ID Task Task Name Duration Start Finish Predecessors
Jun 11, '23 Jun 18, '23 Jun 25, '23
Mode F S S M T W T F S S M T W T F S S 1 Rawmill Feeding Foundation 11 days Sun 6/18/23 Fri 6/30/23 2 P.C Inspection and Casting 1 day Sun 6/18/23 Sun 6/18/23 3 Bottom and top Reinforcement Erection 5 days Mon 6/19/23Fri 6/23/23 2 4 Reinforcement Inspection 1 day Mon 6/26/23Mon 6/26/23 3 5 Shuttering Erection 2 days Tue 6/27/23 Wed 6/28/23 4 6 Formwork Inspection 1 day Thu 6/29/23 Thu 6/29/23 5 7 R.C Casting 1 day Fri 6/30/23 Fri 6/30/23 6