1 Rawmill Feeding Foundation 11 days Sun 6/18/23 Fri 6/30/23
2 P.C Inspection and Casting 1 day Sun 6/18/23 Sun 6/18/23
3 Bottom and top Reinforcement Erection
5 days Mon 6/19/23Fri 6/23/23 2
4 Reinforcement Inspection 1 day Mon 6/26/23Mon 6/26/23 3
5 Shuttering Erection 2 days Tue 6/27/23 Wed 6/28/23 4
6 Formwork Inspection 1 day Thu 6/29/23 Thu 6/29/23 5
7 R.C Casting 1 day Fri 6/30/23 Fri 6/30/23 6