
(c) 3‐D Physical model test south part and 3‐D physical model test North part 
(d) Analysis (numerical modelling) of coastal evolution and siltation  
(e) Analysis (numerical modelling) of water exchange 
(f) Wave physical Model Test of the Stability of Beach Profile 
(g) Analysis  (numerical  modelling)  of  Water  Exchange  Supplementary  Report  for  the  effect  of  Port 
City on Beira Lake outfall  
(h) Ground investigation preliminary report 
(i) 3‐D Physical model test on the Southern Part of Colombo Port City project  
 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015  Chapter 1 ‐ Page 12 

 
 
 

1.5.4   Geophysical Investigation 
The  geophysical  survey  was  carried  out  to  investigate  the  potential  extractable  sand  volume  and 
sedimentological status. Sub‐bottom profiling was conducted to estimate the sediment thickness of 
the area which leading to study sediment distribution. Sub‐bottom profiler was used to investigate 
subsurface geological structures such as stratification (thickness of subsurface strata and extension) 
of  the  area.  Innormar  “SES‐2000”  Sediment  parametric  echo  sounder  was  used  to  differentiate 
strata and data were used to measure the layer thickness of the sediment deposits in the proposed 
site.  SESWIN  and  ISE  1.2  software  were  applied  for  data  acquisition,  processing  and  thickness 
estimation  respectively.  The  sub‐bottom  profiler  was  consists  of  dual  frequency  sonar  head  with 
50m penetration depth, However, depth of penetration is limited by the conditions of the sediments 
and  the  environmental  condition  of  the  survey  area.    The  survey  was  designed  as  systematic 
sampling method and sub‐bottom profiling survey was done along the pre designed lines in the area. 
Each sample was collected within 2 km grid and sub‐bottom profiling was conducted with 1 km line 
spacing.  During  the  analysis  isopach  map,  sediment  distribution  map  and  bathymetric  map  of  the 
area were generated using Surfer and ArcGIS software.  
Frequency of the data acquisition for the investigation was about 8 kHz, while pulse repetition rate 
was  4.  Differential  Global  Positioning  System  (GDPS)  with  accuracy  +/‐  20cm  is  integrated  to  the 
instrument during data acquisition. The hypack navigation system is used to guide the vessel along 
predetermined  survey  lines.      The  average  sand  layer  thickness  was  used  to  estimate  the  sand 
volume.  
Sediment Sampling 
Sediment sampling procedure was designed as systematic manner. Bottom sediment samples were 
collected by manually to identify sand characteristics.  
Sieve analysis 
Grain  size  differentiation  of  the  sediments  was  done  by  sieve  analysis.  Sediment  samples  were 
washed and dried for dis‐aggregation. Larger shells and organic materials were manually removed.  
Percentage ratio of sediment fractions is used for classification of sediments. 
1.5.5  Bathymetric Survey 
Bathymetric  survey  lines  were  designed  with  300m  (line  spacing)  interval  using  Hypack  Max 
software.  Integrated  echo  Sounder  and  positioning  system  (DGPS)  were  used  for  data  acquisition. 
Transducer  of  the  echo‐sounder  was  fixed  on  a  lower  draft  of  small  boat.  The  data  acquisition 
system comprised a computer with Hypack Max software and a display unit. The display navigates 
the  boat  along  the  pre‐set  survey  line  with  the  help  of  left  right  indicator.  Positioning  (Easting  X, 
Northing Y) and depth data from GPS and echo‐sounder (Z) were recorded in a data log file for each 
survey line. Sound velocity was measured using Sound Velocity Probe (SVP) twice a day during the 
survey,  at  the  beginning  and  the  end  of  each  survey.  Echo‐sounder  calibration  was  done  by  “Bar 
check” method. Water level measurements  during the survey  was taken and recorded in every 15 
minutes by Tide Pole.  All (X, Y) coordinates were connected to national grid of Sri Lanka and depth 
was referenced to MSL.  
1.5.6   Ecological Studies:  
The nekton in the marine environment of the reclamation area was observed by visual observations 
carried  out  during  underwater  surveys  while  plankton  were  collected  using  a  50  μ  plankton  net 
drawn through the water. Benthos including reef organisms, other macro‐fauna on the sea bottom 
and  sea  grass  beds  were  examined  during  underwater  surveys  carried  along  a  1  km  long  transect 
which was located in front of Galle Face Green extending over the Palagala reef. (Coordinates of the 
transect are E 79o49’12’’ – E 79o50’24’’ and   N   6o55’18’’ – 6o55’20’’) 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015  Chapter 1 ‐ Page 13 

 
 
 

    
The transect was at a depth ranging from 8 m to 18 m.  The entire transect was on soft bottom except a 
mid‐region  where  it  crossed  the  Palagala  reef.  During  underwater  surveys,  a  1  m  x  1  m  quadrate  was 
used at each sampling site to estimate the cover of benthic organisms.   
The  percentages  of  animals  and  plants  were  estimated  using  the  visual  estimation  technique.    The 
organisms were identified to the lowest taxonomic group possible. During the period of the underwater 
surveys,  due  to  high  turbidity,  the  visibility  was  very  low  being  less  than  1.0  m.    Therefore,  the 
abundance  of  fish  in  this  area  could  not  be  estimated.  The  mollusk  shells  that  were  washed  onto  the 
shore were collected and identified using Kirthisinghe (1978). 
In order to recognize the existing biological environment in the proposed sand extraction area, data 
and  information  were  gathered  from  both  primary  and  secondary  sources.  Existing  literature  on 
describing  habitats,  resources,  environmental  conditions  was  analyzed  to  ascertain  ecological 
importance and assess the potential consequences of sand dragging activities.  
Present distribution, biodiversity and health of coral reefs/ sea grass beds 
Information  on  coral  and  sea‐grass  distribution  was  initially  gathered  by  topography  map  and 
exploiting  traditional  knowledge  of  fishermen.  Afterwards  underwater  manta  tow  survey  was 
conducted to ensure the selected sites are in a comparable habitat. Visual surveys using Underwater 
Visual  Census  (UVC)  were  conducted  during  daylight  hours  between  7:00  and  16:00,  on  the  days 
where  the  visibility  was  relatively  fair.  Ten  dive  sites  in  each  representative  habitats;  reef  and 
sand/mud  were  surveyed  from  15th  September  to  10th  October  2015.  Moreover  data  gathered 
from  same  techniques  for  the  coral  reef  survey  for  Onagala  and  associated  environment  in 
November 2012 and March 2014 were also used.   
Belt transect laid at each dive sites was surveyed by concurrently employing two experienced SCUBA 
divers.  They were instructed to swim along at a steady pace without stopping, so they generally did 
not deviate from the belt‐transect to inspect crevices. The fish observer followed the belt transect of 
50  x  4  m  by  swimming  along  the  center‐line  of  the  belt  transect  with  a  PVC  rod  as  guide.  The 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015  Chapter 1 ‐ Page 14 

 
 
 

observer count, recorded the species diversity and the second diver videoed all fish within the area 4 
m to either side of the center line and also 2 m upwards of the eye level.  
At  each  transect  mobile  and  the  sessile  fauna  and  the  substrate  was  recorded  in  terms  of  the 
percentage  cover  of  sand,  rubble,  limestone  platform,  coral  or  terrestrial  rock  and  mud.  Other 
benthic taxa such as black coral and whip coral and the percentage cover of other conspicuous biota 
such as sea‐grass and algae were also recorded. Transects were laid systematically and objectively to 
clearly visualize the local habitat features. All survey points were marked using GPS. 
Present distribution, species composition and richness of sea bottom macro zoo benthos 
More than twenty five fish in mono‐specific groups were observed to estimate the total population. 
For  schools  of  mixed  species  the  number  was  estimated  for  the  entire  school  by  making 
approximation  of  the  proportion  of  each  species  comprising  the  school.  Photographs  and  videos 
were also used for estimation, validation and species identification. Benthic samples were randomly 
collected  using  an  Ekman  Bottom  Grab  Sampler  from  the  two  sand  borrow  sites  so  that 
representing  both  muddy  and  sandy  substrates.  Samples  were 
stored in 10% formalin and rose Bengal solution and sieved for the 
identification  and  enumeration  of  sediment  ‐  dwelling  macro 
organisms by different size categories residing in the sediment. 
Under  water  photographs  (photo  quadrat)  and  video  of  the 
substrate  along  the  distance  of  50  m  transect  were  also  made  to 
validate the point intercept method facilitate species identification.  
Photographs  were  made  using  a  10  mega  pixel  Canon  IXUS  digital 
camera.  The  photos  were  geo‐referenced  through  post  processing 
of  the  track  recorded  by  a  GPS,  being  towed  by  the  same  diver 
taking  the  photos.  The  organism  lying  beneath  each  point  was 
identified  to  the  most  detailed  taxonomic  or  most  precise 
taxonomic level possible, depending on the resolution of the video images and photographs and also 
the skill of the observer. Quantitative analyses were performed based on the following eight major 
benthic categories: abiotic (subdivided into bare rock, rubble, dead coral, mud, sand & silt), biotic: 
(soft coral, gorgonian, hard coral, molluscs, sea‐grass, sea weeds). 
Present occurrence of endangered species or extra ordinary natural resources 
The  relevant  information  on  endangered  species  was  obtained  from  available  literature,  personal 
communications with the coastal communities and independent recording of their sightings through 
employing  onboard  observers  at  limited  occasions.  The  research  platform  was  an  18  foot  OBM 
fishing  boat.  The  boat  generally  ran  4‐6  hour  trips  between  06:00 hrs  to  18:00 hrs.  Two  trained 
observers  recorded  sightings  from  amidships  to  the  bow,  one  looking  to  port  and  the  other  to 
starboard. They searched for cetaceans, sea turtles by eye and using binoculars. It should be noted 
that search efforts ceased during bad weather namely, rain, strong winds, and rough seas. Ten visits 
were  made  during  the  study  period  and  in  each  visit,  the  entire  beach  stretch  was  surveyed  two 
times; early morning and night.  Further, information also gathered through interactions with locals, 
especially  fishermen.  Questions  were  asked  on  the  sightings,  presence  of  turtles  close  or  far  from 
the shore, number of turtles incidentally captured and species.  Afterwards beach surveys conducted 
to determine the turtle nesting in the west coast.  
Present conditions concerning nutrient dynamic, algae blooms and water turbidity 
Totally  22  sampling  positions  were  selected  from  sand  extraction  area  to  study  the  nutrient 
dynamics and phytoplankton assemblage.  Water samples were collected at the depth of 0.5 m from 
the  surface  to  study  the  nutrient  levels  and  preserved  at  ‐20o  C.  Phytoplankton  samples  were 
obtained  using  a  net  with  a  mesh  size  of  10  µm  and  immediately  preserved  with  Lugol’s  iodine 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015  Chapter 1 ‐ Page 15 

 
 
 

solution. Turbidity was measured by a turbidity meter. In addition to turbidity, total suspended solid 
level (TSS) was measured. 
Phytoplankton:  Supernatant  of  the  preserved  phytoplankton  sample  was  decanted  without 
disturbing  the  settled  cells  so  that  the  sample  is  concentrated  to  a  known  volume.  One  ml  of  this 
concentrated  sample  was  placed  in  the  Sedgwick  rafter  cell  and  observed  and  the  number  of 
phytoplankton was counted under the light microscope at a magnification of 10x10. Samples were 
analyzed  for  determination  of  phytoplankton  abundance,  composition  and  diversity  (Newell  and 
Newell 1963; Robert Perry 2003; Verlencar, X.N. &Somshekar Desai, 2004, Jayasiri,2009).  
Determination of Chlorophyll content in waters: Chlorophyll was determined by filtering 1 litre of 
the  water  samples  using  GF/C  filters  (nominal  pore  size  0.7  μm)  under  low  vacuum.  The  pigment 
extraction was done with 10 ml of 90% acetone. The optical density (absorbance) of the extract was 
determined  using  a  UV  Visible  spectrophotometer  (Parsons  and  Strickland  1963;  Richards  and 
Thompson 1952). Chlorophyll a concentrations was calculated using the equations of Parsons et al. 
(1984). 
Nutrients  analysis:  Nutrients  (Nitrite‐N,  Nitrate‐N,  Phosphate‐P  and  Silicate‐Si)  were  analyzed 
according  to  the  standards  procedure  of  Parsons  et  al.,  (1984)  using  spectrophotometer  (OPTIZEN 
3220UV). Sample preparation for nitrite and nitrate was done according to the Cadmium reduction 
method and absorbance was measured at 543 nm wavelength. Phosphate was analyzed according to 
the  ascorbic  method  and  absorbance  was  measured  at  885  nm  wavelength.  For  the  analysis  of 
silicate, molibdate method was used and absorbance was measured at 810 nm wavelength. 
Total  suspended  solids  (TSS):  Filter  papers  (GF/C  [0.7  micro  pore  size  of  47  mm  diameter])  were 
dried  in  an  oven  at  105  °C  for  1  hour  period.  Then  the  initial  weights  of  filter  papers  (W1)  were 
measured  using  analytical  balance  (Precisa  XB  120A).  Each  1  litre  of  samples  was  filtered  using  a 
filter  unit  and  filter  papers  were  dried  in  an  oven  at  105  °C  for  1  hour  until  get  a  constant  weight 
(W2). Then the final weights are recorded. Following equation was used for the calculation of TSS in 
mgL‐1. 
W2– W1
TSS 1000 
Volume
 
 
Breeding  grounds  /  spawning  grounds,  nursery  grounds  and  migratory  routs  for  commercial  and 
ecologically important marine organisms: 
Spawning ground is a place where fish leave their eggs for fertilization. Many fish species aggregate 
to spawn. Whereas some species may aggregate behaviourally and so may have extensive spawning 
grounds  that  may  change  location  slightly  from  year  to  year,  other  species  may  aggregate  over  a 
more restricted spatial extent. The grounds where juveniles are found at higher densities are termed 
nursery grounds. They have reduced rates of predation and have faster growth rates than in other 
habitats,  which  should  result  in  nursery  grounds  providing  a  greater  relative  contribution  to  adult 
recruitment in comparison to non‐nursery ground habitats. Migration of fish is defined as an active 
main movement from one habitat to another (Nikolsky, 1963). There are three main movements in 
the migratory cycle of fishes; spawning migration, feeding migration and winter migration. 
The most effective methodology to adopt to identify the spawning grounds is to collect data on the 
distribution  of  the  planktonic  stages  of  fish  eggs  and  larvae  (ichthyoplankton).  In  a  multispecies 
situation  spawning  strategies  are  varied  and  as  such  fish  egg  and  fish  larvae  data  have  to  be 
collected  with  different  target  species  and  spatial  and  temporal  coverage  to  infer  species  specific 
spawning  areas.  Since  lack  of  time  series  data  on  ichthyoplankton,  the  present  study  adopted  a 
robust and indirect method to delineate spawning grounds and season of selected species exploiting 
research experience and the traditional knowledge of fishermen.    

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015  Chapter 1 ‐ Page 16 

 
 
 

Small pelagic resources are the main fisheries in the study area. The species composition of the catch 
dominates  by  Amblygstersirm  (hurulla),  and  Sardinellalongiceps  (salaya).  Bottom  trawling  for 
shrimps is the second most important fishery and the shrimp catch consisting mainly Penaeus indicus 
and Metapenaeus dobsoni. Information on spawning grounds and seasons of dominate species were 
obtained from literatures.  

There are numerous methods for tracing the migrations of fishes. Most commonly applied methods 
are;  marking,  tagging,  parasite  studies,  length  frequency  and  catch  rates  analysis.  However,  these 
methods are more precise where large scale migration occurs in more extended area and also it is 
hard to fit successfully tags to all fish species especially for small fish to fishery and all size groups of 
fish. Therefore migration of fish and shrimps and retirement were made through length frequency 
analysis. 

Identification and mapping of fishing grounds 
Use of study area as a fishing ground was physically inspected at sea. Two to three observers (NARA 
scientists) were onboard at the sea to record the information such as type of the boat, fishing gear 
used,  fishing  time  and  target  fishery  etc.  The  fishing  roots  or  navigational  roots  of  the  boats  were 
tracked to collect information on the spatial extent of fishing activities in the study area using a GPS. 
The fishing grounds were then mapped using Geographic Information system (GIS). Attribute maps 
were also generated based on the required visual representation. 
Biodiversity profile within the sand borrow sites 
The information/ observations/evidences gathered in the above mentioned surveys were utilized to 
describe the bio diversity profile within the sand borrow sites. 
1.5.7  Assessment of the socio‐economic environment 
The  socio‐economic  assessment  of  the  CPCD  area  was  carried  out  using  both  published  and 
unpublished  data.  First,  a  thorough  study  of  socio‐economic  conditions  of  the  entire  project  area 
was carried out (including GN divisions of the project area, and Colombo Metropolitan Area) using 
both  published  and  unpublished  secondary  data  by  the  Department  of  Census  and  Statistics  on 
labour  force  ,  business  activities  ,  housing  conditions  ,  poverty,    income  and  expenditure  patterns  
and Construction Industry.  In addition, unpublished data were also collected form the  Ministry of 
Fisheries and District Fisheries Officials on fish production, stock of fishing vessels, and living status 
of  fishing  communities  in  Wellawatha,  Dehiwala,  Modera  and  Mattakkuliya  fish  landing  centers. 
Published  reports  by  the  Department  of  Archeology  were  also  used  to  assess  the  impacts  on 
archeological and cultural resources. Data on business activities in Fort and Petah, cost of municipal 
services,  assessment  rates  and  tax  structures  were  collected  form  the  CMC.    Second,  a  series  of 
depth interviews were also conducted with leading hoteliers operating in immediate vicinity of the 
project, policy makers and administrators to illicit information on potential impact of tourism, urban 
development, investment promotion, business development and trade relations.  
The  socio‐economic  study  related  to  sand  exploration  sites  was  conducted  using  structured 
questioner  (Annex  V),  structured  interviews  with  fishers  and  semi  structured  interviews  with  key 
informants  of  the  fishing  community.    In  addition  the  participatory  rapid  appraisal  (PRA)  methods 
were  applied  to  extract  qualitative  data  from  stakeholders.    The  updated  statistical  information  of 
the fishing community was collected from the Department of Fisheries in Negombo.  
 
 
 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015  Chapter 1 ‐ Page 17 

 
 
 

1.6 Main beneficiaries  
1.6.1   Importance of Western Region Development 
A key objective of the recently created Ministry of Megapolis and Western Development is to separate 
the Western region of Sri Lanka from the other regions to promote a higher rate of growth, which will 
not only benefit the Western Region, but also other regions through backward integration. According to 
the  CESMA  Plan  of  2004:  “The  spill  over  effects  from  a  strong  economic  region  with  the  capability  of 
launching investment into other regions will lead to an expansion of other economic activities. The fast 
development of the Western Region is expected to lead to higher production of goods and services in 
other regions which will in turn lead to higher economic growth for the country as a whole”. Therefore it 
is envisaged that the initiatives of the newly formed Ministry of Megapolis & Western Development will 
spill over to other regions, reducing regional economic disparities.  
The Colombo Port City is expected to become a catalyst in the economic growth of the Western Region 
of Sri Lanka with multiplier benefits from the project positively impacting the regions.  
 
1.6.2   Key Economic Benefits from Colombo Port City 
The key benefits form the Colombo Port City during the reclamation phase of the project are described 
below: 
(a) A  foreign  direct  investment  (FDI)  of  approximately  US$  1,400  million,  the  largest  private 
investment by any company in Sri Lanka, local or foreign, in a single project: FDIs has significant 
economic benefits to Sri Lanka’s balance of payments, technology transfer, local employment and 
value creation. 
(b) Benefits of an investment by one of China’s largest companies, CCCC, and prospects of further 
investments by this company, related Group companies and other companies from the region: 
CCCC, the parent company of the Project Company, is ranked No 187 among global Fortune 500 
companies having assets of over US$ 100 billion and turnover per annum of over US$ 60 billion. 
Majority owned by the Government of China, CCCC is a public company listed on the Hong Kong 
stock  exchange.  It  is  China’s  largest  port  design  and  Construction  Company  and  the  largest 
dredging  company in the world. The  Group is also the leading  company in  the world for  design 
and  construction  of  roads  and  bridges  and  the  leading  manufacturer  of  container  cranes  in  the 
world,  with  75%  of  the  global  market  share.  The  Group  has  15  years  experience  in  Sri  Lanka 
having successfully competed 28 projects valued at $3.4 billion.  
(c) Long term nature of the investments by CCCC: The Port City project does not provide any returns 
to  the  investor  in  the  first  5‐8  years  from  project  implementation.  In  fact  the  return  on 
investment  and  payback  from  the  project  to  the  investor  is  in  excess  of  15  years. 
Notwithstanding,  CCCC  has  expressed  an  interest  in  building  Sri  Lanka’s  largest  office  tower  on 
reclaimed  land  in  Port  City  upon  completion  of  the  required  Phase  2  EIA,  thus  establishing  the 
company as a long‐term investor in Sri Lanka  
(d) Value of land: The Colombo Port City is estimated to contain around 173 ha of marketable land. 
These will be leased/sold to third party developers in keeping with applicable laws and at market 
prices jointly decided by the GOSL and Project Company. The market value of the 173 ha of new 
marketable  land,  based  on  the  current  average  market  price  of  approximately  Rs  9  million  per 
perch, can be estimated as follows 
 Value of UDA/Government land of 63 ha at current market prices: US$ 1.6 billion or Rs 225 
billion 
 Owning  this land on a freehold basis will considerably strengthen the  balance sheet of the 
UDA. 
 Value of 110 ha of land to be allocated to Project Company is US$ 2.8 billion 
(e) Employment  and  Technology  transfer:  The  Project  Company  employed  over  1550  direct  staff, 
almost  all  Sri  Lankan,  including  60  Sri  Lankan  professionals  and  engineers.  (This  number  has 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015  Chapter 1 ‐ Page 18 

 
 
 

reduced  by  80%  during  the  suspension  period).  As  explained  in  greater  detail  later  in  this  SEIA 
report, the direct and indirect employment potential with the recommencement of construction 
would  be  around  6400  representing  skilled,  unskilled,  technical  and  managerial  categories.  The 
Project has also employed best in class overseas and local consultants for the various aspects of 
design and monitoring aspects of Port City.  
 
The key benefits form the Colombo Port City after the reclamation phase of the project will be covered 
in greater detail in the Phase 2 EIA study.  These include: 
 Creation  of  higher  paying  service  sector  jobs  through  new  investments  in  buildings  and 
infrastructure at Port City and the attraction of new businesses. 
 Establishing Colombo as a business, financial and tourism hub of South Asia 
 Creation  of  public  amenities  such  as  parks,  theme  parks  and  other  recreational  facilities  within 
Colombo’s CBD for all strata of society to enjoy.   
 
1.7 Applicable laws and regulations 
The  Project  must  conform  to  the  National  Environmental  Impact  Assessment  requirements  identified 
below.  In addition, there are a number statutes and regulations that are applicable (and not applicable) 
to the project, which have been taken into account during the planning and development stages.  These 
applicable/non‐applicable laws and regulations are discussed in the paragraphs below. 
1.7.1    Sri Lanka Lands Ordinance and UDA Act No 41 of 1978 
The  Hon.  Attorney  General  has  opined  that  the  UDA  cannot  be  a  signatory  to  the  Project  Agreement 
replacing the SLPA as it lacks the legal capacity under the UDA Act. This is in view of the fact that upon 
creation of new land by reclamation of the sea the entire Port City land will be gazetted under the Sri 
Lanka  Lands  Ordinance,  a  subject  matter  falling  under  the  purview  of  His  Excellency  the  President  in 
terms  of  the  said  Ordinance.  The  UDA  could  therefore  declare  the  land  reclaimed  by  the  Port  City 
Project as an “Urban Development Area” only after the reclamation process is over and a declaration is 
made under the Lands Ordinance. Accordingly, prior permission from the Land Commissioner prior to 
completion of reclamation does not arise 
1.7.2  National Environmental Act No. 47 as amended by Act No. 56 of 1988 (NEA) 
National Environmental (Amendment) Act No. 56 of 1988 of Sri Lanka stipulates EIA as a mandatory 
requirement for establishment of various large scale developmental projects in Sri Lanka and assigns 
regulatory functions to the Central Environmental Authority (CEA). 
According  to  Part  IV  C  of  the  above  mentioned  amendment  act,  all  "prescribed"  development 
projects are required to be subjected to Environmental Impact Assessment.  
The National Environmental Act further stipulates that approval for all prescribed projects shall have 
to be obtained from the appropriate project approving agencies concerned or connected with such 
prescribed project. Central Environmental Authority (CEA) is the PAA in present case. 
EIA provisions are also included in the Fauna and Flora (Amended) Act No. 49 of 1993. According to 
this Act, any development activity of any description what so ever proposed to be established within 
one mile from the boundary of any National Reserve, is required to be subject to EIA, and written 
approval should be obtained from the Director General, Department of Wild Life Conservation prior 
to implementation of such projects. Although the EIA is applicable for the project, the provisions of 
Fauna and Flora (Amended) Act No. 49 are not applicable as there are no National Reserves within 
one mile from the project boundary. 
 
 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015  Chapter 1 ‐ Page 19 

 
 
 

1.7.3   Coast Conservation Act No. 57 of 1981 

The  Coast  Conservation  Act  No.  57  of  1981 


together  with  the  Coast  Conservation 
(Amendment) Act, No. 64 of 1988 and Coast 
Conservation  (Amendment)  Act,  No.  49  of 
2011  governs  the  Coastal  Zone.    This  Zone 
comprises  mainly  “the  area  lying  within  a 
limit of three hundred meters landwards of 
the Mean High Water line and a limit of two 
kilometers  seawards  of  the  Mean  Low 
Water line”.  Any person desiring to engage 
in a development activity within the Coastal 
Zone  will  be  required  to  obtain  a  permit 
issued  by  the  Department  prior  to 
commencing the activity.   

The  EIA  process  is  part  of  the  permit  Coastal Zones of Sri Lanka 


procedure  mandated  in  Part  II  of  the  Coast 
Conservation  Act  (CCA).  Section  16  of  the  Coast  Conservation  Act  (CCA)  confers  on  the  Director 
General  of  Coast  Conservation  and  Coastal  Recourse  Management  Department  (CC&CRM),  the 
discretion to request a developer applying for a permit (to engage in a development activity within 
the  Coastal  Zone)  to  furnish  an  Initial  Environmental  Examination  or  Environmental  Impact 
Assessment relating to the proposed development activity.  The CCA does not however specify how 
and  when  this  discretion  should  be  exercised.    The  Coast  Conservation  and  Coastal  Recourse 
Management Department (CC&CRM) interprets this provision as requiring an EIA when the impacts 
of the project are likely to be significant.   
However,  the  list  of  “prescribed  projects”  published  in  the  Gazette  Notification  No.  772/22  dated 
24.06.1993  under  the  National  Environmental  Act  states  that  the  CCA  applies  to  those  prescribed 
projects only if they are located wholly within the Coastal Zone. 
Nevertheless,  as  the  Coast  Conservation  Act  states  that  it  is  established  to  regulate  and  control 
development  activities  within  the  Coastal  Zone,  the  Coast  Conservation  and  Coastal  Recourse 
Management  Department  is  the  final  authority  to  determine  whether  to  permit  a  development 
activity in terms of the CCA, even though such activity may be required to go through the approval 
process laid down in the NEA. 
1.7.4 Mines and Mineral Act No.33 of 1992 (MMA) 
According to Section 12 of MMA, Geological Survey and Mines Bureau (GSMB) is responsible to regulate 
the mining activities in Sri Lanka. 
1.7.5   Marine Pollution Prevention Act No. 59 of 1981 
As  per  requirements  of  the  Marine  Pollution  Prevention  Act  No.  59  of  1981,  all  ships  that  enter  the 
territorial waters of Sri Lanka should comply with appropriate measures for preventing and controlling 
pollution of the sea from  a wide range of sources  ranging  from  sewage  to harmful  chemicals.  This 
act enables carrying out the requirements and conditions stipulated in the international convention for 
prevention of pollution from ships (MARPOL Convention)  to which  Sri  Lanka  is a signatory.   
Therefore,  ships  and  barges  which  supply  equipment  and  machinery  for  the  proposed  development   
should comply with the provisions of the Marine  Pollution  Prevention  Act 59 of  1981. The executing 
agency of the act is the Marine Pollution Prevention Authority of Sri Lanka. The said Act requires that 
developments such as Port City should include sufficient facilities  for pollution  abatement  of marine  

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015  Chapter 1 ‐ Page 20 

 
 
 

waters  as well  as  contingency   measures   in  place  to  cope   with   the  failure  of  such systems.   The 
contingency measures are also helpful to prevent pollution of the coastal zone from oil spills. 
The Marine Environment Protection (Dumping at Sea) Regulation No 1 of 2013 is not applicable to the 
Project Company or its dredging contractor. According to the Marine Pollution Prevention Act No. 35 of 
2008, it is clear that MEPA is tasked with prevention and control of pollution arising out of ship based 
activity  and  shore  based  maritime  related  activity  in  the  territorial  waters  of  Sri  Lanka  or  any  other 
maritime  zone,  its  fore‐shore  and  the  coastal  zone  of  Sri  Lanka.  There  is  no  provision  for  the  Project 
Company or its dredging contractor, which engages in reclamation of land for commercial development 
by dredging sand and creating land and beaches from such sand to apply for a license or permit under 
the above regulation. 
 
1.7.6  The  Antiquities  Ordinance  No.  9  of  1940  (now  Act)    and  the  subsequent    amendments,  in   
particular Antiquities (Amendment) Act  No 24 of 1998 
Under  the    requirements    of  Sections    43A    and  43B    of  the  Antiquities    (Amendment)    Act  No.  24  of 
1998, separate  approval  is required  from the Director General,  Department   of  Archaeology,   for  the  
satisfactory   completion   of  an  Archaeological Impact Assessment. This is implemented through the 
'Project  Procedure  Regulation  No.1  of  2000  (published  in  Gazette  Extraordinary  No.  1152/14,  October 
2000). 
1.7.7 Civil Aviation Authority Act No 14 of 2010 
The regulation and control of matters related to civil aviation and aviation in general, is in terms of the 
Civil Aviation Authority Act No. 14 of 2010 (hereinafter referred to as “the Civil Aviation Authority Act” 
and/or  “the  Act”).  Section  2  of  the  Act  states  that  the  Chicago  Convention  shall  govern  all  activities 
relating to civil aviation in Sri Lanka. Further, Section 3 of the Act states that “the provisions of this Act 
shall  apply  in  respect  of  all  activities  relating  to  civil  aviation  within  the  territory  of  Sri  Lanka”  and  in 
particular, in respect of inter alia registration of aircraft, regulation, administration and safety oversight 
of activities relating to civil aviation carried out within the territory of Sri Lanka.  
 
Section  32  of  the  Act  states  as  follows:  “32(1):  No  foreign  military  or  state  aircraft  may  enter  the 
territory of Sri Lanka, without a special permission or authorisation for the same being obtained from the 
Secretary to the ministry of the Minister in charge of Defence. 32(2): No foreign civil aircraft may enter 
the territory of Sri Lanka without a special permission or authorisation from the Director‐General”. 
 
For the purpose of the Chicago Convention the territory of a State shall be deemed to be the land areas 
and territorial waters adjacent thereto under the sovereignty, suzerainty, protection or mandate of such 
State”.  Article  1  of  the  Chicago  Convention  states  that:  “The  contracting  States  recognise  that  every 
State has complete and exclusive sovereignty over the air‐space above its territory”. Therefore, in terms 
of  the  Act,  the  Director‐General  of  the  Civil  Aviation  Authority  and/or  the  Minister  in  charge  of  the 
subject  of  aviation  have  exclusive  control  over  inter  alia  the  registration  of  air‐craft  and  aerodromes, 
licensing,  the  determination  of  air‐worthiness  of  aircraft,  seizure  of  aircraft  and  the  flight  schedule  of 
aircraft within the territory of Sri Lanka.  
 
The  reclaimed  land  has  no  impact  on  regulation  and  control  of  matters  related  to  civil  aviation  and 
aviation in general, in terms of the Civil Aviation Authority Act No. 14 of 2010. This is in view of the fact 
that upon creation of new land by reclamation of the sea the entire Port City land will be gazetted under 
the Sri Lanka Lands Ordinance, a subject matter falling under the purview of His Excellency the President 
in terms of the said Ordinance.  
 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015  Chapter 1 ‐ Page 21 

 
 
 

1.8 Conformity  to  Coastal  Resources  Management  Plan  and  any  other  development/  conservation 
plans of the area 
1.8.1 The Coastal Zone Management Plan (CZMP) 
The  CZMP  was  developed  in  1990  and  revised  in  1997  and  2004.  The  aim  of  the  CZMP  (2004)  is  to 
regulate development within the jurisdiction of the CCD in order to ensure that development pressures 
are not detrimental to coastal processes. In order to achieve this, the CZMP has identified areas suitable 
for development activities and corresponding setback limits for intended infrastructure.  
The Port City Development does not fall within the framework of a routine development activity on land 
within the coastal zone. The specific environmental and social concerns relating to the implications for 
coastal  management  of  the  proposed  Port  City  Development  have  been  identified  by  the  CCD  in  the 
scoping of the ToR for this SEIA study.  
1.8.2 The Master Plan for Coastal Erosion Management 
This  is  the  key  plan  developed  by  the  CCD  to  address  the  growing  problem  of  coastal  erosion  in  Sri 
Lanka. It was first developed in 1986 and revised in 1993. The CCD periodically reviews the plan in order 
to  ensure  that  a  consistent  approach  is  adopted  for  coast  protection.  The  CCD  upgraded  the  Plan  in 
2000  under  the  Coastal  Stabilisation  Component  of  the  ADB  funded  Coastal  Resources  Management 
Plan (CRMP).  
The proposed project does not impact on any aspects connected to the CRMP. It is pointed out later in 
the SEIA report, in keeping with studies carried out and recommendations of Lanka Hydraulics Institute 
(LHI), the process of sand extraction would occur at depths of 15m or more, thereby having no impact 
on coastal erosion. 
1.9 Approvals  needed  from  relevant  agencies  and  any  conditions  laid  down  by  such  agencies  for 
reclamation, sand and rock extraction 
1.9.1 Geological Survey and Mines Bureau 
The project would require the SLPA/UDA to assign the exploration and mining licenses from the GSMB 
for the sand borrow areas identified by the GSMB to the Project Company. Prior to the commencement 
of  construction  on  16th  September  2014,  the  SLPA  obtained  from  GSMB  the  following  licenses  and 
assigned them to the Project Company: 
 Exploration  License  No  EL/177  for  Map  No  59  dated  21st  June  2011.  (Later  an  Industrial  Mining 
License No: IML/A/HO/832 was issued by the GSMB to SLPA for the same area).  
 Exploration License No: EL/281 dated 8th November 2013.  
This  SEIA  study  is  being  carried  out  for  the  area  identified  in  the  above  exploration  licenses  for  the 
purpose of sand extraction.  
1.9.2 Urban Development Authority 
The Hon. Attorney General has given an opinion to the Cabinet appointed Officials Committee for Port 
City that the UDA Act does not permit the declaration of any land area as an Area of Authority under the 
UDA  Act  until  the  reclamation  is  completed  and  the  reclaimed  area  is  gazetted  under  the  Lands 
Ordinance as territory of Sri Lanka.  
1.9.3  Department of Coast Conservation & Coastal Resources Management 
Upon the SEIA process being concluded satisfactorily, as the Project Approving Agency for the SEIA, the 
CCD will under Part III Section 14 of the Coast Conservation & Resource Management Act No 57 of 1981, 
shall issue a Permit for Development for the reclamation works to re‐commence.  
Unless extended, the original Development Permit issued by the CCD for reclamation would lapse.  
 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015  Chapter 1 ‐ Page 22 

 
 
 

1.9.4  Colombo Municipal Council 
Consents from the CMC would not arise for the reclamation stage of the project and will be obtained 
during the Phase 2 EIA 
1.9.5  Marine Environmental Protection Authority (MEPA) 
The  SLPA,  on  behalf  of  the  Project  Company,  obtained  approval  issued  under  the  Marine  Pollution 
Prevention Act No 35 of 2008 for the oil spill contingency plan on 18th December 2014. In this regard the 
applicable law in connection of reclamation of land from the sea is as follows: 
 Any development activity within the coastal zone needs a permit under the CCD Act as mentioned 
above. There is no specific provision in the Marine Environmental Protection Act that requires a 
permit to be obtained for such development activities. 
 Regulations  under  the  MEPA  Act  do  not  apply  to  the  Port  City  Project  and  therefore,  the 
SLPA/UDA is not bound to obtain any further permit from MEPA. 
1.9.6  Department of Fisheries 
It  is  intended  that  the  Department  of  Fisheries  with  the  assistance  of  other  relevant  Government 
agencies  and  local  authorities  shall  be  assigned  the  responsibility  of  managing  the  disbursement  of 
funds  allocated  to  the  relevant  Ministry  for  uplifting  the  socio‐economic  conditions  and  any  loss  of 
fishing grounds of fishermen impacted by the sand extraction. 
Furthermore, it is proposed that the routes to be travelled by the dredgers of the Project Company may 
be gazetted under the Fisheries & Aquatic Resources Act. 
1.9.7  Board of Investment of Sri Lanka 
The Agreement between the Project Company and the BOI was signed on 11th November 2013. The BOI 
Agreement may require certain amendments at the time the UDA steps into the role of the SLPA under 
the Development Agreement of 16th September 2014.  
1.9.8 Strategic Development Act 
Notification under Section 3(2) of the Strategic Development Projects Act No. 14 of 2008, published in 
the Gazette Extraordinary No. 1879/6 of 11th September 2014, and Notification under Section 3(4) of 
the Strategic Development Projects Act No. 14 of 2008 was published in the Gazette Extraordinary No. 
1889/6 of 17th November 2014. These Gazette notices were published following Cabinet decision dated 
13th January 2014 approving the proposals made in Cabinet Memorandum No. MP&H/2013/21, dated 
20th September 2013, concerning the Colombo Port City Project. By this Cabinet decision the Colombo 
Port City Project was approved inter alia as a Strategic Development Project. 
1.9.9  Land Commission’s Department 
Approval  from  the  Land  Commissioner’s  Department  as  stated  above  does  not  arise  for  at  the 
reclamation stage of the project, when reclaiming a sea area. 
1.9.10  Department of Archaeology 
SLPA  has  obtained  Letter  of  Approval  from  the  Department  of  Archaeology  dated  18th  July  2012 
following the Archaeological Impact Assessment of the Colombo Port City Development Project done by 
the Underwater Archaeology Unit of the Department of Archaeology from November 2011 to February 
2012 pursuant to a request made by the SLPA by letter dated 22 June 2010. 
Furthermore, the Ministry of Megapolis and Western Development has obtained the following consents 
from the Department of Archaeology by way of letter dated 21st October 2015: 
1. During the period of reclamation, the Project Company will be  subject to the supervision of the 
Underwater Archaeology Unit of the Department of Archaeology 
2. Reclamation should occur only in areas indicated in the application submitted to the Department 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015  Chapter 1 ‐ Page 23 

 
 
 

3. If at any point in time archaeological artefacts are discovered, the Project Company should inform 
the  Underwater  Archaeology  Unit  of  the  Department  of  Archaeology  and  immediately  cease  to 
reclaim of dredge in the specific area the discovery was made.  
1.9.11 Road Development Authority  
Approval of the RDA/PRDA/LA (if required) for transport of quarry material will be the responsibility of 
the  individual  quarry  owners  who  will  supply  the  material  to  the  Port  City  site.  However,  GSMB 
Technical  Services  (Pvt)  Ltd,  who  was  appointed  by  the  Project  Proponent  for  the  purpose  of  carrying 
out the quarry material extraction study has recommended several mitigation measures as explained in 
Chapter 3, 4 and 5 of this SEIA to minimise the potential impacts on road transport system.  
As mentioned earlier, the Traffic Impact Assessment for Colombo Port City will be carried out during the 
Phase 2 EIA. 
 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015  Chapter 1 ‐ Page 24 

 
 
 

CHAPTER 6  
EXTENDED COST‐BENEFIT ANALYSIS 
 
6.1 Introduction 
The  development  of  Port  City  plays  an  important  role  in  promoting  growth  in  the  relatively  small 
economy of Sri Lanka. The benefits and objectives of reclaiming land to extend the Colombo Central 
Business District has  been elaborated  elsewhere in this report.  The main purpose of Colombo Port 
City  (CPC)  is  to  create  a  regional  business  hub,  a  city  with  a  distinct  brand  with  high  quality  public 
spaces and infrastructure facilities, attractive to local and international developers and investors. 
The  structural  changes  of  the  economy  over  the  past  ten  years  indicate  the  dominance  of  service 
sector  economic  activities,  particularly  in  the  areas  of  tourism,  ICT,  ports  and  shipping,  retail, 
transport  and  financial  services.  The  CPC  has  the  capacity  to  contribute  towards  service  sector 
oriented growth and development by attracting high profile FDI’s and generating wide range of direct 
and indirect benefits to the national economy.  
The CPC project is to be implemented over a 25‐year period. Large‐scale land reclamation involves 
numerous  complex  social,  environmental  and  economic  effects.  These  social  and  environmental 
costs are difficult to measure and to value.  The proposal to create land reclaimed from the sea at 
this  location  was  made  technically  feasible  due  to  construction  of  breakwater  (around  1.5km  in 
length perpendicular to the shore‐line) of the Colombo South Port expansion. 
The CPC does not involve replacing any economic activities in the project location or its immediate 
neighborhood.  Thus, the benefit generated by the entire reclaimed land becomes an additional asset 
to  Sri  Lanka  as  a  result  of  a  Foreign  Direct  Investment  (FDI)  project.  In  summary,  the  qualitative 
benefits of CPC can be summarized as follows: 
(a) The creation of additional oceanfront land designed to expand the CBD of Colombo that will 
enable an integrated master plan to be developed. This is expected to establish the city as a 
centre  for  finance,  tourism,  shopping  and  entertainment,  attracting  new  investments  and 
new buyers of real‐estate and tourists who will spend more money and entrepreneurs who 
will invest in new businesses in Sri Lanka 
(b) The  GOSL  is  able  to  attain  some  of  the  vision  and  objectives  stated  in  the  CESMA  plan  of 
2004,  though  without  the  burden  of  spending  state  resources  on  the  development  or 
relocating  the  Jaye  Container  Terminal’s  port  related  activities  as  envisaged  in  the  CESMA 
Plan  
(c) Colombo  becoming  a  destination  for  tourism  will  smoothen  out  the  cyclicality  of  current 
tourist  arrival  patterns  and  have  a  beneficial  impact  on  resort  hotels  around  major  tourist 
attractions in Sri Lanka such as the Cultural Triangle.  
(d) Oceanfront land within CBDs of emerging business cities encourages finance, commerce and 
residential living within close proximity to each other. Colombo’s CBD has only fragmented 
undeveloped land parcels remaining with limited views of the ocean on all fronts.  
 
The CPC project therefore creates new land that will generate economic returns to the Government, 
the investor, the city and the country as a whole. 

 
6.2. Identification of Potential Impacts 
 
Although  reclamation  projects  are  generally  regarded  as  an  incremental  asset  to  a  nation,  the 
extended economic impact of a project such as CPC that intends to position Colombo as a regional 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015                             Chapter 6‐ Page 1 
 
 
 

business  and  tourism  hub  needs  to  be  assessed  in  terms  of  social,  economic  and  environmental 
factors.  
The  negative  impacts  of  the  project  cover  several  physical  impacts  e.g.  construction  work  related 
activities, and activities at the project location having impacts on its immediate neighborhoods and 
the  environment.    The  positive  impacts  of  the  project  include  employment  creation,  enhanced 
foreign investment, positive revenue generation to the government, transfer of technology and value 
added contribution to the national economy. Once the physical, socio‐economic and environmental 
impacts  of  the  CPC  are  identified  and  quantified,  the  next  step  of  analysis  is  to  monetize  these 
impacts with economic prices.  
The  application  of  shadow  prices  to  reflect  the  true  economic  values  of  costs  and  benefits  of  the 
project  was  carried  out  using  economic  conversion  factors.  Ideally,  conversion  factors  should  be 
frequently  updated  to  take  into  account  changes  that  might  occur  through  time.  Unfortunately, 
those for Sri Lanka were calculated almost 30 years ago and they are not appropriate to be used for 
Cost‐Benefit‐Analysis  valuations  in  2015  because  significant  changes  have  taken  place  in  the 
economic  structure  of  Sri  Lanka  over  the  past  30  years.  Thus,  the  conversion  factors  developed  by 
the National Planning Department in the 1980s were adjusted to reflect changes in the economy and 
the impact of taxes and subsides.  Several conversion factors were used to convert the market prices 
to economic prices and conversion factors applied for material, labour, technical, and executive level 
occupations were 1.000, 0.755, 0.722 and 0.776 respectively. 
In carrying out the cost‐benefit analysis, the standard methodology of comparing with an alternative 
project location was not considered as CPC is constructed south of the east‐west breakwater of the 
Colombo South Harbour (CSH).  It is a location where there will be a natural accumulation of sand.  It 
is  for  that  reason  that  this  location  had  been  identified  for  this  type  of  development  by  all 
development plans including the CESMA Plan commissioned in 2003‐04, developed around 7 years 
prior to commencement of construction of CSH. This apart, there is no feasible alternative (technical 
and  financial)  to  creating  oceanfront  lands,  with  all  the  related  benefits  pointed  out  earlier,  within 
the Colombo Central Business District.   
The development of the Port City will not create a littoral barrier. The barrier itself is already present 
via  the  east‐west  breakwater  of  the  CSH.  Undertaking  reclamation  in  an  area  where  sand  will 
naturally accumulate with time is a very common practice in coastal engineering and not technically 
challenging.    In  view  of  these  unique  characteristics  of  the  proposed  project  site,  and  site  having 
already  been  identified  for  the  purpose  of  reclamation  for  extension  of  the  Colombo  CBD,  the 
standard methodology of using an alternative project location will not be considered in carrying out 
the extended cost‐ benefit analysis. 
 
6.3. Multiplier effects and Long‐term outcomes 
The proposed CPC has the capacity to contribute significantly to the economic well‐being of the city 
of  Colombo  and  the  Colombo  Metropolitan  Region  (CMR).    The  long‐term  employment  figures 
include jobs at the CPC, jobs generated by multinational firms, jobs supporting local purchases made 
by local and foreign employees at CPC at grocery stores, retail outlets, restaurants, local government 
services, schools, hospitals, etc. and firms that provide services to the CPC companies such as office 
supplies and equipment, utilities, communications and professional services.  
The project has the potential for generating wide range of indirect socio‐economic benefits such as 
attracting  high  profile  FDI  and  thereby  creating  direct  employment  mainly  for  professional  and 
technical occupations in areas such as Information Communication Technology (ICT), banking, fund 
management,  investment  banking,  real  estate,  retail  and  tourism  sub‐sectors.    The  employees  of 
these  occupational  groups  are  expected  to  be  well  paid  and  have  the  capacity  to  create  indirect 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015                             Chapter 6‐ Page 2 
 
 
 

employment in the national economy due to high disposable income.  The proposed project also has 
the  capacity  to  attract  high  profile  FDI  particularly  for  high  value  added  service  sector  investments 
and  headquarters  of  export  manufacturing  establishments.  The  immediate  impact  of  such 
investments would be an increase in GDP and also an increase in foreign exchange earnings.  
In  addition  to  job  creation,  other  long‐term  outcomes  include  fostering  modern  management 
practices  in  various  fields  that  will  upgrade  the  living  standards  of  Colombo.  The  project  will  also 
provide socio‐economic benefits through the utilization of world‐class residential spaces.  Additional 
economic  benefits  could  also  be  realized  through  an  increase  in  higher  paying  jobs  related  to 
international  trade  and  the  movement  of  greater  amounts  of  imports  and  exports  through  the 
Colombo port. 
As  revealed  in  a  recent  study  (World  Bank,  2015),  if  managed  well,  urbanization  can  lead  to 
sustainable  growth  by  increasing  productivity,  allowing  innovation  and  new  ideas  to  emerge.    It 
further  states  that  better  cities  can  help  reduce  vulnerability  to  poverty,  improve  living  conditions, 
and  create  environment  for  more  and  better  paying  jobs.    Income  generation  is  comprised  of 
investment  and  expenditure  by  the  CPC,  the  total  employee  payroll  and  benefits  of  business 
establishments.  However,  these  factors  alone  do  not  represent  the  total  economic  contribution  of 
the project to the national economy.   Economic studies find  that many additional jobs are created 
indirectly  as  a  result  of  the  financial  transactions  of  a  business,  its  suppliers,  customers  and 
employees.  For  example,  Job  creation  during  the  construction  of  the  reclamation  and  protective 
works  of  CPC  would  be  more  than  1700  direct  jobs  per  annum  while  its  impact  on  indirect 
employment would be around 4500. In addition, a further 4500 would be indirectly employed at the 
quarry sites and quarry supply chain during the reclamation.   
 
The  predicted  new  job  creation  would  be  around  15000  per  annum  during  the  1st  10  years  of 
business  operations  (i.e.  with  the  commencement  of  real  estate  developments  on  the  reclaimed 
land). Its impact on indirect employment would be around 22500 per annum in the first 10 years of 
business  operations  based  on  1.0:01.5  ratio  of  indirect  employment.    At  the  end  of  20  years  of 
business operations the total direct employed will be assumed to about 62,000 and indirect about 
30,000 (ratio direct to indirect is 1:0 – 0.5) 

 
6.4. Extended Cost‐Benefit Analysis (CBA) 
 
CPC (the reclamation stage only) is a FDI project without local capital. Local capital would be incurred 
for  the  provision  of  infrastructure,  which  will  be  priced  at  market  rates  giving  a  return  to  utility 
providers. This aspect will be covered in greater detail in the Phase 2 EIA.  
 
Notwithstanding, its impact on the national economy was taken into account by way of valuing cost 
of  factor  services  both  at  market  prices  and  at  shadow  prices.    In  carrying  out  the  extended  CBA, 
firstly,  all  quantifiable  major  costs  and  benefits  of  the  project  were  valued  at  market  prices.  The 
direct benefits of the CPC to the GOSL was defined to include lease/sale income from 63 hectares of 
land allocated to the GOSL to developers, direct and indirect employment in construction work and 
quarry  sites,  income  from  municipal  service  taxes,  direct  and  indirect  employment,  consumption 
effect of foreign employment and backward linkage effect of foreign firms (e.g. purchase of material 
and  other  service  inputs).  The  key  cost  items  considered  in  the  CBA  for  the  reclamation  project 
envisaged  under  this  SEIA  study  include  construction  costs,  opportunity  cost  of  material  (e.g.  sea 
sand), loss of royalty income to the government in providing sea sand and environmental costs.   
 
 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015                             Chapter 6‐ Page 3 
 
 
 

 
6.4.1. Extended Cost‐Benefit‐Analysis for the reclamation stage 
The reclamation stage of CPCDP involves reclaiming sea sand from the Indian Ocean in proximity to 
the Galle Face Green. Reclaimed land amounting to about 173 hectares will be sold/leased to local 
and  foreign  real  estate  developers  for  a  variety  of  activities  such  as  office,  residential,  retail,  and 
leisure activities. The reclamation stage is expected to take approximately three years to complete. 
The Extended Cost‐Benefit‐ Analysis has been based on the financial analysis of overall project, while 
taking into account the environmental and social costs and benefits as a result of the implementation 
of the project. 
The key parameters adopted and key assumptions on costs and benefits made in the calculation for 
the  Cost‐Benefit‐Analysis  are  presented  in  Appendix  3,  and  the  details  of  the  calculation  are 
presented  in  Appendix  4.  Appendix  3  describes  how  the  anticipated  environmental  impacts 
identified  in  Chapter  4,  the  mitigation  measures  suggested  in  Chapter  5,  and  the  monitoring 
measures  recommended  in  Chapter  7  have  been  taken  into  consideration  in  the  calculation 
presented in Appendix 4. 
A broad summary of financial, economic and environmental Costs and Benefits is presented below. 
Table 6.1:  Descriptions of Financial, Economic and Environmental Costs and Benefits. 
Reclamation stage only   Financial  Financial +  Financial + Economic + 
   Economic  Environmental 
Internal Rate of Return‐IRR  %  8.66%  8.9489%  8.861% 
Net Present Value – NPV  USD m  350  3871  3770 
Benefits to Cost Ratio     1.17  1.198  1.18 
 
The underlying analysis behind the above numbers are presented in paragraphs below 
 
6.4.1.1. Benefit streams 
a) Financial benefit streams 
Land sales  
After reclamation, the total land available for sale is approximately 173 hectares. It is estimated that 
land  sales  will  generate  about  USD  6.0  billion  over  20  years,  considering  a  conservative  base  land 
price of USD 2,300 per square metre (Rs. 8 million per perch) and a low land price inflation of 3% per 
annum. Land will be available for sale from the fourth year. 
 
b) Economic benefit streams 
Employment creation  
One of the key benefits of the CPC is its ability to create direct and indirect employment. This would 
lead to further economic growth in Sri Lanka as employee wages will drive consumption and capital 
expenditure, thus benefitting a range of industries.  
During the reclamation stage, it is estimated that approximately 1,800 direct jobs will be created, of 
which  about  80%  will  be  sourced  from  Sri  Lanka.  A  conversion  ratio  of  0.776  has  been  used  when 
considering unskilled labour. 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015                             Chapter 6‐ Page 4 
 
 
 

Construction  of  the  CPC  and  the  creation  of  direct  employment  will  also  lead  to  the  generation  of 
many  indirect  jobs.  CPC  requires  about  2.8  million  m3  of  granite  for  the  construction  of  the 
breakwater  and  protection  work.  This  is  estimated  to  generate  about  3,000  skilled  and  1,500 
unskilled jobs at the independently owned quarry sites in the country. Hence indirect jobs via quarry 
sites are estimated at about 4,500. 
 
 
Consumption effect of foreign employment 
As mentioned above, during reclamation about 20% of the labour force is slated to comprise foreign 
nationals.  They  are  expected  to  spend  at  least  a  third  of  the  wages  (likely  to  be  higher  than  local 
wages) in Sri Lanka and consume a variety of products and services, which is likely to drive growth in 
domestic industries.  
 
c) Environmental benefit streams 
In  the  long  term,  the  construction  of  the  breakwater  of  CPC  will  benefit  the  fishing  industry  in  Sri 
Lanka. According to research, fish temporary avoid the immediate vicinity of construction activities. 
However, on completion these developed structures create potential foraging and spawn habitats for 
fish thus creating a diverse biological community. 
 
6.4.1.2. Cost streams 
a) Financial cost streams 
Construction cost  
The reclamation cost is estimated at USD 1.4 billion.  
Sales and General expenses   
During  the  reclamation  stage  to  effectively  generate  land  sales,  CPCDP  will  undertake  a 
comprehensive  global  marketing  campaign  to  target  key  stakeholders.  Moreover,  skilled  and 
operational personnel will be employed to manage operations. As such, approximately 3.0% of land 
sale revenue is to be allocated for these activities.  
Debt to Equity 
A  debt  to  equity  ratio  of  70:30  is  assumed  for  the  project,  which  is  not  unusual  for  real  estate 
projects 
 
b) Economic costs streams 
Loss of revenue to the government 
The  CPCDP  requires  approximately  65  million  m3  of  sea  sand.  At  present  the  Sri  Lanka  Land 
Reclamation  and  Development  Corporation  provides  sea  sand  for  construction  purposes  for  which 
royalty,  Nation  Building  Tax  (NBT)  and  Value  Added  Tax  (VAT)  are  required  to  be  paid  to  the 
government by the buyer. For CPC, the developer will be utilising its own equipment to dredge the 
sea  sand  during  reclamation  stage,  as  such,  the  government  has  decided  to  forgo  the  applicable 
royalty and taxes. The economic cost to the government of this waiver is estimated at roughly Rs.5.3 
billion.  
Income support to fishermen 
CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015                             Chapter 6‐ Page 5 
 
 
 

There  is  no  fishing  ground  in  the  project  location  and  no  fishing  boats  are  operating  in  the 
reclamation  area. A benefits program  to fishermen will be implemented  by  the government  to the 
fishermen located in the sand borrow areas. For purposes of this analysis, the total amount over the 
3 year reclamation period is assumed at Rs. 1,000 million. (Note this figure may vary as the benefits 
program  will  be  subject  to  review  after  1  year  by  the  GOSL  and  reduce  significantly  assuming  the 
SLLRDC borrow site will be used to mine sand instead of SLPA Site 1). 
As noted earlier, there is no fishing activity in the Port City location, which covers a sea area of 1km. 
The closest fish landing areas are 8‐10km away from the project site. Thus, development activities of 
CPC will not negatively affect the fishing communities living in the Modara/ Mattakkuliya (distance of 
8  kms)  or  Dehiwala‐  Mount  Lavinia  (distance  of  10km)  fish  landing  centers.  The  fishermen  living  in 
both  locations  mostly  (about  64%)  use  mechanised  crafts  for  fishing  and  hence  the  CPC  activities 
would not restrict fishing activities.  
Impact on Hotels 
The impact on tourism industry was also assumed to be not significant as it is very unlikely that the 
activities of the proposed project would significantly impact the business activities of the two hotels 
located near the CPC in the medium to long term. (I.e. Kingsbury and Galadari hotels). However, it is 
plausible  that  during  the  period  when  construction  takes  place  close  to  Chethiya  Road/Kingsbury 
hotel road, there will be a short‐term impact on the hotel. However, these impacts will be mitigated 
and will generate medium to long term benefits in view of the following: 
(a) Foreign consultants to CPC choosing to stay at the nearby two hotels during construction due 
to the close proximity to CPC’s project office and head office in Colombo 
(b) The construction of the linear park close to the Kingsbury hotel as shown in the master plan 
(c) The use of adjacent hotels by investors and consultants who intend on becoming real estate 
developers within CPC and during construction of new developments 
(d) Longer term benefits of Colombo emerging as a business and tourism hub  
 
c) Environmental cost streams 
This  section  identifies  some  of  the  environmental  impacts  caused  by  CPC,  and  where  possible, 
quantified in monetary terms their cost for the inclusion in the extended cost‐benefit analysis.  
 
Archeological and Cultural Aspects  
According  to  the  estimate  prepared  by  the  Underwater  Archeology  Unit  of  the  Department  of 
Archeology  (2012),  the  potential  loss  to  archeological  and  cultural  aspects  is  estimated  at  Rs.1.2 
million for the project.  
Possible accident costs  
Possible  accident  costs  is  estimated  at  Rs.178.5  million  per  year  during  reclamation  based  on  the 
insurance cost of the EPC contractor, considering construction activities as well as transporting rocks 
and other construction material, which may lead to deaths or injuries of workers.  
Mitigation costs  
Environmental mitigation cost is estimated at Rs.63.5 million, which is computed on the basis of Rs 
21.2 mn for each of the first 3 years of construction  
Monitoring costs  
Based  on  the  EMP  monitoring  schedule  and  the  monitoring  test  rates,  the  monitoring  schedule  is 
created  based  on  the  Environmental  Management  Plan,  which  details  parameters  air,  noise, 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015                             Chapter 6‐ Page 6 
 
 
 

vibration,  water  quality,  cultural  heritage,  ecology  and  fish  habitats,  beach  profile,  bathymetry, 
photographic  survey  and  satellite  images.  For  each  parameter,  EMP  has  determined  monitoring 
frequencies.  As  such,  a  total  cost  of  roughly  USD  1.7  million  is  estimated  for  the  duration  of  the 
project. 
 
 
 
v) Aquaculture resources 
As noted earlier, since there are no aquaculture activities going on in the reclamation area or Sand 
extraction areas, the environmental cost of aquaculture is negligible. The biological environment also 
consists of few species, which are not utilized economically. Most regions of the underwater reef are 
silted  and  do  not  provide  a  conducive  environment  for  biota.  Hence  the  environmental  cost  of 
biological resources at the reclamation site is also negligible 
The summary of the above mentioned environmental costs is given below in US$ 
Environmental costs Total (US$ mn)

1. Aquaculture Resources 6.8

2. Archeological and Cultural Aspects (rounded off) 0.0

3. Possible accident costs 3.8

4. Mitigation costs 0.4

5. Monitoring costs 1.7

Total 12.7

 
6.4.2. Extended Cost‐Benefit‐Analysis for the CPC 
The following section details an extended CBA for the CPC under a hypothesis of 20 years of business 
operations.  Compared  to  the  reclamation  stage,  financial  costs  and  benefits  remain  unchanged 
though there is an increase in environmental costs. However a significant improvement in economic 
benefits accrues to Sri Lanka from the overall CPC over its lifetime of 20 plus years.  
The following table summarizes key financials and the descriptions relating to incremental economic 
and environmental costs and benefits (after the reclamation stage). This aspect is subject to further 
study and evaluation under the Phase 2 EIA. 
Table 6.2: Descriptions of Incremental Economic and Environmental Costs and Benefits (after the 
  Reclamation Stage) 
Whole  project  (3  years  of  Financial  Financial +  Financial + 
construction  +  20  years  of  Economic  Economic + 
business operations)     Environmental 
IRR  %  8.7%  15.64%  15.55% 
NPV  USD m  350  2,358  2,347 
Benefits to Cost Ratio     1.17  2.04  2.03 
 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015                             Chapter 6‐ Page 7 
 
 
 

The  analysis  does  not  provide  detailed  estimates  for  possible  revenue  streams  for  more  than  23 
years as it is difficult to predict such revenue sources due to the uncertainty surrounding the various 
parameters affecting both cost and revenue estimates. 
 
 
 
6.4.2.1. Economic benefits  
Employment  creation,  the  effect  of  foreign  employment  and  the  backward  linkage  outcome  of 
foreign firms, value added contribution of local firms and the impact on indirect employment were 
taken into consideration in evaluating the benefit streams of the project. 
CPC  will  continue  to  be  a  significant  job  creator,  with  a  conservative  basis  of  about  2,500 
employment opportunities generated in its first year of business operations and thereafter rising to 
over  65,000  in  the  23rd  year.  As  mentioned,  jobs  will  be  created  in  commercial  activities,  office 
complexes, hotels and in other areas such as leisure, hospitals, schools, convention centres etc. As in 
the reclamation stage, a significant number of indirect employment opportunities will be created. 
The  value  added  contribution  to  the  country  from  businesses  locating  at  the  Port  City  is  another 
significant benefit. Assuming conservative local wage estimates and wage share of total value add at 
22%, the contribution to Sri Lanka from firms in the CPC is likely to rise from about Rs.5.0 billion in 
the first year of business operations to roughly Rs.130 billion per annum, at full year of operations 
(year 23‐25). Moreover, backward integration as a result of foreign companies consuming materials, 
service  facilities  etc.  will  also  contribute  to  the  local  economy  (conservatively  estimated  at  12%  of 
foreign employees wages) 
Benefits  from  the  consumption  effect  of  foreign  workers  will  continue  to  accrue  to  domestic 
industries  and  is  valued  at  almost  Rs.24  billion.  Further  municipal  councils  will  benefit  from  fees 
related  to  annual  rates,  licenses  and  trade  licenses.  The  estimation  of  municipal  service  cost  and 
revenue  are  based  on  existing  cost  data  relating  to  the  main  business  sectors  of  the  Colombo 
Municipal City (CMC). The estimated figures capture only the lower‐bound values. Similarly, with the 
presence  of  high  profile,  multinational  organizations  the  municipal  service  income  could  be  much 
higher. 
Additionally,  there  are  benefits  that  accrue  from  CPC  that  cannot  be  reasonably  quantified.  These 
include benefits from operating a financial hub, boost to industries such as tourism, trade, as well as 
from the creation of a favourable image and positive goodwill of Sri Lanka.  
 
6.4.2.2. Economic costs 
Note that this section is a preliminary analysis to be further studied during the Phase 2 EIA 
i) Operating costs  
Cost  of  municipal  services:  it  is  assumed  that  35%  of  the  municipal  revenue  will  be  utilized  for 
maintenance purposes of the Port City.  
ii) Provision of utilities, waste disposal facilities etc. at boundary.  
The cost of provision of utilities including a waste disposal facility that the government may create to 
cater to the demand of the Port City is under estimation. For the purpose of this cost benefit analysis, 
it  can  be  assumed  in  the  model  that  the  total  cost  for  the  Port  City  is  2.7Km2  x  USD18 
million/Km2=USD48.6 million, and developed in 4 stages: 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015                             Chapter 6‐ Page 8 
 
 
 

Table 6.3: Provision of Utilities, Waste Disposal Facilities etc. at Boundary 
Year  5  10  15  20 
Investment  18.6  10  10  10 
(USD 
million) 
 
 
ii) Provision of road connection at boundary 
According to the “Transport and Traffic Study” prepared by the CECB, certain road enhancement and 
development  projects  that  will  improve  connectivity  and  transport  infrastructure  to  CPC  are  being 
studied. Among these potential road projects, only the following two projects are directly connected 
to  the  Port  City  and  will  perform  as  the  main  entrance  of  the  Port  City.  The  two  projects  will  be 
developed in the fifth and tenth year respectively. 
Table 6.4: Road enhancement and development projects 
Relevant Road Project  Estimated Cost 
1. Elevated Port Access Road to Colombo Port  USD 250 million 

2. Extension of Marine Drive up to Galle Face Roundabout  USD 100 million 

 
6.4.2.3. Others  
Additionally,  there  are  benefits  that  accrue  from  CPC  that  cannot  be  reasonably  quantified.  These 
include benefits from operating a financial hub, boost to industries such as tourism, trade, as well as 
from the creation of a favorable image and positive goodwill of Sri Lanka.  
 
6.5. Overall Assessment 
The post‐war development efforts of the government are aimed at developing Sri Lanka as a dynamic 
business hub using its strategic geographical location effectively. This requires participation of high 
profile foreign investors particularly to promote high value added service sector oriented economic 
activities e.g. financial services, ICT. The spill over benefits of CPC would be skills development and 
transfer of technology and access to foreign markets.  Proposed CPC will be vital in promoting such 
development efforts.  
The  proposed  project  has  the  potential  to  attract  foreign  direct  investment,  create  employment 
opportunities, and to improve living standards in CMR.  Empirical evidence of Thilakaweera (2013) in 
the  context  of  Sri  Lanka  reveals  unidirectional  causality  from  infrastructure  to  FDI  in  promoting 
growth.  This  finding  lends  strong  evidence  in  support  of  CPC  as  a  major  infrastructure  project  in 
promoting growth. The social, economic and environmental benefits described in this analysis reveal 
that the CPC, in addition to the direct service it will provide locally, would contribute substantially to 
the  economic  wellbeing  of  Colombo  and  other  districts  of  CMR.  The  CPC  has  capacity  to  generate 
income,  creates  wealth  and  employment  for  the  citizens  of  the  country,  increase  tax  revenue  and 
advance environmental and social wellbeing of Colombo District.  
 
 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015                             Chapter 6‐ Page 9 
 
 
 

Sri Lanka as a Financial Centre 
The  dominance  of  established  financial  centers  has  been  changing  over  the  past  50  years  with  the 
emergence  of  more  competitive  business  centers  in  Asia.    With  the  distinct  possibility  of  India 
becoming the next economic power house, Sri Lanka seems to be one of the best financial centers 
which could serve investor needs of high growth economies in Asia.  With its long standing links with 
European countries, Sri Lanka could also be a best financial center for servicing investors originating 
from Europe and North America doing business into South Asia 
Sri  Lanka  has  a  distinct  advantage  in  promoting  Colombo  as  a  regional  financial  center.    Proposed 
CPC  would  be  a  strong  positive  factor  in  promoting  such  a  strategy  in  view  of  its  business  friendly 
policies, facilities proposed, connectivity and strategic location. The business center of Colombo also 
offers  several  other  facilities  such  as  sound  legal  framework,  governing  corporate  law  and 
accountancy  standards,  congenial  and  relatively  low  cost  living  conditions,  good  ICT  infrastructure, 
pro‐market policy regime, modern infrastructure, good banking network, educated and skilled labour 
force and low cost of living (e.g. Rent Index 13.87) and (Quality of Life Index 25.55 in 2015).  Its stock 
market operations are being revitalized and the present government is committed to promote both 
local  and  foreign  participation  in  the  stock  market.    The  spin‐off  benefits  of  an  expanding  financial 
services  sector  will  no  doubt  result  in  increased  foreign  direct  investments  and  growth  in  other 
sectors of the national economy.   
 
Opportunity to develop both the Old City and the New City 
As  mentioned  earlier,  Colombo  Port  City  provides  an  opportunity  for  the  old  and  historic  part  of 
Colombo to interface with a modern planned metropolis like no other in developing Southeast Asia.  
As  the  hub  of  the  island’s  commercial  capital,  Fort  has  had  a  long  history  from  the  18th  century 
commencing the time of the Dutch.  That explains the architectural heritage of the city, which must 
be protected for the benefit of future generations.  Some of the key building which deserve special 
mention in old Fort are Old Dutch Hospital, Cargill’s and Millers Buildings, Victoria arcade and Grand 
Orient  Hotel  (GOH,  1775),  Bristol  Building,  Gaffoor  Building,  Times  Building,  Old  Fort  Light  House, 
Clock Tower, General Post Office, Queen’s House, Bank of Ceylon Building, and YMCA Building. They 
should be renovated while keeping the old look intact. At present, the preservation of these iconic 
buildings  is  faced  with  a  serious  threat  of  high  demand  pressure  for  commercial  space.    The 
emergence of high‐rise buildings in and around Fort has already damaged the majestic appearance of 
the old Fort of Colombo and new business activities does not appear to be spreading to outer skirts 
of the main business center over the past fifty years.  
In  spite  of  various  efforts  by  successive  governments  to  shift  some  of  the  government  institutions 
and commercial centers from the main business center, Fort and adjoining areas continue to attract 
investors rather than outer lands of the Colombo City.  This is due to cluster based business growth 
particularly with respect to urban growth centers.  The latest addition to this trend is the emergence 
of  port  cities.    These  growth  centers  are  characterized  by  a  bundle  of  most  modern  services 
demanded  by  high  profile  investors.    On  one  hand,  the  proposed  CPC  would  cater  to  the  investor 
needs of the emerging business world and on the other hand, it would provide an opportunity for the 
government to protect the old city of Colombo for the benefit of future generations.  It would also 
offer  wide  range  of  economic  benefits  to  the  country  by  way  of  enhancing  investor  confidence, 
attracting  foreign  direct  investment,  creation  of  high  quality  employment,  and  a  range  of  other 
economic benefits through backward and forward linkages.  The new construction provides an ideal 
opportunity for the City of Colombo to diversify its operations through multiple sources of business 
activities. 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015                             Chapter 6‐ Page 
10 
 
 
 

In summary, the cost‐benefit analysis using sectorial conversion factors and environmental costs for 
the same period revealed that CPC project is a worthwhile investment from both an economic and an 
environmental  point  of  view.      This  is  a  project  that  has  potential  for  offering  long‐term  economic 
benefits  for  Sri  Lanka.  The  project  has  capacity  to  attract  FDI,  promote  high  value  added  products 
and  services,  transfer  of  technology,  integration  with  global  markets  and  creation  of  high  quality 
employment opportunities, particularly in the services sector.  
 
 
 
 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015                             Chapter 6‐ Page 
11 
 
 
 

6.6. Summary CBA  
Table 6.5: Summary of the cost benefit analysis 

 
 
 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015                             Chapter 6‐ Page 12 
 
 
 

6.7. Sensitivity Analysis ‐ NPV 
6.7.1. Reclamation stage 
Table 6.6: Sensitivity analysis of Reclamation stage 

Description   NPV at 6.5%  NPV at 8.0%  NPV at 10.0% 


Discount rate (USD m)  Discount rate  Discount rate 
Fin.   Fi+Ec  Fi+Ec+Env  (USD m)  (USD m) 
 

Fin.   Fi+Ec  Fi+Ec+Env  Fin.   Fi+Ec  Fi+Ec+Env 


   

1. Base case   350   387   377   91   128   117   -153   -118   -128  


     

2.  Reduction  234   272   261   -5   32   22   -228   -193   -203  


in initial land       

price by 5% 

3.  153   191   180   -91   -54   -65   -319   -283   -293  
Construction       

cost 
increase  by 
10% 

4.  Cross  37   75   64   -187   -150   -160   -394   -358   -368  


sensitivity       

(scenarios  2 
and  3 
combined) 

  
 
 
 
 
 
 
 
 
 
 
 
 
 
 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015                             Chapter 6‐ Page 
13 
 
 
 

6.7.2. Reclamation and 20 years of business operations 
Table 6.7: Sensitivity analysis of Reclamation & Operational stage 

Description   NPV at 6.5%  NPV at 8.0%  NPV at 10.0% 


Discount rate (USD m)  Discount rate  Discount rate 
Fin.   Fi+Ec  Fi+Ec+Env  (USD m)  (USD m) 
 

Fin.   Fi+Ec  Fi+Ec+Env  Fin.   Fi+Ec  Fi+Ec+Env 


   

1. Base case   350   2,358   2,347   91   1,660   1,650   -153   986   976  


     

2.  Reduction  234   2,242   2,231   -5   1,564   1,554   -228   911   901  
in initial land       

price by 5% 

3.  153   2,161   2,151   -91   1,478   1,468   -319   821   811  
Construction       

cost 
increase  by 
10% 

4.  Cross  37   2,046   2,035   -187   1,382   1,372   -394   745   736  
sensitivity       

(scenarios  2 
and  3 
combined) 

 
 
 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015                             Chapter 6‐ Page 
14 
 
 
CHAPTER 8 
CONCLUSIONS & RECOMMENDATIONS 
 
 
This  Supplementary  Environmental  Impact  Assessment  SEIA  is  based  on  Terms  of  Reference 
issued  by  the  Department  of  Coast  Conservation  and  Coastal  Resources  Management  to  the 
Project  Proponent,  the  Ministry  of  Urban  Development,  Water  Supply  &  Drainage  on  30th 
August  2015.  Upon  the  UDA  being  gazetted  under  the  Ministry  of  Megapolis  &  Western 
Development, this Ministry was designated as the Project Proponent.  
 
The  investor  in  Port  City,  China  Communications  &  Construction  Company  (CCCC),  is  a  public 
listed  company  in  Hong  Kong  and  among  the  world’s  largest  construction  and  real  estate 
companies  with  assets  of  over  $100  billion.  The  total  foreign  direct  investment  (FDI)  in  the 
reclamation stage of the Port City covered under this SEIA is envisaged at around $1400 million, 
the largest ever single FDI approved by the BOI to date. The financial investment in the project 
therefore has no Government guarantees.  
The  project  commenced  construction  on  16th  September  2014  at  the  request  of  GOSL  on  the 
basis  mentioned  in  this  report  to  coincide  with  the  State  visit  of  the  President  of  China  and 
continued construction until the Project Company was informed in writing on 6th March 2015 to 
temporarily  suspend  construction.  Since  a  sudden  suspension  of  any  coastal  land  reclamation 
project  is  unsafe  and  ill‐advised  prior  to  protecting  what  has  been  constructed,  the  Project 
Company  made  a  written  request  to  the  GOSL  to  carry  out  protection  in  connection  with  the 
partially constructed breakwater to ensure that works completed will not be destroyed due to 
natural causes during the period of suspension, damage is not caused to the Fibre Optic Cable 
laid  by  Sri  Lanka  Telecom  in  proximity  to  the  breakwater  by  loose  rock  and  material  is  not 
washed away due to monsoon activity and transported to the surrounding areas – especially the 
Galle  Face  beach  promenade  and  the  Baire  Lake  outlet.  The  Project  Company  received  the 
required permission to undertake protective works via a decision of the Cabinet of Ministers and 
has been carrying out such works throughout the suspension period.  
 
The  Project  Company  has  hired  world‐renowned  international  consultants  working  together 
with local specialists to advise on various aspects connected to the development. International 
consultants include: Atkins of UK for Master plan review; Aecom of USA for utility design, road 
design and landscaping; Sweco of Sweden for overall master planning; Jones Lang LaSalle (JLL) 
and  CB  Richard  Ellis  (CBRE)  of  UK  for  financial  and  marketing  pre‐feasibility  and  CDR 
International of The Netherlands for technical review of designs of the EPC contractor. A highly 
competent team of technical consultants assisted the Lead Consultant to this SEIA study, CECB, 
in preparing this SEIA report. They included LHI Coast & Water, CDR, University of Moratuwa, 
GSMB Technical Services and NARA. 
This  SEIA  report  draws  the  conclusion  that  due  to  the  construction  of  the  Colombo  South 
Harbour, the incremental environmental impacts from the construction of Colombo Port City is 
minimal/negligible at the reclamation site and the coastal zone to the North and South of the 
site. The Project will also in not contribute to coastal erosion. For erosion to occur the proposed 
project must create an obstruction  to the longshore drift or  must transfer sediment from  the 
dynamic  coastal  zone  to  deep  waters.  Neither  of  these  occurs  with  the  Port  City  Project  as 
demonstrated  in  numerous  modelling  studies  carried  out  as  described  above  for  both  the 
Colombo South Port EIA, the Port City EIA of 2011 and this SEIA 
 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015 Chapter 8‐ Page 1


During  construction  and  post  construction  period  of  the  South  Port  there  was  no  overall 
negative  impact  on  the  coastline  or  on  the  natural  ecosystems.  Throughout  the  construction 
process including dredging and reclamation, a wide range of parameters including “continuous” 
water  quality  measurements  were  made.  On  more  than  95%  of  the  occasions    (continuous 
measurements  over  4  years)  the  total  suspended  sediment  levels  at  the  reference  point  at 
Kelani  River  mouth  was  greater  than  at  the  project  site  (3  locations),  indicating  the  natural 
turbidity  from  turbulent  river  flow  was  more  significant  than  that  of  dredging.  Contrary  to 
popular  belief  dredging  did  not  cause  serious  impacts  and  natural  ecosystems  such  as  reef 
systems will continue to be affected by sediment laden river turbulence.  
 
Port  City  breakwater  will  have  a  crest  level  of  +4.0  m  above  mean  sea  level  (low  crest 
breakwater allowing overtopping) in comparison to the crest level of +10.3 m of the Colombo 
South Port Project, leading to a significantly less quarry material requirement for Colombo Port 
City. Colombo South Harbour used around 2 mn m3 or 57% more than the total requirement of 
3.5 mn in quarry material required for Port City. The quarry material already at site is around 
700,000  m3 and hence the additional amount required to complete Port City is 2.83 mn m3.   
 
The Port City Project covered under this SEIA comprises of the following elements of work: (a) 
sand dredging and transport (b) filling for reclamation and ground treatment to reclamation, (c) 
construction  breakwater  and  other  related  structures  (edge  revetments/seawalls,  artificial 
beaches,  groyne  at  Beria  outfall,  inner  breakwater,  marina  basin,  and  lagoon  and  canal.  The 
protection of the environment has been achieved by measures starting from the review of the 
location of the selected site, to a detailed study of appropriate engineering design solutions, and 
to the deployment of environmentally friendly methods of construction.  

The scale of reclamation for 269ha of land area is considered optimal for the following reasons: 
 
(a) The economic justification for the scale of the project has been described earlier in this 
SEIA report. This includes some theory and practical reasons explaining the case for the 
Colombo Central Business District (CBD) being expanded to encourage waterfront living 
and  working  within  a  systematically  master  planned  area  with  the  aim  of  positioning 
Colombo as the most liveable city in South Asia. When developed, Colombo Port City is 
expected  to  evolve  as  a  regional  financial  centre,  shopping  and  entertainment  district 
and a tourist attraction that will potentially double average stay in Colombo by a typical 
tourist  and  attract  at  least  500,000  new  tourists  to  Colombo.  Colombo  Port  City  is 
therefore expected to smoothen out the cyclical nature of tourist arrivals to Sri Lanka 
thereby having far reaching economic benefits to the regions as well.  
(b) The  footprint  of  the  reclamation  for  269ha  is  within  the  shadow  created  by  the 
breakwater of the Colombo South Port while being able to maximize the development 
potential  of  the  strategic  site.  The  overall  concept  master  plan  for  Colombo  Port  City 
corresponds  to  plans  prepared  by  CESMA  International  Pte  Ltd  of  Singapore  in  2004 
under the Western Region Megapolis Regional Structure Plan in terms of location, scale 
and amount of land to be released annually for development, based on a 25 year time 
horizon for development of Port City. 
(c) Due to the long term nature of the project where land will be released gradually on a 
phased  basis  at  market  prices  jointly  agreed  with  the  UDA/GOSL  (this  is  stated  in  the 
Project  Agreement)  and  the  fact  that  Colombo  Port  City  is  expected  to  attract  new 
demand, the creation of new land through this development is not expected to have an 
adverse impact on property prices at an aggregate level. In fact, with Port City expected 
to  attract  new  residents  to  Sri  Lanka  such  as  entrepreneurs,  fund  managers,  retirees 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015 Chapter 8‐ Page 2


and the Diaspora, at the aggregate level, property prices are expected to increase over 
time.  
(d) The  offshore  breakwater  is  necessary  to  protect  the  reclaimed  land.  The  scale  and 
therefore construction cost of such a breakwater will not be reduced even if the area of 
reclamation  is  reduced.  As  such,  the  financial  investment  in  the  project  may  not  be 
justifiable  should  the  scale  of  reclamation  be  reduced,  particularly  in  considering  the 
large area of 96 ha (or 36%) of the reclaimed area allocated as common areas for use by 
the  public  as  roads,  parks  etc.  This  does  not  include  around  20ha  of  artificial  public 
beaches  of  30‐80m  in  depth  being  created,  which  increases  the  public  spaces  to  over 
40%.    Furthermore,  23%  of  the  reclaimed  area  is  allocated  to  the  Government  as 
marketable  land,  leaving  the  Project  Company  with  41%  of  the  land  reclaimed  for  its 
own financial returns. 
(e) From  the  submission  of  the  initial  proposal  by  the  investor  in  April  2011,  though  the 
reclamation area proposed has increased from 200ha to 269 ha for reasons mentioned 
above, the area allocated to the Project Company has actually decreased to 110 ha as 
shown in the chart below. This is a consequence of the extensive negotiations over 2 ½ 
years by GOLS’ SCARC and the TEC.  It will be noted from the chart below that 92% of 
the 36 ha increase from 233 to 269 ha is on account of increase in public spaces. 
 
Land distribution  Project Company    Project Company  Negotiated Position       SEIA of 2015 
Proposal*   Proposal  
   Apr 2011  Oct 2012        Sept 2014**       
   Land (ha)  %  Land (ha)  %  Land (ha)  %  Land (ha)  % 
Land allocated to 
project company  120  60%  120  52%  108  46%  110  41% 
Land to 
SLPA/UDA/Government        50  21%  62  27%  63  23% 
Public areas (excluding 
beach)  80  40%  63  27%  63  27%  96  36% 
TOTAL RECLAIMED 
AREA  200  100%  233  100%  233  100%  269  100% 
_________________ 
Notes:  
* Joint venture option proposed, though the Government would have to fund its portion of the equity in cash from 
State resources. 
** The Project Agreement stipulates a reclaimed area of no less than 233 ha and marketable area of no less than 
170 ha. Formula for land allocation between the GOSL and Project Company in case marketable land exceeds 170 
ha and applied in allocation given in this SEIA 
 

The  above  mentioned  aspects  provide  the  basis  for  expanding  the  reclaimed  area  from  what 
was proposed in the approved EIA (2011) and Addendum to the EIA (2013), though within the 
geometric framework of the original conceptual designs. That is, given the above constraints of 
geometric similarity and the specified physical boundaries of the Colombo South breakwater, a 
suitable  size  for  the  project  may  be  selected,  subject  to  confirmation  from  design  studies 
supported  by  comprehensive  modelling.  As  elaborated  elsewhere,  such  modelling  has  been 
carried  out  for  the  expanded  area,  including  for  the  Beira  Lake  outfall.  Therefore,  there  are 
strong justifications for the expansion and modification to the original design for Colombo Port 
City.  
This SEIA also evaluated the cost‐benefit of this project and concluded that significant economic 
benefits  can  be  generated  from  the  project,  particularly  during  the  second  phase  of  benefits 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015 Chapter 8‐ Page 3


from the construction of the built environment of Port City. Through the analysis presented the 
following conclusions were also reached: 
 The  extraction  of  rock  material  required  to  complete  the  Port  City  Project  constitutes 
44%  of  the  reserves  of  11  quarries  surveyed  for  this  SEIA  and  that  the  11  quarries 
constituted  only  9%  of  the  number  of  quarries  in  Colombo  and  Gampaha  districts. 
Moreover, may quarries are idle today and the 2.83 mn  m3 of quarry material required 
would  not  have  an  impact  on  supply  or  price  impact  to  the  construction  industry  at 
large. 
 With  the  mitigatory  measure  of  making  available  the  SLLRDC  borrow  site  for  sand 
dredging, the 65 mn m3 of sand required to complete Port City consumes only 17% of 
the dredge‐able/available sand volume available in the borrow areas as designated by 
GSMB. This, combined with the fact that the area to be dredged will only be 15‐25% of 
the  dredge‐able  area  of  200    km2,  avoiding  environmentally  sensitive  fishing  grounds 
and routes is feasible 
 There is negligible ecological impact at the reclamation site. Sand dredging is expected 
cause  only  local  and  temporary  impacts  on  the  biological  environment  due  to  the 
removal  of  benthic  fauna  and  increasing  turbidity  as  a  result  of  an  increase  in 
suspended particles in water columns.  
 The aspects of aesthetics in relation to the project is adequately covered in relation to 
the integration of the old city (particularly the Presidential Secretariat building) and the 
new and the creation of around 45 ha of park lands, including a central Park around 4 ½ 
times  the  size  of  Galle  Face  Green  for  public  use.  The  positioning  of  the  Presidential 
Secretariat  building  facing  the  central  axis  of  the  concept  mater‐plan  Port  City  is  in 
keeping with the concept proposal prepared by the UDA and presented to SLPA in 2010, 
when the project was contemplated as a public investment. 
 The marina, the park, the artificial beaches, the lagoon and canal (for swimming, water 
sports and relaxation), the attraction of waterfront living are the key aspects that will 
underpin the positioning of Port City as an attractive location to “live, work and play” 
and the marketing strategy that will attract local and foreign developers to develop the 
built  environment  according  to  the  concept  master  plan  submitted  to  the  UDA  for 
preliminary planning clearance.   
 Accordingly,  Colombo  Port  City  will  provide  facilities  and  amenities  ranging  from 
commercial  spaces,  recreational  areas,  cultural  facilities,  water  sports  and  park  areas 
that is not available to the residential and transient population of Colombo City. 
 Hydrodynamics  in  the  project  area  will  vary  marginally  with  the  development  of  Port 
City.  But  the  increase  of  current  speed  is  not  significant.  Also  no  significant  current 
increase  is  observed  in  the  navigation  channel  area  and  existing  port  premises  and 
therefore no impact on the channel. 
 Reasonable  velocities  exist  throughout  the  year  covering  different  wave  &  wind 
combinations  in  the  area  between  the  reclamation  and  offshore  breakwater  and 
therefore no stagnation will occur.  
 Proposed port city layout provides required calmness level inside the marina and water 
area for almost all dominant wave directions.  
 No significant morphological changes can be seen in seabed with the new development 
at the reclamation site. 
 Although  there  is  a  tendency  of  spreading  the  plume  in  southern  and  northern 
directions  away  from  the  site  boundary  during  the  monsoon  periods,  sediment 
concentration is below  the value of 4mg/l.  Therefore, increase in suspended sediment 
level  during  bottom  dumping  operations  is  negligible  and  therefore  no  severe  impact 
occurs due to bottom dumping operations. 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015 Chapter 8‐ Page 4


 Maximum  suspended  sediment  concentration  for  rainbow  dumping  is  obtained  as 
7.73mg/l.  Therefore,  spreading  of  suspended  sediment  plume  away  from  the  site 
boundary during rainbow dumping process is also negligible. Furthermore, deposition of 
the  floated  material  is  also  observed  within  the  site  periphery  and  hence  there  is  not 
impact to the surrounding area due to rainbow dumping 
 Since  the  suspended  sediment  concentration  due  to  rainbow  dumping  operations  are 
within the ambient TSS level, impact to the environment is negligible.  
 Continuous  water  quality  measurements  over  4  years  during  construction  and  post 
construction  of  Colombo  South  Port  revealed  that  effects  due  to  natural  turbidity  of 
Kelani River was more significant than that of the construction of the new port.  
 Therefore the incremental environmental impact from Port City evaluated in this SEIA is 
minimal due to the construction of the Colombo South Port.  
 
The approach to the SEIA and engineering process has been one of mitigation through planning 
and design, whereby some of the potential environmental impacts have been reduced as far as 
practicable  through  an  iterative  planning  and  design  process.  This  has  decreased  the  overall 
impacts materially.  
 
The  SEIA  study  has  been  supported  by  engineering  design  investigations,  which  included  a 
plethora of field studies as well as mathematical and physical modelling and simulation studies 
described  in  various  chapters  of  this  report  and  summarized  in  the  Executive  Summary.  In 
addition,  detailed  environmental  studies  relating  to  marine  ecology  and  fisheries,  underwater 
and  built  cultural  heritage,  socio  economics,  extended  cost  benefit  analysis,  noise  and 
vibrations  were  carried  out  to  obtain  information  on  the  existing  environment.  Thereafter, 
impacts  arising  from  the  Phase  1  of  the  Port  City  project  covered  under  this  SEIA  were  duly 
assessed  taking  into  account  the  effects  of  the  proposed  development  within  the  identified 
location.  
 
As mentioned at the outset of this study, as stipulated in the Project Agreement entered into 
between the GOSL and the Project Company, the EIA process for Port City Project has 2 phases. 
This  SEIA  is  a  continuation  of  the  Phase  1  environmental  assessment  of  the  reclamation, 
material extraction for reclamation and protective and related works. The Phase 2 EIA for the 
construction  of  the  buildings  and  infrastructure  of  the  Port  City,  including  traffic  impact 
assessment,  will  commence  very  shortly.  The  phase  2  EIA  study  will  be  based  on  the  concept 
master plan and infrastructure requirements submitted to the UDA (and described in this SEIA).  
 
The  Monitoring  Plans  have  been  divided  into  those  for  Impact  Confirmation  Monitoring  and 
Compliance Monitoring. Note that the Colombo Port City Project as constructed over a 6 month 
period ending March 2015 and the Monitoring Plan presented herein has been refined based on 
extensive  monitoring  data  obtained  during  construction.  The  recommended  functions  of  the 
Environmental Monitoring Committee (EMC) take cognizance of the importance of stakeholder 
participation  in  both  Impact  Confirmation  and  Compliance  Monitoring.  It  is  intended  that  the 
Project Company and the GOSL/Ministry of Megapolis & Western Development/UDA will enter 
into  an  understanding  on  mitigation  measures  and  resource  requirements  for  implementing 
such measures including the contents of the EMP.  
 
In conclusion, it should be emphasized that from the initial stages where the Port City project 
was  contemplated  as  a  GOSL/SLPA  funded  public  investment  project  and  later  as  a  private 
investment  via  CCCC,  during  the  period  leading  to  the  signing  the  Project  Agreement  and  in 
terms  of  the  Agreement  itself,  the  responsibility  for  carrying  out  the  required  environmental 
studies and obtaining the required permits and consents in relation to all environmental studies 
CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015 Chapter 8‐ Page 5


including this SEIA has  been the responsibility of the GOSL/SLPA, and, in terms of Clause 3 of 
the  GOSL  Agreement  and  the  Project  Agreement  annexed  thereto,  all  rights,  obligations  and 
liabilities  of  the  SLPA  are  deemed  as  rights,  obligations  and  liabilities  of  the  GOSL.  During  the 
course  of  this  year,  the  GOSL  has  decided  that  the  Ministry  of  Megapolis  &  Western 
Development  should  be  assigned  the  responsibility  of  securing  required  environmental 
consents, pending necessary legal and legislative lacuna impacting the UDA from stepping into 
the  role  of  the  SLPA  being  addressed  with  the  assistance  and  recommendation  of  the  Hon. 
Attorney General.  
In  light  of  the  above,  the  EIA  team  has  highlighted  below  several  concerns  and 
recommendations that would need careful consideration and execution: 
1. Securing the cooperation and buy‐in of the impacted fishing communities: Currently, 
considerable  publicity  has  been  given  regarding  the  concerns  of  fishermen  on  the 
impact of sand extraction from the designated borrow areas on fisheries. As such, it is 
vitally important that the fisher community is educated on the aspects of the project, 
the  implementation  plan,  safety  and  mitigation  measures  taken  and  specifics  of  the 
income  support  and  benefits  program  for  which  funds  are  to  be  allocated  to  the 
Ministry of Megapolis as recommended in this SEIA study. It is therefore recommended 
that  the  relevant  Government  agencies  carefully  program  the  implementation  of  the 
benefits program in consultation with the community stakeholders. 
 
2. Mitigation measures for sand borrowing: The Colombo Port City Project would require 
65mn m3 of sand to be extracted over a period of up to 36 months from the 2 borrow 
areas  assigned  by  GSMB  for  the  purpose  of  this  project.  The  length  of  the  dredging 
period is also dictated by the speed of construction of the breakwater, which has to be 
slowed  down  during  monsoon  periods.  Of  the  borrow  areas,  Site  1,  nearer  to  the 
shoreline,  is  a  fishing  area  comprising  spawning  grounds.  For  this  reason,  the  SEIA 
stipulates  that  only  up  to  30%  of  the  total  sand  requirement  of  65  mn  m3  should  be 
obtained from this site. This EIA recommends that the suggested mitigation measure of 
obtaining sand from the borrow area assigned to SLLRDC be pursued. Assuming that the 
availability of the required quantity of sand is confirmed via exploration studies at the 
SLLRDC  borrow  area,  this  site  be  used  to  dredge  sand  in  preference  to  Site  1  that  is 
nearer to the shoreline.  
 
3. Shore Profile Survey: Near‐shore profile survey is proposed at 500m‐line spacing from 
MHWL  to  16m  water  depth  of  the  coastal  stretch  from  10km  to  35km  north  up  to 
Negombo lagoon mouth and from 10km to 15km south up to Mount Lavinia headland. 
The survey data will be used to monitor the shore profiles after the construction of port 
city.  Therefore,  it  is  recommended  to  commence  beach  monitoring  as  soon  as 
reclamation  works  commences  to  assess  whether  there  will  be  a  significant  change 
occurring (even though it is very unlikely for reasons mentioned in this report) due to 
the  construction  activities  relating  to  reclamation  and  breakwater  construction.  It  is 
noted that beach profiles taken in the above manner as part of the EMP at prescribed 
intervals prior to suspension of the project shows no changes to the near‐shore profile. 
commencement  (this  has  been  done)  and  thereafter  monitoring  be  carried  out  at 
prescribed time intervals.  
 
 
 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015 Chapter 8‐ Page 6


 
The SEIA study has considered the following key elements 
(a) The existing environment 
(b) The significance and the contribution of the project towards national development and 
the potential evolution of Colombo a financial, commercial and tourism hub 
(c) The potential environmental impacts including their magnitude and significance caused 
by the proposed development 
(d) The  ability  to  eliminate  and/or  minimize  the  identified  negative  impacts  effectively 
through both the “mitigation by design” process and the identified mitigatory measures  
On the basis of the detailed analyses of the above aspects presented in this study and on the 
assumption that the recommendations for the mitigation of identified impacts are adopted and 
adequately  implemented,  it  is  concluded  that  there  is  no  insurmountable  environmental 
impacts associated with the construction of the reclamation and related protective works and 
the extraction of required material for the said construction – sea sand and quarry material. 
 

CECB ‐ SEIA Report – Proposed Colombo Port City Development Project‐ December 2015 Chapter 8‐ Page 7

You might also like