You are on page 1of 21

B13211 NIL 09.02.2021 09.02.

2021 FOUR LANING OF END OF PANDOH BYPASS TO TAKOLI


SECTION OF NH21 FROM KM 221.305 TO KM 242.000 IN
PROJECT:
THE STATE OF HIMACHAL PRADESH UNDER NHDP
S.Rajesh 10.02.2021
PHASE IV-B ON HYBRID ANNUITY MODE
CLIENT:

NATIONAL HIGHWAY AUTHORITY OF INDIA

CONCESSIONAIRE:
SHAPOORJI PALLONJI PANDOH TAKOLI HIGHWAY
PRIVATE LIMITED

CONTRACTOR:
SHAPOORJI PALLONJI INFRASTRUCTURE CAPITAL
COMPANY PVT. LIMITED

PROOF CONSULTANT:
GEOCONSULT INDIA PRIVATE LIMITED

CONSULTANT:
AVANT-GARDE SYSTEMS AND CONTROLS PRIVATE
LIMITED

VENDOR:

VIVID ELECTROMECH PVT. LTD.

PACKAGE NAME: LT SWITCHGEAR

PANEL DRAWINGS AND DOCUMENTS –T2-02 P2 PSS


DOCUMENT TITLE:
PCC

PROJECT DOCUMENT NO: B13211-SP-LTS-VEL-T202P2-GEN-0001

VENDOR DOCUMENT NO. VEPL- LTS-VEL-T202P2-GEN-0001


FOUR LANING OF END OF PANDOH BYPASS TO
TAKOLI SECTION OF NH21 FROM KM 221.305 TO
KM 242.000 IN THE STATE OF HIMACHAL
PRADESH UNDER NHDP PHASE IV-B ON HYBRID
ANNUITY MODE VIVID ELECTROMECH
SHAPOORJI PALLONJI PVT. LTD.
INFRASTRUCTURE
PANEL DRAWINGS AND DOCUMENTS –T2-02 P2 Rev : R5
CAPITAL COMPANY Date : 19-JAN-21
PSS PCC
PVT. LIMITED
Cover Page
Doc. No: B13211-SP-LTS-VEL-T202P2-GEN-0001
Page 2 of 2

ISSUED FOR
INFORMATION APPROVAL
INQUIRY ORDER
CONSTRUCTION AS BUILT
REVISION STATUS:
PREPARED REVIEWED APPROVED
REV. NAME
NAME DATE DATE NAME DATE
MECH ELEC CIVIL C&I SES
R0 SHAHID 24-05-2020 ME 24-05-2020 AP 24-05-2020

R1 SHAHID 26-05-2020 ME 26-05-2020 AP 26-05-2020

R2 SHAHID 14-07-2020 ME 14-07-2020 AP 14-07-2020

R3 SHAHID 22-07-2020 ME 22-07-2020 AP 22-07-2020

R4 SHAHID 31-07-2020 ME 31-07-2020 AP 31-07-2020

R5 SHAHID 19-01-2021 ME 19-01-2021 AP 19-01-2021

REVISION SUMMARY SHEET

REV. DETAILS / DESCRIPTION DATE

R0 SUBMISSION FOR APPROVAL 24-05-2020

R1 AS PER CMNT. (18.06.2020) 26-05-2020

R2 AS PER CMNT. (04-07-2020) 14-07-2020

R3 AS PER CMNT. (20-07-2020) 22-07-2020

R4 AS PER CMNT. (29.07.2020) 31-07-2020

R5 AS BUILT DRAWING 19-01-2021